the first class a 1 effluent permit in montana
play

The First Class A-1 Effluent Permit in Montana Moonlight Basin, Big - PowerPoint PPT Presentation

The First Class A-1 Effluent Permit in Montana Moonlight Basin, Big Sky Montana Topics Effluent Reuse Treatment Selection Design & Permitting Construction Project Challenges 4/30/2020 The First Class A-1


  1. The First Class A-1 Effluent Permit in Montana Moonlight Basin, Big Sky Montana

  2. Topics Effluent Reuse • Treatment Selection • Design & Permitting • Construction • Project Challenges • 4/30/2020 The First Class A-1 Effluent Permit in Montana 2

  3. Regulation Montana DEQ Circular DEQ-2, Appendix B Class A-1 Standard 5/19/2020 The First Class A-1 Effluent Permit in Montana 3

  4. 5/19/2020 The First Class A-1 Effluent Permit in Montana 4

  5. Treatment Selection Moonlight Basin Resort: Original Plant was a trickling • filter system treating septic tank effluent. Disposal to drainfield. An oxidation ditch treatment • plant replaced the original plant. Storage ponds and disposal to forest irrigation. 5/19/2020 The First Class A-1 Effluent Permit in Montana 5

  6. Treatment Selection Preliminary Engineering Report • Make Recommendations For Wastewater Treatment and Disposal 5/19/2020 The First Class A-1 Effluent Permit in Montana 6

  7. Wastewater Treatment Alternatives • Single MBR • Existing Oxidation Ditch, 2 New Oxidation Ditches • Existing Oxidation Ditch, 2 New SBRs • Existing Oxidation Ditch, 2 New MBRs 5/19/2020 The First Class A-1 Effluent Permit in Montana 7

  8. New Plant Effluent Disposal Options • Golf Irrigation • Surface Water Discharge • Groundwater Discharge • Class A-1 Compatible with Each Option 5/19/2020 The First Class A-1 Effluent Permit in Montana 8

  9. Wastewater Treatment Selection • Existing Oxidation Ditch, 2 New MBRs Selected 5/19/2020 The First Class A-1 Effluent Permit in Montana 9

  10. Design Pre-Selection • Request for Proposals • Solicitation from 3 Manufacturers • Conducted Interviews • Three Engineers Reviewed and Scored Proposals 5/19/2020 The First Class A-1 Effluent Permit in Montana 10

  11. Design Pre-Selection • Treatment Requirements 5/19/2020 The First Class A-1 Effluent Permit in Montana 11

  12. Design Pre-Selection • MBR Requirements 5/19/2020 The First Class A-1 Effluent Permit in Montana 12

  13. Wastewater Equipment/Process Pre-Selection • Selected Suez (formerly GE) 5/19/2020 The First Class A-1 Effluent Permit in Montana 13

  14. Wastewater Equipment/Process Pre-Selection • 3 Train Bioreactors and Membrane Basins for Operational Flexibility • 4 Stage Process- Pre Anoxic, Aerobic, Post Anoxic, Membrane Basin (Aerobic) • Process Chemical Systems- Sodium Hydroxide, MicroC, and Alum • Membrane Chemical Systems- Sodium Hypochlorite and Citric Acid • ZW-500 Reinforced Hollow Fiber PVDF Membranes 5/19/2020 The First Class A-1 Effluent Permit in Montana 14

  15. Wastewater Equipment/Process Pre-Selection 5/19/2020 The First Class A-1 Effluent Permit in Montana 15

  16. New Design- Plant Overall Site Plan Existing Effluent Pond Pond 3 Existing Oxidation Ditch 5/19/2020 The First Class A-1 Effluent Permit in Montana 16

  17. Design- Plant Site Plan 5/19/2020 The First Class A-1 Effluent Permit in Montana 17

  18. Design- Process Flow Diagram 5/19/2020 The First Class A-1 Effluent Permit in Montana 18

  19. Design- Hydraulic Profile 5/19/2020 The First Class A-1 Effluent Permit in Montana 19

  20. Design- Main Building Processes Housed Indoors, Separate Headworks, Separate Chemical Rooms, Operator Lab and Offices 5/19/2020 The First Class A-1 Effluent Permit in Montana 20

  21. Design-Lower Level Area Access to Equipment, Flooded Suction for Influent Pump Station, MBR Pumping Systems, NPW and Effluent Pumping Systems 5/19/2020 The First Class A-1 Effluent Permit in Montana 21

  22. Design-Solids Handling Aerobic Digesters Equalization Screw Press Dewatering 5/19/2020 The First Class A-1 Effluent Permit in Montana 22

  23. Permitting • Plans and Specifications Review Submittal to DEQ, August 31, 2016 • Provided Additional Information About Storage Pond and Golf Irrigation. • Approved by DEQ: January 23, 2017 5/19/2020 The First Class A-1 Effluent Permit in Montana 23

  24. Permitting • Monitoring Requirements Year Total Coliform Total Nitrogen BOD 5 TSS 1 Weekly Bi-weekly Monthly Monthly 2 Monthly Monthly Quarterly Quarterly 3 Monthly Quarterly Quarterly Quarterly 4 and beyond Quarterly Quarterly Semi-annually Semi-annually 5/19/2020 The First Class A-1 Effluent Permit in Montana 24

  25. Construction • Bids Due: January 2018 • Contractor- Dick Anderson Construction • Original Contract Amount: $8.36 M • Work began May 2018 • Completed November 2019 • Final Amount: $8.63 M May 3, 2018 5/19/2020 The First Class A-1 Effluent Permit in Montana 25

  26. Construction August 3, 2018 July 3, 2018 5/19/2020 The First Class A-1 Effluent Permit in Montana 26

  27. Construction September 14, 2018 October 30, 2018 5/19/2020 The First Class A-1 Effluent Permit in Montana 27

  28. Construction • Challenge- Dry In For Work To Continue Through The Winter • Pre-Engineered Steel Buildings November 30, 2018 5/19/2020 The First Class A-1 Effluent Permit in Montana 28

  29. Construction January 7, 2019 5/19/2020 The First Class A-1 Effluent Permit in Montana 29

  30. Construction August 27, 2019 5/19/2020 The First Class A-1 Effluent Permit in Montana 30

  31. Construction • Start-Up and Seeding • ~32,000 Gallons From Big Sky County Water & Sewer District September 30, 2019 5/19/2020 The First Class A-1 Effluent Permit in Montana 31

  32. Construction-Final Completion 5/19/2020 The First Class A-1 Effluent Permit in Montana 32

  33. Construction-Final Completion Fine Screens Influent Pumps 5/19/2020 The First Class A-1 Effluent Permit in Montana 33

  34. Construction-Final Completion Bioreactors and UV Bioreactors 5/19/2020 The First Class A-1 Effluent Permit in Montana 34

  35. Construction-Final Completion Process and Membrane Blowers MBR Pumps 5/19/2020 The First Class A-1 Effluent Permit in Montana 35

  36. Construction-Final Completion Aerobic Digesters 5/19/2020 The First Class A-1 Effluent Permit in Montana 36

  37. Challenges and Approaches • Choosing Treatment and Disposal: Compile a PER to Study and Recommend a Solution • 1 st of a Kind Permitting: Research and Communicate with Regulators • Existing Infrastructure: Permitting to Allow a New Use Includes Inspections, Testing, and Reports • Construction: Managing Season and Suppliers • Start-Up: Provide Initial Operational Support 5/19/2020 The First Class A-1 Effluent Permit in Montana 37

  38. Questions? Eric Blanksma, PE eblanksma@m-m.net 406-495-3434

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend