Test Before Touch Test Before Touch Easier Said Than Done - - PowerPoint PPT Presentation

test before touch test before touch easier said than done
SMART_READER_LITE
LIVE PREVIEW

Test Before Touch Test Before Touch Easier Said Than Done - - PowerPoint PPT Presentation

Test Before Touch Test Before Touch Easier Said Than Done Easier Said Than Done Ken Crawford, DuPont Ken Crawford, DuPont Kent Haggerty, Dupont Kent Haggerty, Dupont Overview Overview Test Before Touch (TBT) Principles


slide-1
SLIDE 1

“ “Test Before Touch Test Before Touch” ” Easier Said Than Done Easier Said Than Done

Ken Crawford, DuPont Ken Crawford, DuPont Kent Haggerty, Dupont Kent Haggerty, Dupont

slide-2
SLIDE 2

Overview Overview

  • Test Before Touch (TBT) Principles
  • Key Learnings by One Company
  • One Method for Performing a TBT
  • Induced Voltages
  • Medium Voltage Testing
  • Summary & Conclusions
slide-3
SLIDE 3
slide-4
SLIDE 4

How Would You Verify Power is Off? How Would You Verify Power is Off?

  • What would be the plan?
  • What could go wrong?
  • What instruments to use?
  • What PPE is needed?
  • How to minimize hazards?
  • Where are the shock and arc hazards?
  • Are you qualified to work on this equipment?
slide-5
SLIDE 5

Key Learnings in One Company Key Learnings in One Company

  • TBT Not Fully Understood
  • Inadequate Training

– No Planned Approach – Best Practices Not Documented – Did Not Warn of Common Mistakes

  • Concepts Seemed Simple
  • Proper TBT Involves Knowledge and Planning
slide-6
SLIDE 6
  • Consider All Circuits Energized Until Tested
  • Test EVERY Conductor To Be Touched
  • PPE Is Required Until Test is Completed
  • Test Instrument Must Be Verified
  • Knowledge of Equipment Is Essential
  • Test Circuit Again If Job Continuity Is Broken
  • Testing Must Be Done At Each Location

Where Conductors Are Going To Be Touched

“ “Test Before Touch Test Before Touch” ” (TBT) (TBT) Key Principles Key Principles

slide-7
SLIDE 7

Protect the Person

Shock Protection

“#” indicates US ANSI voltage class “00” rated 500 volts; “2” rated 17,000 volts

Arc Flash Protection

slide-8
SLIDE 8

Selecting The Proper Tester Selecting The Proper Tester

  • Zero Indication Must Mean No Voltage

Present

  • Testers With Limitations

– Multi-meters Can Be on Wrong Setting – Some Solenoid Testers May Not Always Indicate – Proximity Testers May Give False Indication

  • Voltage Only Tester Should Be Used for TBT
  • No Single Voltage Tester Will Cover All

Applications

slide-9
SLIDE 9

Solenoid Tester Limitations Solenoid Tester Limitations

Solenoid testers may not indicate backfeed Solenoid testers may not indicate backfeed from control power transformer from control power transformer

M

C A B

Control Power Transformer Ground Test Point 120V 480V

V

C

Solenoid Will Solenoid Will NOT NOT Activate Due to Impedance Activate Due to Impedance

  • f Transformer and Tester
  • f Transformer and Tester

Solenoid Testers With Voltage Indicating Solenoid Testers With Voltage Indicating Lights Are Preferred Lights Are Preferred Blown Fuse Ground Test Point

slide-10
SLIDE 10

Limitations of Proximity Testers Limitations of Proximity Testers

Multi Multi-

  • Conductor or Shielded Cables

Conductor or Shielded Cables Require Special Attention Require Special Attention Proximity Tester Reads Energized Conductor Ground Conductor Shields Energized Conductor

slide-11
SLIDE 11

Proximity Tester Limitations Proximity Tester Limitations for Low Voltage Testing for Low Voltage Testing

  • Detects AC Voltage Only
  • Will Not Indicate Voltage Inside

– Grounded Enclosures – Shielded Cables – Internally Wet Cables

  • May Not Indicate Voltage if

– Cable is Partially Buried – Insulated Test Point is Against Grounded Metal – Operator Isolated From Ground

slide-12
SLIDE 12

Testing Method on Testing Method on Low Voltage Circuits Low Voltage Circuits

1.

Test Ground to Phase for all Phases

– Keeps Meter at Zero Volts for Most of the Test – Voltage Usually Lower (e.g. 277 Vs. 480)

  • 2. Test Neutral to Phase (if available)

– Provides Backup Test to Ground to Phase

  • 3. Test Phase to Phase (if available)

– Check Each Phase to All Other Phases (A-B,A-C,B-C) – May be Only Valid Test on Ungrounded Systems

slide-13
SLIDE 13

Steps in Performing Steps in Performing Absence of Voltage Absence of Voltage Tests Tests

slide-14
SLIDE 14

Step 1 Step 1 -

  • Probing Position

Probing Position

  • Place the Red Lead in the Meter

– Reduces Risk of Contact

  • Black Lead Placed on Ground First and

Removed Last

tester

slide-15
SLIDE 15

Step 2 Step 2 -

  • Check Meter

Check Meter

  • Verify Meter on Energized Source Before & After

Test

  • Source Must Be Same Type (AC or DC) As The

Equipment To Be Tested.

slide-16
SLIDE 16

Step 3 Step 3 -

  • Verify Circuit Is

Verify Circuit Is “ “Off Off” ”

  • Verify the Circuit Requiring Work is Turned "Off"

And Any Disconnect Knife Blades Are Open

Knife Blades Are Open

slide-17
SLIDE 17

Step 4 Step 4 -

  • Ground to Phase Test

Ground to Phase Test

  • Must be Absolutely Certain of a Reliable Ground

– If Not Sure, Test Ground Point

  • Reliable Ground Point Depends on Equipment

t

slide-18
SLIDE 18

Step 4 Step 4-

  • Ground to Phase Test

Ground to Phase Test -

  • Cont.

Cont. Ground Test Point Depends on the Equipment Ground Test Point Depends on the Equipment

Reliable Ground Test Point Reliable Ground Test Point Not a Reliable Ground Test Point

slide-19
SLIDE 19

Reliable Ground Test Point Not a Reliable Ground Test Point Not a Reliable Ground Test Point

Step 4 Step 4 -

  • Ground to Phase Test

Ground to Phase Test -

  • Cont.

Cont. Ground Test Point Depends on the Equipment Ground Test Point Depends on the Equipment

slide-20
SLIDE 20

Test Points Test Points

  • The Load Side of Switch Should be Tested First
  • Never Use Fuse Caps (Ferrules) as a Test Point

– Some Fuses Have Insulated Ferrules Don’t Test Here

slide-21
SLIDE 21

Test Points (cont Test Points (cont’ ’d) d)

Phase Test Points

Test on the Fuse Holder Not the Fuse

slide-22
SLIDE 22

Step 5 Step 5 -

  • Phase to Phase Test

Phase to Phase Test

  • Check Phase to Phase Even if Ground to

Phase Checks Indicate "0" Volts

– Provides Backup Check – May Be Only Valid Test on Ungrounded Systems

  • Phase to Phase Test Alone Is Not Sufficient
slide-23
SLIDE 23

C A B

Blown Fuses

  • r faulty

switch

Phase Phase-

  • to

to-

  • Phase Test Limitations

Phase Test Limitations

Meter Meter Does Not Does Not Indicate Voltage Indicate Voltage

xxxxxxx xx voltmeter voltmeter V V

Proximity Tester Does Indicate Voltage

slide-24
SLIDE 24

Task: Replace Motor T Task: Replace Motor T-

  • Leads in

Leads in a a 3 Phase Motor Starter 3 Phase Motor Starter

What Are The Minimum What Are The Minimum Number of Tests Required? Number of Tests Required?

slide-25
SLIDE 25

C A B

Control Power Transformer 120V 480V

Motor Test Points M

Testing to Remove Motor Leads for Testing to Remove Motor Leads for 480V Starter 480V Starter

A Total of 12 Tests Are Required A Total of 12 Tests Are Required 6 Ground To Phase & 6 Phase to Phase 6 Ground To Phase & 6 Phase to Phase

slide-26
SLIDE 26

Voltage Measured on Voltage Measured on “ “De De-

  • energized

energized” ” LV Circuit, What Do You Do? LV Circuit, What Do You Do?

  • Verify Proper Circuit & Equipment

– Check Prints, Labels, Resources

  • Determine if Voltage is Induced

– Detected by Meters With High Input Z ~ 10 M Ω – Low Input Z Meters Collapse Induced Voltage Z~ 2 kΩ – Verify Voltage Collapses to “0” With Low Z Tester

  • Voltage Still Present After Loading Circuit

– Check for Backfeed, Equipment Failure

slide-27
SLIDE 27

Close Coupling in Cable Tray Close Coupling in Cable Tray

V

High Z Digital Meter Reading 95V High Z Digital Meter Reading 95V Analog Meter Reading 80V Analog Meter Reading 80V Low Z Digital Meter Reading 0V Low Z Digital Meter Reading 0V

Induced Voltage Value Depends Induced Voltage Value Depends

  • n Meter Impedance
  • n Meter Impedance
slide-28
SLIDE 28

Testing Insulated Conductors

slide-29
SLIDE 29

Testing Insulated Conductors Testing Insulated Conductors

  • Use a Proximity Tester for a First Test
  • Should Not Be Used as the Only Test
  • If No Voltage Indicated

– Wearing PPE, Expose Conductor For Testing – Verify “0” Volts With Contact Meter

  • Voltage Indicated with Proximity Tester

– Verify Proper Circuit is Locked out – Re-Check source for Induced Voltage Using a High Impedance Meter – If Voltage is Present, Load Circuit at Switch with a Low Impedance Meter and Re-check Insulated Conductor

slide-30
SLIDE 30

V

Verifying Induced Voltage on Insulated Verifying Induced Voltage on Insulated Conductors Conductors

Low Impedance Meter Proximity Tester Indicates Induced Voltage on Insulated Conductor Proximity Tester Does Not Indicate Voltage Due to Circuit Loading by Low Impedance Meter Proximity Tester

slide-31
SLIDE 31

Testing Testing Medium Medium Voltage Voltage Circuits Circuits

slide-32
SLIDE 32
slide-33
SLIDE 33

Considerations in Testing Considerations in Testing Medium Voltage Systems Medium Voltage Systems

  • Proximity Testers Often Preferred Due to

Strong Electric Fields

– Direct Contact Not Required – Only One Probing Stick Needed – Can Test Taped Connections

  • Shielded Conductors Cannot Be Tested

Except at Terminal Connections

– Spiking Tool May Be Necessary to Verify Shielded Conductors Are De-energized

slide-34
SLIDE 34

Shielded Cable - Proximity Tester Will Not Indicate

tttT

Proximity Tester Will Work Here Medium Voltage Medium Voltage Shielded Cables Require Shielded Cables Require Special Attention Special Attention Cable Shield Terminates Here

slide-35
SLIDE 35

Which Shielded Cable Is De Which Shielded Cable Is De-

  • Energized?

Energized?

slide-36
SLIDE 36

Gauss Meter For Cable Identification Gauss Meter For Cable Identification

slide-37
SLIDE 37

Spiking Tool Spiking Tool

slide-38
SLIDE 38
slide-39
SLIDE 39

Summary & Conclusions Summary & Conclusions

  • Consider All Circuits Energized Until Tested
  • Training and Knowledge Required
  • Plan for Testing
  • Use Proper Voltage Tester
  • Use Appropriate PPE
  • Test Before Touch Not Always Simple
slide-40
SLIDE 40

Test Test Every Circuit, Every Every Circuit, Every Conductor, Every Time Conductor, Every Time Before Before You You Touch! Touch! It Could Save It Could Save Your Your Life! Life!

slide-41
SLIDE 41

“Test Before Touch” Easier Said Than Done Questions?