The Hunters Point Power Plant Closure and Cleanup Project Advisory - - PowerPoint PPT Presentation

the hunters point power plant closure and cleanup
SMART_READER_LITE
LIVE PREVIEW

The Hunters Point Power Plant Closure and Cleanup Project Advisory - - PowerPoint PPT Presentation

The Hunters Point Power Plant Closure and Cleanup Project Advisory Committee Meeting March 1, 2011 March 1, 2011 1 Introductions Project Advisory Committee Members PG&E Project Managers Fred Flint d l Loren Loo David


slide-1
SLIDE 1

The Hunters Point Power Plant Closure and Cleanup

Project Advisory Committee Meeting

March 1, 2011 March 1, 2011

1

slide-2
SLIDE 2

Introductions

  • Project Advisory Committee Members
  • PG&E Project Managers

d l ‐ Fred Flint ‐ Loren Loo ‐ David Harnish

  • Clean‐up Contractors

‐ URS – Joe Morgan, Sr. Project Manager ‐ ERRG – Terry Winsor, Sr. Project Manager ‐ SCA – Chuck Siu, President ‐ JBR Partners – James Bryant

2

JBR Partners James Bryant

slide-3
SLIDE 3

Agenda

  • Safety moment

Safety moment

  • Cleanup progress
  • Upcoming work
  • Air monitoring updates
  • Local jobs
  • Questions
  • Questions
  • Feedback

3

slide-4
SLIDE 4

Safety

PG&E Environmental Remediation

COMMITTED TO SAFETY COMMITTED TO SAFETY

Every Day Every Action Every Action Everyone

Eyes Up…Head On

4

slide-5
SLIDE 5

HPPP Site Aerial

5

slide-6
SLIDE 6

Soil Testing and Cleanup

6

slide-7
SLIDE 7

Cleanup Progress

  • Remediation work began September

g p 2010

  • As of February 10, 2011, completed

removal of 22 124 tons (902 trucks removal of 22,124 tons (902 trucks worth) of contaminated soil from areas A, C/D and J

  • Ongoing removal of crushed concrete

and asphalt stockpiles for recycling

  • Ongoing storm water and site
  • Ongoing storm water and site

management activities; 1,667,200 gallons of storm water removed A watering truck and excavator in Area J

7

slide-8
SLIDE 8

Upcoming Work

Areas A C/D and J: Areas A, C/D and J:

  • Continuing soil excavation

and off-hauling

  • Beginning to backfill

excavations with clean soil

  • Paving of Area J

Area B: Area B:

  • Dismantlement of existing

structures

  • Relocation of work trailers

t l d A J to newly paved Area J Area F:

  • Removal of soil and

Soil excavation in Area A

8

underground infrastructure Soil excavation in Area A

slide-9
SLIDE 9

Upcoming Work

Area H: Area H:

  • Surveying work in

preparation for upcoming cleanup activities Area I:

  • Collection of soil samples

Collection of soil samples using a truck-mounted drill rig (see photo at right) Truck-mounted drill rig

9

slide-10
SLIDE 10

Dust Control and Air Monitoring

  • Air monitoring has been taking place at the site

g g p since dismantlement work began in 2007

  • Approved dust control plan on file with the Bay

Area Air Quality Management District (BAAQMD) Area Air Quality Management District (BAAQMD)

  • Out of 250 days at the site, we have had 12 days

where readings for naturally occurring asbestos were above the trigger level

  • Readings for all other constituents continue to be

under health‐protective levels under health‐protective levels

  • All air monitoring results are reported to DTSC

and BAAQMD

10

slide-11
SLIDE 11

Communications

  • Project Advisory Committee outreach

j y

  • Weekly Email
  • Phone Outreach
  • Meetings
  • Regular project updates/

newsletter to extended community

  • Reports on pge.com/hunterspoint
  • Full data reports
  • Summary graphs
  • Coordination with regulatory agencies
  • Bi-weekly reports to BAAQMD and DTSC
  • Weekly BAAQMD site visits
  • Reports available on DTSC website
  • Hard copy reports available at APRI (1301 Evans Ave )

11

Hard copy reports available at APRI (1301 Evans Ave.)

slide-12
SLIDE 12

Dust Control Measures

Measures in place on work days: p y

  • Spraying water to suppress dust:
  • Watering trucks
  • Hand‐held hoses

W t i t th f li

  • Water misters on the fence line
  • Applying soil tackifier
  • Washing truck tires
  • Covering truck loads

g

  • Fence screening
  • Washing of adjacent streets
  • Covering soil stockpiles
  • Lowered on site speed limit
  • Lowered on‐site speed limit

12

slide-13
SLIDE 13

Adaptive Dust Control Solutions

 Additional fenceline water misters Additional fence screening 

13

slide-14
SLIDE 14

Adaptive Dust Control Solutions

 Increased application of water pp and soil tackifier Increased street washing with watering trucks 

14

watering trucks 

slide-15
SLIDE 15

Local Jobs Program

  • Local hiring program involves working

g p g g closely with the City of San Francisco’s CityBuild program and local labor leaders

  • While the exact number of workers varies

While the exact number of workers varies with activities on the Site, we are currently employing:

  • 5 (31%) local laborers and operators
  • 5 (31%) local laborers and operators
  • 5 (100%) local truckers

A i ti ith i t f it ti iti

  • Assisting with variety of on-site activities:

soil excavation, dust mitigation, traffic control, trucking, storm water management

15

slide-16
SLIDE 16

Contact Us

For more information:

  • Project Hotline: (415) 626‐3055
  • Environmental Remediation Response Line: 1‐866‐247‐0581
  • Project Email: communityfirst2010@yahoo.com

16

slide-17
SLIDE 17
  • Questions?

Questions?

  • Feedback?

17

slide-18
SLIDE 18

Thank you Project Advisory Committee Meeting

18