the future of the power industry
play

The Future of the Power Industry: Implications for Network - PowerPoint PPT Presentation

The Future of the Power Industry: Implications for Network Regulation Paul Centolella President, Paul Centolella & Associates, LLC Senior Consultant, Tabors Caramanis Rudkevich ACCC/AER Regulatory Conference Brisbane, Queensland August 4,


  1. The Future of the Power Industry: Implications for Network Regulation Paul Centolella President, Paul Centolella & Associates, LLC Senior Consultant, Tabors Caramanis Rudkevich ACCC/AER Regulatory Conference Brisbane, Queensland August 4, 2016

  2. Overview • Challenges and Opportunities: Common to US and Australia • Approaches to Distributed Energy Resource (DER) Valuation and Integration – Planning and Administrative Valuation – Markets and Pricing • Structuring a Market for DER: Platforms and Distribution System Operators (DSOs) • Grid Architecture for Networks with Significant DER • Implications for the future of network regulation August 4, 2016 ACCC/AER Regulatory Conference 2

  3. Challenge: Remaining Affordable • AU Forecast Electricity Consumption to 2036 Revenue growth is disappearing: “ Consumption of grid-supplied – electricity is forecast to remain No Increase flat for the next 20 years, despite projected 30% growth in population” 1 • Electric utilities have to invest: – Replacing aging infrastructure: U.S. utilities need $673 Billion (USD) in new reliability investment in this U.S. Investor Owned Electric Utility Capital decade, exceeding market cap of US Spending & Free Cash Flow 120 investor owned electric companies 2 100 – 80 New requirements: Climate 60 adaptation, Distributed resources, Billion US$ 40 Physical and cyber security 20 • Potential for Negative Cash Flow 0 & Increasing Rates 3 -20 -40 -60 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Capital Expenditures Free Cash Flow August 4, 2016 ACCC/AER Regulatory Conference 3

  4. Challenge: Ensuring Reliability and Security • Growing dependence on reliable electric service: – Economy is increasingly digital – Population is increasingly urban • Mounting weather & climate risks: – Severe Storms – Extreme heat – Drought & fire Metcalf Substation • Vulnerability of critical cyber / physical systems – Interdependence, Inherently Open System, Unregulated Supply Chain, Fragmented Control, Dynamic Threats August 4, 2016 ACCC/AER Regulatory Conference 4

  5. Challenge: Providing Access to New Resources • High penetration of variable resources impacts network operations, ramping requirements, system costs, & conditions for price volatility • Reported 7/7/16 price South Australia price variance: $100 to $14,000(AU$)/MWh 4 • Economies of scale remain important 6 CA ISO Forecast 2020 Impact of PV: • Utility scale PV < Half Cost of Small Distributed PV 5 3 Hour Ramp More than 12,000 MW Cumulative PV Installations 7 Australian PV Institute 6000 5000 4000 MW 3000 2000 8 1000 0 2008-01 2008-06 2008-11 2009-04 2009-09 2010-02 2010-07 2010-12 2011-05 2011-10 2012-03 2012-08 2013-01 2013-06 2013-11 2014-04 2014-09 2015-02 2015-07 2015-12 2016-05 ~1,100MW on installed domestic PV capacity on a ~5,000MW network. In some postcodes >40% of customers have PV. Total energy delivered is ~ 7% (1438GWh) of total usage August 4, 2016 ACCC/AER Regulatory Conference 5

  6. Challenge: Becoming Sustainable • Climate is a Global Problem: – If developed economies had Zero CO 2 emissions, Carbon budget for 2 o C stabilization could be breached by 2050 Onshore Wind Costs = 142% of • Low carbon technologies need to Advanced Gas Combined Cycle (US$) With $30/T Carbon Price cost less to scale globally – While costs of low carbon power have fallen, the full cost remains above that of gas generation in most of the US & of coal in many growing economies 9 • Requires Innovation – Learning by doing is insufficient to achieve timely improvements August 4, 2016 ACCC/AER Regulatory Conference 6

  7. Opportunity: Integration of Digital Technology • Expansion of affordable computation + connectivity + data collection is producing: – Low transaction cost and multi-sided markets – Unbundling of products and services to match consumer specific characteristics and preferences – Intelligent and high speed cyber/physical systems – Improved asset utilization and recruitment of underutilized resources – Greater precision in system controls • Electricity sector has yet to fully realize the benefits of digital technology August 4, 2016 ACCC/AER Regulatory Conference 7

  8. DER Valuation: 2 Approaches • Fundamental Approaches to Valuation: – Planning and administrative valuation approaches (e.g. LMP +D, feed-in tariff, net metering retail rate credits) – Market based valuation via Distribution Locational Marginal Prices (DLMP) • What is the difference? – LMP+D and similar approaches are based on planning or administrative forecasts of average expected “avoided costs.” For example LMP (i.e. nodal, or wholesale value, of real energy) plus D (an planning or administrative forecast of average avoided distribution system costs). – LMP+D requires more transparent distribution planning & more detailed regulatory review of distribution plans – DLMP is a granular, market measure of short run marginal cost (SRMC) at the specific time and location for the provision or use of core electric products August 4, 2016 ACCC/AER Regulatory Conference 8

  9. LMP + D Value by Time and Location: Consolidated Edison (New York City) • Only 22% of Consolidated Edison’s NYC distribution networks have peaks that coincide with system peak 10 – Demand response programs based on the needs of the bulk power system would not address many of the needs of distribution systems • Half of the incremental PV installations are in ConEd’s night - peaking distribution networks – Such PV installations may have little or no positive distribution (D) value and may increase distribution costs August 4, 2016 ACCC/AER Regulatory Conference 9

  10. LMP + D Value by Time and Location: Consolidated Edison (New York City) • In ConEd’s mesh network placement of distributed resources has a significant impact – Must be placed near constrained component to be effective • Multiplying effect: The farther DER are from constrained component, the more DER kW are needed to provide equivalent load support – More distributed placement is less efficient: Smaller amounts of DER at multiple node points will require even more kW than shown here August 4, 2016 ACCC/AER Regulatory Conference 10

  11. Plan Based LMP + D Value: ConEd Brooklyn Queens Demand Management (BDQM) Project • Targets load growth in 3 networks of Brooklyn and Queens Burroughs of NYC • Plan to defer $1 Billion (US$) in traditional network upgrades with $200 million (US$) incentive program • DER procurements through open RFI and structured auctions • Regulator treating expenditures as 10-year regulatory assets earning base ROE + performance adder (up to 100 bp) August 4, 2016 ACCC/AER Regulatory Conference 11

  12. Anticipated 2018 BQDM Resource Portfolio • Energy Efficiency, Voltage Optimization, Gas-fired Generator, Fuel Cell, and Evening Demand Response • Supplemented with modest contributions from PV and Battery Storage Targeted Need Fuel Cell & Gas DG may operate when no load relief is needed August 4, 2016 ACCC/AER Regulatory Conference 12

  13. Planning / Administrative Valuation • Targeting DER can defer more expensive distribution investments • Time and location have a significant impact on value • Planning forecasts /administrative valuations won’t fully capture load and network configurations changes or emergence of better resource options • Scaling planning and administrative valuation to optimize high penetrations of DER will be challenging for utilities and regulators • Use of competitive procurements (without first disclosing avoided costs) can contribute to savings • Fixed output resources may defer costs in some hours and provide unneeded and more costly power in other hours • Option contracts that enable utility to call DER when needed may provide a more efficient alternative August 4, 2016 ACCC/AER Regulatory Conference 13

  14. 11 Pricing: Core Electric Products from DER (ONLY 3!) • The 3 Rs – Real Energy – Reactive Power – Reserves • The 3 Rs require tradeoffs – Tradeoff between producing real versus reactive power – Tradeoff between committing now to produce real or reactive power (now and forward) and being available to provide reserves August 4, 2016 ACCC/AER Regulatory Conference 14

  15. Granular Pricing: Time Variance Peak Day Hourly Zonal LMPs for Selected PJM Zone 90 80 70 60 US$ / MWh 50 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 PJM Data Miner: Locational Marginal Prices Total LMP August 4, 2016 ACCC/AER Regulatory Conference 15

  16. Granular Pricing: Locational Variance (RTO) Variance in Peak Day Ave. Hourly Nodal & Zonal LMPs for Selected PJM Zone 1000 800 600 400 US$ / MWh Minimum Nodal LMP 200 Maximum Nodal LMP Zonal LMP 0 -200 -400 12 Hours with Max LMP Variance in Zone >$50/MWh -600 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 PJM Data Miner: Locational Marginal Prices Total LMP August 4, 2016 ACCC/AER Regulatory Conference 16

  17. 12 Granular Pricing: Real & Reactive Power DLMPs Modeling Results: Summer Day, High DER Scenario for an Illustrative 800 Bus (US$) Commercial / Residential Distribution Feeder (US$) August 4, 2016 ACCC/AER Regulatory Conference 17

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend