The Lake Turkana Wind Power project Part I General Information - - PowerPoint PPT Presentation

the lake turkana wind power
SMART_READER_LITE
LIVE PREVIEW

The Lake Turkana Wind Power project Part I General Information - - PowerPoint PPT Presentation

The Lake Turkana Wind Power project Part I General Information Presented by Henk Hutting 4/9/2012 1 OUTLINE Where will we build and what Does the wind blow up there How do we connect to the grid Can 300 MW be fed into the


slide-1
SLIDE 1

4/9/2012 1

The Lake Turkana Wind Power project

Part I

General Information

Presented by Henk Hutting

slide-2
SLIDE 2

4/9/2012 2

OUTLINE

  • Where will we build and what
  • Does the wind blow up there
  • How do we connect to the grid
  • Can 300 MW be fed into the system of

Kenya

  • What are the social and environmental

impact

  • When will it happen
slide-3
SLIDE 3

4/9/2012 3

Location of the Site Location of the Transformer Transmission Line Transport Road

slide-4
SLIDE 4

4/9/2012 4

Landscape of wind farm area

slide-5
SLIDE 5

4/9/2012 5

What else do we need besides 365 wind turbines

  • Power collection system
  • 100 km of site roads
  • Control room, workshop, warehouse, workers

rest facilities and canteen

  • Camp for 600 people during construction
  • Permanent housing for 100 staff members: a

full fledged village

  • A Lodge
slide-6
SLIDE 6

4/9/2012 6 2 4 6 8 10 12 14

10 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

W i n d s p e e d m / s

April 2008

Available almost every day

Average daily wind speed

slide-7
SLIDE 7

4/9/2012 7

Yearly profile wind energy

And throughout the year

slide-8
SLIDE 8

4/9/2012 8

Can 300 MW be fed into the system of Kenya

The total installed capacity in Kenya is ~ 1200 MW

  • Integration study by VTT of Finland demonstrated:

– Thanks to large amounts of hydro power including storage basins, large amount of wind power can be integrated – Avoided capacity by the wind farm: 97 MW in dry years – Avoided costs more than 10 cents/kWh up to 20 cents/kWh in dry years – Both Hydro and diesel units can respond quick enough to cope with fluctuations from the wind farm

slide-9
SLIDE 9

4/9/2012 9

What are the social and environmental impacts

Minor negative impact

  • n:
  • Visual intrusion
  • Cultural contamination
  • Loss of habitat
  • Ponding conditions

Positive impacts on:

  • CO2 emissions
  • Local employment
  • Economic growth
  • Rural electrification
  • Access Communications

(ICT)

  • Road Accessibility
slide-10
SLIDE 10

4/9/2012 10

When will be build the farm

Strongly depends on planning transmission line

  • Start road construction: January 2010
  • Start building facilities: July 2010
  • Start building wind turbines: May 2011
  • Operation first wind turbine: July 2011
  • Final take over: July 2012
slide-11
SLIDE 11

4/9/2012 11

The Lake Turkana Wind Power project

Part II

In Partnership with AfDB

Presented by Hela Cheikhrouhou

slide-12
SLIDE 12

4/9/2012 12

Outline

  • Rationale for banks involvement
  • Role of AfDB
  • Project features
  • Project cost and financing
  • Project processing plan
  • Key considerations
  • Contact details
slide-13
SLIDE 13

4/9/2012 13

Rationale for the banks involvement

  • At 300 MW, it will be high impact, high visibility for Kenyan economy
  • Increase Kenya’s installed capacity by 25%
  • It will represent about 12.5% of additional capacity needed by 2020
  • Least cost, clean and renewable energy
  • Diversify Kenya’s hydro and substitute diesel based generation
  • Good demonstration of PPP co-operation by concurrent development of the

transmission line

  • The evacuation route will encourage geothermal power development along

its path

slide-14
SLIDE 14

4/9/2012 14

Role of AfDB

  • AfDB is the mandated lead arranger (MLA)
  • The Bank will be responsible for facilitating the entire debt

tranche of about €300m from DFI and commercial sources

  • The Bank is interested in providing upto €100m for its own

account.

  • DFI loan tenor of upto 12 years and 9 years from commercial

sources

  • The bank along with the sponsors held a DFI seminar in Tunis where

participants indicted level of interest in the project

  • The bank continues to hold bi-monthly DFI meetings to discuss project

updates and financing terms

slide-15
SLIDE 15

4/9/2012 15

Project Features

  • Power to be sold to KPLC on take or pay basis
  • Negotiated Tariff rate:
  • PPA duration: 20 years
  • Plan for first turbine installation – July 2011
  • End of construction – July 2012

Tariff

(€ cents/KWh)

Load Factor Comments 7.22 55% Annually calculated 3.61 > 55% Annually calculated

slide-16
SLIDE 16

4/9/2012 16

Project Cost and financing

2009 2010 2011 2012 Total Total investment 8.8 156.9 258.7 9.4 433.8 Financing Structure Equity (30%) 8.8 87.3 34 130.1 Debt (70%) 69.7 224.6 9.4 303.7 Total sources of funds 8.8 156.9 258.7 9.4 433.8

slide-17
SLIDE 17

4/9/2012 17

Average Number of turbines installed 365 Average Farm capacity (MW) 303 Average expected Load factor 55% Average Energy at Load factor of 55%, GWh 1,388 Tariff – At 55% load factor, Eur Cts/ KWh 7.22 Average Revenue (Euro - Millions) 104.1

Revenue Analysis

slide-18
SLIDE 18

4/9/2012 18

Annual Ratios Minimum

Historic Senior DSCR 1.48x Forward Senior DSCR 1.48x Senior LLCR 1.70x

Summary of Project outputs

slide-19
SLIDE 19

4/9/2012 19

Project Returns Discount Rate Result Project FIRR, nominal 16.81% Project FIRR, real 14.52% Equity Returns Equity FIRR, nominal 24.00% 20.37% Equity FIRR, real 21.57% 18.01% Equity FNPV, nominal 24.00% (18.7) EUR million Equity FNPV, real 21.57% (18.7) EUR million

Project Returns

slide-20
SLIDE 20

4/9/2012 20

Project processing plan

  • Operating Committee (OpsCom) – End May 2009
  • Joint Lender’s appraisal mission – Mid June 2009
  • Board date – End July 2009
slide-21
SLIDE 21

4/9/2012 21

Key Considerations

  • Structure and financing for the 400kv transmission line needs to be

developed in tandem with the Genco.

  • Equity partners with track record in executing similar projects in developing

countries.

  • IPP license and execution of PPA nearing conclusion
  • Finalization of Vestas quotation and negotiation for full EPC wrap in May

2009

  • GoK proposed letter of comfort to lenders for KPLC payment will need to be

strengthened with full government guarantee.

slide-22
SLIDE 22

4/9/2012 22

Contacts

Obiora Okoye

Investment Officer Infrastructure Finance Division

  • .okoye@afdb.org

+216 71103816

Hela Cheikhrouhou

Manager Infrastructure Finance Division h.cheikhrouhou@afdb.org +216 71102140

Youssef Arfaoui

Investment Officer - RE Expert Infrastructure Finance Division y.arfaoui@afdb.org +216 71102308