A present at ion for: The Cleveland City Planning Commission December 19, 2008 Presented by: The Ohio Department of Transportation and The City of Cleveland Lakefront West Purpose: Convert US-6 from high speed limited access freeway to a


  1. A present at ion for: The Cleveland City Planning Commission December 19, 2008 Presented by: The Ohio Department of Transportation and The City of Cleveland

  2. Lakefront West Purpose: Convert US-6 from high speed limited access freeway to a boulevard in accordance with Connecting Cleveland: The Waterfront District Plan Current Cost Estimate: TRAC Budget PE = $1.6M TRAC Budget DD = $3.2M TRAC Budget RW = $5.0M TRAC Budget CO = $40M TRAC Budget TOTAL = $49.8M Status: Project in Preliminary Engineering Phase

  3. Lakefront West Schedule: Stakeholder Committee Meeting – December 2, 2008 Public Meeting – December 11, 2008 Planning Commission Meeting – December 19, 2008 Preliminary Engineering/Environmental Document – 2009 Detail Design – 2010/2011* Right-of-Way Acquisition – 2011/2012** Construction – 2012/2013/2014* * New Railroad Bridge Carrying Norfolk Southern Tracks over Extension of West 73 rd Street Controls Overall Schedule ** 24 Months Required if Business Relocation Involved. *** Once Environmental Document is Approved (2009), then opportunities exist to individually advance components.

  4. Potential Early Deployment Projects Group 1 – West 76 th Street Pedestrian & Bicycle Access • Schedule: Detail Design – 2009/2010 Construction – 2010/2011 Group 2 – Multi-Purpose Trail from West 25 th Street to West 65 th Street; West 49 th Street Connection; West Blvd./Lake Ave. Connection Schedule: • Detail Design – 2009/2010 Construction – 2011/2012 Potential Safety Project Group 3 – West 28 th Street Pedestrian Improvements. Close West 28 th Street Entrance Ramp to SR 2/Main Avenue Bridge Eastbound Schedule: • TBD

  5.  Safety and Operational Improvements to the West Blvd. and Lake Ave. Intersection, including retaining and reconfiguring the existing ramps. Lakefront front West – Phase I

  6.  Rehabilitate the West 76 th St. Underpass, including improving pedestrian and bicycle access to Edgewater Park Beach. Lakefront front West – Phase I

  7.  Construct a NEW Underpass with Norfolk Southern Railroad and extend West 73 rd St. North to the West Shoreway and Edgewater Park. Lakefront front West – Phase I

  8.  Construct a NEW Underpass with Norfolk Southern Railroad and extend West 73 rd St. North to the West Shoreway and Edgewater Park. Lakefront front West – Phase I

  9.  Construct a NEW Connection (right-in/right-out) at Division Ave.  Construct a NEW Connection (right-in/right-out) at West 54 th St. Lakefront front West – Phase I or II

  10.  Reconfigure West 49 th St. Bridge to accommodate the Multi-Purpose Trail.  Safety and Operational Improvements to West 45 th St. and West 49 th St. Lakefront front West – Phase I

  11.  CLOSE Entrance Ramp from West 28 th St. to SR-2 EB. Use entrance at W. 45 th St.  Relocate the US-6 Entrance and Exit Ramps from West 25 th St. to West 28 th St.  Reconfigure the Intersection of West 25 th St./Main Ave./Washington Ave. Lakefront front West – Phase II

  12. Lakefront front West – Phase II

  13. Lakefront front West – Phase II

  14.  CLOSE the Entrance Ramp from West 28 th St. to SR-2 EB.  Relocate the US-6 Entrance and Exit Ramps from W. 25 th St. to W. 28 th St. Lakefront front West – Phase II

  15.  CLOSE the Entrance Ramp from West 28 th St. to SR-2 EB.  Relocate the US-6 Entrance and Exit Ramps from W. 25 th St. to W. 28 th St. Lakefront front West – Phase II

  16.  Construct NEW Multi-Purpose Trail from West 25 th St. to West 65 th St., Connecting the bicycle lanes on the Veteran’s Memorial Bridge with the existing Multi-Purpose Trails within Edgewater Park.  Construct NEW Multi-Purpose Trails along West Shoreway from West Blvd. to West 65 th St. Lakefront front West – Phase I and II

  17.  Reconstruct US-6 pavement, including Reconfiguring the Typical Section. Lakefront front West – Phase II

  18.  Reconstruct US-6 pavement, including Reconfiguring the Typical Section. Lakefront front West – Phase II

  19. Lakefront West Visit www.innerbelt.org then select the “Lakefront West” logo. • Project Update December 2008. • Comment Form. • Today’s presentation and graphics. Thank you.

  20. Lakefront front West – Plan

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.