The Norwegian-German subsea cable project Schleswig-Holstein / Eastern Norway County Network 07.11.12 The Norwegian 930 employees Transmission System Operator Nine overhead Four subsea interconnectors interconnectors 10 000 km lines


slide-1
SLIDE 1

The Norwegian-German subsea cable project

Schleswig-Holstein / Eastern Norway County Network 07.11.12

slide-2
SLIDE 2

Nine overhead interconnectors 930 employees Four subsea interconnectors The Norwegian Transmission System Operator

slide-3
SLIDE 3

 10 000 km lines  Population: 5 million  15 inhabitants pr km2  11 000 km lines  Population: 27 million  370 inhabitants pr km2

slide-4
SLIDE 4
slide-5
SLIDE 5

Tveiten Tonstad Kristiansand Feda Kvilldal Tjele Barkefryd Eemshaven

NorNed

Blyth Wilster Moorriem Hurva Hallsberg

The German Cable Project 2018/2021

3700 MW 700 MW 1400 MW

From 5400 MW to 10300 MW in 10 years

Existing interconnector Future interconnector Future interconnector Existing interconnector

slide-6
SLIDE 6

Effect on grid in Norway - export mode

2011 2022

slide-7
SLIDE 7

German Grid development plan (a scenario)

7

slide-8
SLIDE 8

Tonstad Feda Wilster Moorriem

The Norwegian- German project

slide-9
SLIDE 9

 Animation

slide-10
SLIDE 10

Norwegian TSO, owner and operator of Norwegian grid, including interconnectors

Projectpartners:

German TSO, owns and operates grids at connection points Government owned investment bank active in financing Energiewende projects

slide-11
SLIDE 11

Status

 Parties: Statnett – KfW/TenneT 50-50  Cooperation agreement in place  Full political support  Ongoing licensing processes in

 Germany

 Schleswig-Holstein (NORD.LINK)  Niedersachsen (NorGer)

 Denmark  Norway

 Decision NORD.LINK vs NorGer Q1/2013.

slide-12
SLIDE 12

Required licenses/permits for NORD.LINK/NorGer

Technical license License according to the Offshore Energy Act Power exchange license Exclusive Economic Zone (EEZ) Regional Planning Procedure Planning Approval Procedure Offshore license Planning Approval Procedure Regional Planning Procedure Norwegian Water Resources and Energy Directorate Ministry of Petroleum and Energy Ministry of Petroleum and Energy Danish Energy Agency Federal Maritime and Hydrographic Agency (BSH) State Mining Authority (LBEG)

  • f Clausthal-

Zellerfeld State Company for Road Construction and Transport (LBV) State Company for Road Construction and Transport (LBV) State Company for Road Construction and Transport (NLStBV) State Company for Road Construction and Transport (NLStBV)

slide-13
SLIDE 13

Planned/approved/in use offshore windpark Wattenmeer National Park Restricted Area

  • Military Practice Area
  • Submarine Diving Area
  • Fly zone

Sylt Outer Reef Nature Reserve SPA Östliche Deutsche Bucht (Protected Area) Seevogelschutzgebiet Helgoland (Protected Area) Shipping Separation Area (Shipping lanes) Protection Corridor – No Anchoring Zone NorGer Proposed Route Nord.Link Proposed Route Bird Protection Area

NorGer

Former Munitions Dumping Grounds

Map: Common Wadden Sea Secretariat

Offshore planning

slide-14
SLIDE 14

 Grid connection point – feasible plot  Feasible onshore route

 Agreements with 250 landowners  Property- and environmental compensations

 Crossing of infrastructure

 Crossing of dikes  Crossing of Nord-Ost See Kanal  Crossing of roads and bridges  Crossing agreements offshore infrastructure

Onshore - overall feasibility