the problem
play

The Problem The Mayo River Flood Control project was initiated by - PowerPoint PPT Presentation

The Problem The Mayo River Flood Control project was initiated by Yukon Government Community Services in response to significant winter ice-related flooding on the lower Mayo River affecting the Village of Mayo and Yukon Energys operations,


  1. The Problem The Mayo River Flood Control project was initiated by Yukon Government Community Services in response to significant winter ice-related flooding on the lower Mayo River affecting the Village of Mayo and Yukon Energy’s operations, between 2010 and 2014.  Private and public properties affected by flooding (private residences, Village of Mayo infrastructures, YEC diesel plant, Emergency ice removal roads and trails, etc.)  Significant capital costs to Yukon Government to perform emergency flood relief efforts including extensive ice removal  Reduction in winter generation at Yukon Energy’s Mayo Generating Station over at least 4 winters  Constant community concerns over winter months and lack of trust amongst stakeholders creating stress within the community Emergency ice removal Mayo River Flood Control Project 2017 Yukon Engineering Excellence Award

  2. Approach to the Solution During the preliminary design phase the causes of flooding were analyzed and long term objectives were defined. Numerous studies were completed which include hydraulic/ice studies, geomorphology analysis, sediment transport analysis, geotechnical assessment, etc. The project goal was to reduce or eliminate flooding in the Village of Mayo, while minimizing human intervention and at the same time providing the opportunity to maximize hydroelectric generation during the winter. Eroding banks 1. Develop and implement a winter operation protocol 2. Increase hydraulic capacity of the lower Mayo River 3. Provide bank stabilization 4. Permanently establish overflow diversion channels Shallow and not well defined channel Existing diversion channel Mayo River Flood Control Project 2017 Yukon Engineering Excellence Award

  3. Flow Management A flow management committee was establish in 2014 by YEC and CS-IDB to collect and analyze data from a monitoring and instrumentation program, as well as to develop flow management procedures to minimize ice-related Ice cover upstream of bridge flooding issues. The goals of flow management are: 1. To promote the formation of an ice cover on the river by reduce frazil ice generation which tend to cause restrictions along the river 2. To minimize daily and hourly flow rate fluctuations to minimize frazil ice transport downriver and to avoid breaking or collapsing the ice cover Frazil ice floating downriver 496 26 Slow flow rate increase following Uncontrolled period freeze-up – minimize flow variations 24 prior to freeze-up Flow cut-back during freeze-up Complete ice cover by late January 495 (and increasing water levels) 22 Elevation (m ASL) 20 Flow (m 3 /s) 494 18 16 493 14 12 492 10 Silver Trail Bridge water levels Mayo River flows 8 491 6 16-Nov-16 23-Nov-16 30-Nov-16 7-Dec-16 14-Dec-16 21-Dec-16 28-Dec-16 4-Jan-17 11-Jan-17 18-Jan-17 25-Jan-17 Mayo River Flood Control Project 2017 Yukon Engineering Excellence Award

  4. Construction of Permanent Works Culvert at salmon channel crossing Design and construction of permanent flood mitigation works was completed in 2016 for the most part. • Permanent access roads along the river to provide access for construction and future Bank protection maintenance. Six culverts were placed along the roads to cross two side channels use as salmon rearing habitat • Sediment removal (estimated volume 6,850 m³) on the lower Mayo River, with access to the Sediment removal Access road built with river gravel different zones via temporary causeways Construction was completed over a 6 week period with a very tight schedule to accommodate the fish timing window for instream works. Numerous • Bank protection with riprap over a linear distance environmental constraints had to be adhered to and the project was completed of 320 m successfully on time with good protection of the environment. • Permanent diversion channels to provide Construction of the permanent works was completed entirely by contractors from the Mayo area. A Project Management approach by Yukon Government additional hydraulic capacity in periods of high facilitated leveraging local resources from the Village. The expertise gained from this project has stayed within the community and it will facilitate future water levels (to be completed in 2017) maintenance and monitoring of the river. This experience will be valuable for projects to be completed in other communities. Mayo River Flood Control Project 2017 Yukon Engineering Excellence Award

  5. The Outcome Both the flow management protocol and the flood mitigation works have proven to be successful in reducing ice-related winter flooding on the lower Mayo River. The ice processes on the river are now well understood and documented. Since the flow management protocol was initiated in fall 2014, the community has not experienced any significant flooding nor has emergency flood relief efforts been required (such as extensive mechanical ice-removal). The construction of the flood mitigation works has allowed to stabilized the lower Mayo River , provide permanent access for future maintenance activities and allowed to lower water levels. A robust monitoring program is now in place and will provide the basis for future flow management on the river. The project has increased the confidence of the residents of Mayo in Yukon Energy’s hydro operations on the river as well as Yukon Government ability to solve the issues of recent years. The project has significantly contributed to the residents of Mayo, providing job opportunities Ice cover forming with shore ice growth and keeping the knowledge of the river within the community . 30 2011/2012 2012/2013 2013/2014 2014/2015 2015/2016 2016/2017 Mayo River Flow (m 3 /s) 25 Flow 20 Management 15 No 10 Management Total winter generation at Mayo GS (YEC) 2011/2012: 21.2 GWh 2014/2015: 30.4 GWh 5 2012/2013: 25.6 GWh 2015/2016: 31.4 GWH Bank protection and access road 2013/2014: 29.2 GWh 2016/2017: 15.4 GWH (as of Jan 15) 0 November December January February March April Mayo River Flood Control Project 2017 Yukon Engineering Excellence Award

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend