the lake turkana wind power
play

The Lake Turkana Wind Power project Part I General Information - PowerPoint PPT Presentation

The Lake Turkana Wind Power project Part I General Information Presented by Henk Hutting 4/9/2012 1 OUTLINE Where will we build and what Does the wind blow up there How do we connect to the grid Can 300 MW be fed into the


  1. The Lake Turkana Wind Power project Part I General Information Presented by Henk Hutting 4/9/2012 1

  2. OUTLINE • Where will we build and what • Does the wind blow up there • How do we connect to the grid • Can 300 MW be fed into the system of Kenya • What are the social and environmental impact • When will it happen 4/9/2012 2

  3. Transmission Line Location of the Site Transport Road Location of the Transformer 4/9/2012 3

  4. Landscape of wind farm area 4/9/2012 4

  5. What else do we need besides 365 wind turbines • Power collection system • 100 km of site roads • Control room, workshop, warehouse, workers rest facilities and canteen • Camp for 600 people during construction • Permanent housing for 100 staff members: a full fledged village • A Lodge 4/9/2012 5

  6. Available almost every day 14 Average daily wind speed 12 W i 10 n d 8 s p e 6 e d 4 m / s 2 0 10 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 April 2008 4/9/2012 6

  7. Yearly profile wind energy And throughout the year 4/9/2012 7

  8. Can 300 MW be fed into the system of Kenya The total installed capacity in Kenya is ~ 1200 MW • Integration study by VTT of Finland demonstrated: – Thanks to large amounts of hydro power including storage basins, large amount of wind power can be integrated – Avoided capacity by the wind farm: 97 MW in dry years – Avoided costs more than 10 cents/kWh up to 20 cents/kWh in dry years – Both Hydro and diesel units can respond quick enough to cope with fluctuations from the wind 4/9/2012 8 farm

  9. What are the social and environmental impacts Positive impacts on: Minor negative impact • CO2 emissions on: • Local employment • Visual intrusion • Economic growth • Cultural contamination • Rural electrification • Loss of habitat • Access Communications • Ponding conditions (ICT) • Road Accessibility 4/9/2012 9

  10. When will be build the farm Strongly depends on planning transmission line • Start road construction: January 2010 • Start building facilities: July 2010 • Start building wind turbines: May 2011 • Operation first wind turbine: July 2011 • Final take over: July 2012 4/9/2012 10

  11. The Lake Turkana Wind Power project Part II In Partnership with AfDB Presented by Hela Cheikhrouhou 4/9/2012 11

  12. Outline  Rationale for banks involvement  Role of AfDB  Project features  Project cost and financing  Project processing plan  Key considerations  Contact details 4/9/2012 12

  13. Rationale for the banks involvement  At 300 MW, it will be high impact, high visibility for Kenyan economy  Increase Kenya’s installed capacity by 25%  It will represent about 12.5% of additional capacity needed by 2020  Least cost, clean and renewable energy  Diversify Kenya’s hydro and substitute diesel based generation  Good demonstration of PPP co-operation by concurrent development of the transmission line  The evacuation route will encourage geothermal power development along its path 4/9/2012 13

  14. Role of AfDB  AfDB is the mandated lead arranger (MLA)  The Bank will be responsible for facilitating the entire debt tranche of about € 300m from DFI and commercial sources  The Bank is interested in providing upto € 100m for its own account.  DFI loan tenor of upto 12 years and 9 years from commercial sources  The bank along with the sponsors held a DFI seminar in Tunis where participants indicted level of interest in the project  The bank continues to hold bi-monthly DFI meetings to discuss project updates and financing terms 4/9/2012 14

  15. Project Features  Power to be sold to KPLC on take or pay basis  Negotiated Tariff rate: Load Tariff Comments (€ cents/KWh) Factor 7.22 55% Annually calculated 3.61 > 55% Annually calculated  PPA duration: 20 years  Plan for first turbine installation – July 2011  End of construction – July 2012 4/9/2012 15

  16. Project Cost and financing 2009 2010 2011 2012 Total Total investment 8.8 156.9 258.7 9.4 433.8 Financing Structure Equity (30%) 8.8 87.3 34 0 130.1 Debt (70%) 0 69.7 224.6 9.4 303.7 Total sources of funds 8.8 156.9 258.7 9.4 433.8 4/9/2012 16

  17. Revenue Analysis Average Number of turbines installed 365 Average Farm capacity (MW) 303 Average expected Load factor 55% Average Energy at Load factor of 55%, GWh 1,388 Tariff – At 55% load factor, Eur Cts/ KWh 7.22 Average Revenue (Euro - Millions) 104.1 4/9/2012 17

  18. Summary of Project outputs Annual Ratios Minimum Historic Senior DSCR 1.48x Forward Senior DSCR 1.48x Senior LLCR 1.70x 4/9/2012 18

  19. Project Returns Project Returns Discount Rate Result Project FIRR, nominal 16.81% Project FIRR, real 14.52% Equity Returns Equity FIRR, nominal 24.00% 20.37% Equity FIRR, real 21.57% 18.01% (18.7) EUR million Equity FNPV, nominal 24.00% Equity FNPV, real 21.57% (18.7) EUR million 4/9/2012 19

  20. Project processing plan  Operating Committee (OpsCom) – End May 2009  Joint Lender’s appraisal mission – Mid June 2009  Board date – End July 2009 4/9/2012 20

  21. Key Considerations  Structure and financing for the 400kv transmission line needs to be developed in tandem with the Genco.  Equity partners with track record in executing similar projects in developing countries.  IPP license and execution of PPA nearing conclusion  Finalization of Vestas quotation and negotiation for full EPC wrap in May 2009  GoK proposed letter of comfort to lenders for KPLC payment will need to be strengthened with full government guarantee. 4/9/2012 21

  22. Contacts Hela Cheikhrouhou Youssef Arfaoui Manager Investment Officer - RE Expert Infrastructure Finance Division Infrastructure Finance Division h.cheikhrouhou@afdb.org y.arfaoui@afdb.org +216 71102140 +216 71102308 Obiora Okoye Investment Officer Infrastructure Finance Division o.okoye@afdb.org +216 71103816 4/9/2012 22

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend