The First Class A-1 Effluent Permit in Montana Moonlight Basin, Big - - PowerPoint PPT Presentation

the first class a 1 effluent permit in montana
SMART_READER_LITE
LIVE PREVIEW

The First Class A-1 Effluent Permit in Montana Moonlight Basin, Big - - PowerPoint PPT Presentation

The First Class A-1 Effluent Permit in Montana Moonlight Basin, Big Sky Montana Topics Effluent Reuse Treatment Selection Design & Permitting Construction Project Challenges 4/30/2020 The First Class A-1


slide-1
SLIDE 1

The First Class A-1 Effluent Permit in Montana

Moonlight Basin, Big Sky Montana

slide-2
SLIDE 2

Topics

  • Effluent Reuse
  • Treatment Selection
  • Design & Permitting
  • Construction
  • Project Challenges

4/30/2020 The First Class A-1 Effluent Permit in Montana 2

slide-3
SLIDE 3

Regulation

Montana DEQ Circular DEQ-2, Appendix B Class A-1 Standard

5/19/2020 The First Class A-1 Effluent Permit in Montana 3

slide-4
SLIDE 4

5/19/2020 The First Class A-1 Effluent Permit in Montana 4

slide-5
SLIDE 5

Moonlight Basin Resort:

  • Original Plant was a trickling

filter system treating septic tank effluent. Disposal to drainfield.

  • An oxidation ditch treatment

plant replaced the original

  • plant. Storage ponds and

disposal to forest irrigation.

5/19/2020 The First Class A-1 Effluent Permit in Montana 5

Treatment Selection

slide-6
SLIDE 6

Treatment Selection

Preliminary Engineering Report

  • Make Recommendations For

Wastewater Treatment and Disposal

5/19/2020 The First Class A-1 Effluent Permit in Montana 6

slide-7
SLIDE 7

Wastewater Treatment Alternatives

  • Single MBR
  • Existing Oxidation Ditch, 2 New Oxidation Ditches
  • Existing Oxidation Ditch, 2 New SBRs
  • Existing Oxidation Ditch, 2 New MBRs

5/19/2020 The First Class A-1 Effluent Permit in Montana 7

slide-8
SLIDE 8

New Plant Effluent Disposal Options

  • Golf Irrigation
  • Surface Water Discharge
  • Groundwater Discharge
  • Class A-1 Compatible with Each Option

5/19/2020 The First Class A-1 Effluent Permit in Montana 8

slide-9
SLIDE 9

Wastewater Treatment Selection

  • Existing Oxidation Ditch, 2 New MBRs Selected

5/19/2020 The First Class A-1 Effluent Permit in Montana 9

slide-10
SLIDE 10

Design Pre-Selection

  • Request for Proposals
  • Solicitation from 3 Manufacturers
  • Conducted Interviews
  • Three Engineers Reviewed and Scored

Proposals

5/19/2020 The First Class A-1 Effluent Permit in Montana 10

slide-11
SLIDE 11

Design Pre-Selection

5/19/2020 The First Class A-1 Effluent Permit in Montana 11

  • Treatment Requirements
slide-12
SLIDE 12

Design Pre-Selection

  • MBR Requirements

5/19/2020 The First Class A-1 Effluent Permit in Montana 12

slide-13
SLIDE 13

Wastewater Equipment/Process Pre-Selection

5/19/2020 The First Class A-1 Effluent Permit in Montana 13

  • Selected Suez (formerly GE)
slide-14
SLIDE 14

Wastewater Equipment/Process Pre-Selection

  • 3 Train Bioreactors and Membrane Basins for Operational Flexibility
  • 4 Stage Process- Pre Anoxic, Aerobic, Post Anoxic, Membrane Basin

(Aerobic)

  • Process Chemical Systems- Sodium Hydroxide, MicroC, and Alum
  • Membrane Chemical Systems- Sodium Hypochlorite and Citric

Acid

  • ZW-500 Reinforced Hollow Fiber PVDF Membranes

5/19/2020 The First Class A-1 Effluent Permit in Montana 14

slide-15
SLIDE 15

Wastewater Equipment/Process Pre-Selection

5/19/2020 The First Class A-1 Effluent Permit in Montana 15

slide-16
SLIDE 16

5/19/2020 The First Class A-1 Effluent Permit in Montana 16

Design- Overall Site Plan

New Plant Existing Oxidation Ditch Pond 3 Existing Effluent Pond

slide-17
SLIDE 17

5/19/2020 The First Class A-1 Effluent Permit in Montana 17

Design- Plant Site Plan

slide-18
SLIDE 18

5/19/2020 The First Class A-1 Effluent Permit in Montana 18

Design- Process Flow Diagram

slide-19
SLIDE 19

5/19/2020 The First Class A-1 Effluent Permit in Montana 19

Design- Hydraulic Profile

slide-20
SLIDE 20

5/19/2020 The First Class A-1 Effluent Permit in Montana 20

Design- Main Building

Processes Housed Indoors, Separate Headworks, Separate Chemical Rooms, Operator Lab and Offices

slide-21
SLIDE 21

5/19/2020 The First Class A-1 Effluent Permit in Montana 21

Design-Lower Level Area

Access to Equipment, Flooded Suction for Influent Pump Station, MBR Pumping Systems, NPW and Effluent Pumping Systems

slide-22
SLIDE 22

5/19/2020 The First Class A-1 Effluent Permit in Montana 22

Design-Solids Handling

Aerobic Digesters Equalization Screw Press Dewatering

slide-23
SLIDE 23

Permitting

  • Plans and Specifications Review

Submittal to DEQ, August 31, 2016

  • Provided Additional

Information About Storage Pond and Golf Irrigation.

  • Approved by DEQ: January 23,

2017

5/19/2020 The First Class A-1 Effluent Permit in Montana 23

slide-24
SLIDE 24

Permitting

  • Monitoring Requirements

5/19/2020 The First Class A-1 Effluent Permit in Montana 24

Year Total Coliform Total Nitrogen BOD5 TSS 1 Weekly Bi-weekly Monthly Monthly 2 Monthly Monthly Quarterly Quarterly 3 Monthly Quarterly Quarterly Quarterly 4 and beyond Quarterly Quarterly Semi-annually Semi-annually

slide-25
SLIDE 25

Construction

  • Bids Due: January 2018
  • Contractor- Dick Anderson

Construction

  • Original Contract Amount: $8.36 M
  • Work began May 2018
  • Completed November 2019
  • Final Amount: $8.63 M

5/19/2020 The First Class A-1 Effluent Permit in Montana 25

May 3, 2018

slide-26
SLIDE 26

Construction

5/19/2020 The First Class A-1 Effluent Permit in Montana 26

July 3, 2018 August 3, 2018

slide-27
SLIDE 27

Construction

5/19/2020 The First Class A-1 Effluent Permit in Montana 27

September 14, 2018 October 30, 2018

slide-28
SLIDE 28

Construction

  • Challenge- Dry In For Work To

Continue Through The Winter

  • Pre-Engineered Steel Buildings

5/19/2020 The First Class A-1 Effluent Permit in Montana 28

November 30, 2018

slide-29
SLIDE 29

Construction

5/19/2020 The First Class A-1 Effluent Permit in Montana 29

January 7, 2019

slide-30
SLIDE 30

Construction

5/19/2020 The First Class A-1 Effluent Permit in Montana 30

August 27, 2019

slide-31
SLIDE 31

Construction

5/19/2020 The First Class A-1 Effluent Permit in Montana 31

September 30, 2019

  • Start-Up and Seeding
  • ~32,000 Gallons From Big Sky

County Water & Sewer District

slide-32
SLIDE 32

Construction-Final Completion

5/19/2020 The First Class A-1 Effluent Permit in Montana 32

slide-33
SLIDE 33

Construction-Final Completion

5/19/2020 The First Class A-1 Effluent Permit in Montana 33

Fine Screens Influent Pumps

slide-34
SLIDE 34

Construction-Final Completion

5/19/2020 The First Class A-1 Effluent Permit in Montana 34

Bioreactors and UV Bioreactors

slide-35
SLIDE 35

Construction-Final Completion

5/19/2020 The First Class A-1 Effluent Permit in Montana 35

Process and Membrane Blowers MBR Pumps

slide-36
SLIDE 36

Construction-Final Completion

5/19/2020 The First Class A-1 Effluent Permit in Montana 36

Aerobic Digesters

slide-37
SLIDE 37

Challenges and Approaches

5/19/2020 The First Class A-1 Effluent Permit in Montana 37

  • Choosing Treatment and Disposal: Compile a PER to Study

and Recommend a Solution

  • 1st of a Kind Permitting: Research and Communicate with

Regulators

  • Existing Infrastructure: Permitting to Allow a New Use Includes

Inspections, Testing, and Reports

  • Construction: Managing Season and Suppliers
  • Start-Up: Provide Initial Operational Support
slide-38
SLIDE 38

Eric Blanksma, PE eblanksma@m-m.net 406-495-3434

Questions?