The GoodThe Badand The Ugly One Towns journey to build a greenway - - PowerPoint PPT Presentation

the good the bad and the ugly
SMART_READER_LITE
LIVE PREVIEW

The GoodThe Badand The Ugly One Towns journey to build a greenway - - PowerPoint PPT Presentation

The GoodThe Badand The Ugly One Towns journey to build a greenway September 14, 2016 - New Milford River Trail Association Presented By: Dennis DiPinto, Director Brookfield Parks & Recreation STILL RIVER GREENWAY 1999 - 2018


slide-1
SLIDE 1

The Good…The Bad…and The Ugly

One Towns journey to build a greenway…

September 14, 2016 - New Milford River Trail Association Presented By: Dennis DiPinto, Director Brookfield Parks & Recreation

slide-2
SLIDE 2

STILL RIVER GREENWAY 1999 - 2018

  • 2.25 miles in length
  • Longest pedestrian bridge in Connecticut
  • $2.8 million to construct!!!
  • Phase One construction 2011-2012
  • Phase Two construction completed 2016
  • 90% of project built in “regulated area” (wetland, flood plains)
  • Nearly 100,000 people use the trail annually (per Connecticut

Trail Census)

  • Town applying for a $25,000 prize from Robert Wood Johnson

Foundation to recognize town’s efforts to improve community health

slide-3
SLIDE 3

Setting the Scene…Brookfield CT

  • Located in Northern Fairfield County in southwest Connecticut. The town is

bounded by New Milford, Bridgewater, Newtown, Bethel and Danbury.

  • Population of about 17,000 people / 6,500 households within its land area of

about 20 square miles…All while enjoying about 10% open space.

  • Median household income is estimated at $110,000, notably higher than

median incomes within in the 10 minute drive which is about $85,000 and the region at $76,000.

  • First Selectman – Town Meeting form of Government

Annual Town/School budget just north of $60,000,000

  • Four public schools that service about 3,000 students

Brookfield is well known for;

  • The Federal Rd. corridor…affectionately referred to by the “miracle mile.”
  • It’s location nestled between Candlewood Lake and Lake Lillinonah.
  • Being home to the first Chick-Fil-A in CT.
  • Families and community pride.

LET’S PUT THIS IS SOME HISTORICAL PERSPECTIVE…

slide-4
SLIDE 4

1999-2002

Laying the Foundation The Parks & Recreation Commission performs scientifically valid “needs assessment study followed by an “awareness campaign.”

slide-5
SLIDE 5

June 2000 – The Mail Survey

YOU ARE ONE OF 2,500 BROOKFIELD HOUSEHOLDS RANDOMLY SELECTED TO…

Participate in the Brookfield Parks and Recreation Commission’s long-range Master Plan.

  • The purpose of this study is to proactively address future needs of the

Community as seen by members of the Community.

  • With your help the Parks and Recreation Commission can

determine your priorities in developing future public leisure

  • pportunities.
  • You represent six Brookfield households, please take a few minutes

to complete this survey. Your responses will be kept anonymous.

Please accept the attached $5.00 “Rec-Buck” as a token of our appreciation for your participation in this “Community Needs Assessment Study”. Use it in place of cash the next time you sign up for a trip or program with the Brookfield Parks and Recreation Department. Instructions: Any adult member of the household on behalf of all family members should complete this

  • survey. Your responses are anonymous and confidential. Your input is needed for planning future

recreational programs and facilities for the residents of Brookfield. Thanks in advance for your participation! PLEASE RETURN COMPLETED SURVEY FORMS By June 23, 2000 BROOKFIELD PARKS AND RECREATION PO BOX 5106 BROOKFIELD, CT 06804

slide-6
SLIDE 6

1999-2002

  • Results of the Needs Assessment

Survey (right) show strong community support for the project

  • The survey return rate of 19% was
  • strong. Most mail surveys among

general populations experience return rates of 5% to 25%

  • Statistically, a sample of 468

surveys represents a margin for error of +/-4.5% providing Brookfield a 95% confidence level

slide-7
SLIDE 7

2001-2002 – Creating Awareness

Partial List of the Needs Assessment “Dog and Pony” show presentation schedule;

  • Conservation Commission
  • Rotary Club
  • High School Parent Group
  • 4 different PTO groups
  • Lions Club
  • Police Commission
  • Various public meetings
  • Parks & Rec. Commission
  • Board of Selectman
  • Board of Finance
  • Board of Education
  • Planning Commission
  • Zoning Commission
  • Commission on aging
  • 2 Women’s clubs
  • Local & Regional EDC
  • Brookfield Education

Foundation

“Movers and Shakers meeting in 2002 spawned the Multi-Use Trail and Rec. Center steering Committees. In 2003 both committees merged to form REC.

slide-8
SLIDE 8

2001-2002

  • Brookfield established a new Recreation

Enhancement Council (501C3

  • rganization)
  • Allowed us to raise money for feasibility

studies and other promotional materials

  • Local EDC support of $5,000 for

feasibility study

  • SRG preliminary design work
  • Our Regional Planning Organization

(HVCEO) awarded Brookfield a $440,000 grant (Federal Transportation Enhancement funds) subject to 80/20 cost sharing

slide-9
SLIDE 9

2003-2004

  • Town Meeting January 2003

approves $110,000 in town funds (the 20% match)

  • Preliminary study shows that

total funds of $550,000 are sufficient to build the project

  • Project comes to a stop

because the 80% Federal funds match is not released until 2006 Grand Total:

slide-10
SLIDE 10

2005-2008

  • TOB recommits to the state / project another $100,000 (or did they).

This is 20% of what is now a 1 million dollar project

  • Preliminary estimates begin to soar mainly due to Bridge length,

environmental issues and DOT required contingency amounts

  • State agrees to increase funding for the project as long as the TOB

agrees to continue to pay the required 20% share

  • Agreements, supplemental agreements, commitments, and deals

with the devil

slide-11
SLIDE 11

2009-2011

  • Cost estimates continue to climb and we approach final design
  • Phase I is broken out of the project because:

– It was the only portion of the trail that did NOT involve environmental permitting – It was VERY important that after so many years of discussion, there was “proof of progress”

slide-12
SLIDE 12

Birds Eye View

Phase I in Yellow Phase II in Red

slide-13
SLIDE 13

Phase I Completed 2011

slide-14
SLIDE 14

2012-2014

  • Final Design of Phase II completed
  • Price tag to complete the project is now at $2.4 million. Somehow

we talked the State into staying on this ride!

  • Town Meeting and ultimately a successful referendum for additional

$481,400 Grand Total:

slide-15
SLIDE 15

2015-2016

slide-16
SLIDE 16

2015-2016

slide-17
SLIDE 17

2015-2016

  • Bid process begins w/ 6 responsible and qualified bids received
  • More contracts, agreements and supplemental agreements…and

then some more…

  • The vetting process
  • Phase II awarded and construction begins
  • Scheduled for completion June 2016 Now October 15th, 2016

Completing a Vision: Referendum passes 1,360 – 273

slide-18
SLIDE 18

The Players

  • Project involved CT DOT, CTDEEP

, EPA and Army Corps of Engineers

  • Coordination between all of the

players is an exercise in frustration and lost time – Took nearly a year to schedule

  • ne joint site walk. Four

different dates arranged – $20,000 spent on required environmental studies – $16,000 spent on required archeological studies

slide-19
SLIDE 19

Permitting

  • During a permit coordination

meeting, CTDOT’s Office of Environmental Planning stated that this trail project was “un-permittable”

  • A field investigation for the presence
  • f turtles was required

– “No turtles were observed within the study area although the southern portion of the Still River Greenway trail does have habitat consistent with that preferred by wood turtles… “

  • It still took almost a full year to get

DEEP to sign off!

slide-20
SLIDE 20

Effectiveness of Site Walks 1st time, DEEP showed, ACOE didn’t 2nd Site Walk, ACOE showed, DEEP didn’t

  • As a result of each site walk, totally different

direction was given re: mitigation ratios and how to proceed

  • Project Site had 5 Vernal Pools; which Buffer

Areas of 250’

  • Extensive Flood Plain – which we were

required to span Floodway = 160’ Flood Plain= 475’

Permitting (Continued)

slide-21
SLIDE 21

Rights of Way

  • Uncooperative Owners

– Property owners were willing to donate an easement to use their property – Until they realized the donation was worth $530,000 !!!

  • We then needed to design

AROUND them

No Way

slide-22
SLIDE 22

Personnel Changes

Over the course of this project…

  • Lead Designer changed 2x
  • DOT Program Administrator

changed 3x

  • Town’s First Selectmen changed 6x
  • Still River Greenway Committee

was reduced from 12 members to 1

  • ACOE Analysts changed 1x
  • Town’s Inland Wetland Agent

changed 2x

slide-23
SLIDE 23

Frustration Over Lack of Progress

More Reaction to Yet More Delays

10-2-13 Email: “I'm the COE project manager in charge of reviewing the regulatory aspects of your project. I was going to present this today at our joint process review meeting with EPA and the other federal/state agencies; however, due to the furlough it was canceled. Today is my last day in the office until at least October 15th-- in part due to the furlough, but also because of scheduled leave from

  • Oct. 7th - 11th. I plan to coordinate the review of this project with EPA once I'm

back, and will forward you relevant comments at that time. For future inquiries about this project, please feel free to call me at (978) xxx-xxxx later in the month. Thanks, and sorry for any inconvenience this may cause!”

Comment from the Town’s Parks and Rec. Department Director: “It’s amazing anything gets done!”

slide-24
SLIDE 24

Funding: Reimbursement for all phases via Transportation Enhancement Funding (80% federal, 20% local) Estimated total cost: $2,803,200 ($2,242,560 Federal and $560,640 local) Note: Included here are additional funds of $396,000 added after bidding process August 2015.

Provided the Town approves the 20% match on this project.

Funding Source Design & Inspections Construction Total Federal $298,604 $1,943,956 $2,242,560 Town of Brookfield $74,651 $485,989 $560,640 Total $373,255 $2,429,945 $2,803,200 Overall Funding

slide-25
SLIDE 25

Contract Amt. Expended YTD Remaining YTD Prime Contractor $2,267,900 $1,352,562 or 60% $915,338 or 40% Design & Inspections $373,265 $300,545 or 80% $72,720 or 20% State Oversight / Mat. testing $162,035 $0 or 0% $162,035 or 100% Total $2,803,200 $1,653,107 or 59% $1,150,093 or 41%

Overall Funding continued… Today we are approx. 90% complete with the Greenway Project Why go through the exercise?

slide-26
SLIDE 26

Enhanced Local Recreational Opportunities

  • Safe place for children to learn

to ride bikes – Brookfield is an old farm town – Narrow, hilly roads without sidewalks

  • Safe place for everyone to

exercise – Biking – Walking – Rollerblading – Jogging/Running Because it’s what our residents wanted and needed…

slide-27
SLIDE 27

Stimulus for Local Economy

  • Northern terminus is “Four

Corners” (the Town is currently working on this area to develop a vibrant pedestrian friendly downtown area). – Brookfield is revitalizing this area into a “village-like,” pedestrian-friendly neighborhood – Greenway will bring people: lunch, coffee shops, ice cream shops, etc.

slide-28
SLIDE 28

Hub for Regional Transportation

  • Northern section is a key

link to connect New Milford and Danbury for “intercity” bikers.

  • Western New England

Greenway initiative: http://wnegreenway.org/

slide-29
SLIDE 29

Rewards for Seeing it Through!

slide-30
SLIDE 30

Rewards for Seeing it Through!

slide-31
SLIDE 31

Rewards for Seeing it Through!

slide-32
SLIDE 32

Rewards for Seeing it through!

slide-33
SLIDE 33

Rewards for Seeing it through!

slide-34
SLIDE 34

Rewards for Seeing it through!

slide-35
SLIDE 35

Rewards for Seeing it through!

slide-36
SLIDE 36

Rewards for Seeing it through!

slide-37
SLIDE 37

Rewards for Seeing it through!

slide-38
SLIDE 38

Rewards for Seeing it through!

slide-39
SLIDE 39

Rewards for Seeing it through!

slide-40
SLIDE 40

Rewards for Seeing it through!

slide-41
SLIDE 41

Rewards for Seeing it Through!

All six Selectman pictured here at the Ground Breaking ceremony (that was held 8 months early). Can you guess why?

If you answered “because it’s an election year” you are correct!

slide-42
SLIDE 42

Questions?