Terramin General Update Matt Daniel Environment and Community S uperintendent Angas Zinc Mine 1 Angas Zinc Mine Ongoing management of site weed control and revegetation During the quarter observed a family of White-browed


slide-1
SLIDE 1

Terramin General Update

Matt Daniel – Environment and Community S uperintendent Angas Zinc Mine

1

slide-2
SLIDE 2

Angas Zinc Mine

 Ongoing management of site – weed control and revegetation

 During the quarter observed a family of White-browed Babblers, first seen on site in 7 years  Picture shows a Little Eagle, taken on AZM (M.Ankor)

 Hydrostor - progress

 Compressed Air Energy S

torage

 Presentation tonight

slide-3
SLIDE 3

Terramin Update

Appointed new CEO – Richard Taylor

 Bachelors of Economics and Law – University of Newcastle  Master of Laws –ANU  Master of Business Administration – Cambridge  Member of Australian Institute of Company Directors  Panaust Asia  Managing Director, copper gold mine, Laos  MMG (Oxiana)  Asia and Country Manager  S

epon copper/ gold mine, Laos

 Department of Foreign Affairs and Trade  World Bank – S

ustainable Energy, Oil, Gas and Mining

slide-4
SLIDE 4

Terramin - Proj ects

 Bird in Hand / Angas Processing Facility

 Beginning t o receive feedback from DEM on BIH ML Proposal

 Draft AZM MPL being reviewed externally prior to the draft being lodged

with DEM

 S

till waiting on DEM approval to begin Managed Aquifer Recharge drilling at BIH

 Tala Hamza  Mining lease application being reviewed by government agencies  Completion of mining lease application ready to be submitted subj ect to

j oint resolution of the Tala Hamza partners

 Continued engagement with the Algerian regulator and government.

slide-5
SLIDE 5

Quarterly Environment Report

Matt Daniel – Environment and Communit y S uperint endent

5

slide-6
SLIDE 6

Activities over Q1

 Annual Compliance report

submit t ed in March

 Continued drafting of MPL for

Angas Processing Facility

 Updated stormwater design

for MPL –AECOM

 S

light cat chment change

slide-7
SLIDE 7

Angas Zinc Mine – Quarterly Environment Report

No non-compliances against lease Conditions for Quarter 1, 2018

Correction to QER

No non-compliance against PM10 Outcome Measurable Criteria

Review: “ PM10 dust levels collected from the HiVol PM10 sampler located at the visitors viewing area (Figure 44 - same location as the HiVol sampler), will be sampled over a 24hour period every six days as per AS , 3580.9.3:2003 standards. Data will demonstrate compliance with NEPM 1998 criteria of <50 micrograms/ m3 per 24 hour period with <5 days exceedances per year.”

Terramin still conducted investigation as to why

slide-8
SLIDE 8

Angas Zinc Mine – Quarterly Environment Report

17th March 2018 - Saturday

PM10 measured 55ug/ m3 over 24 hours

Unusual - Investigation showed wind direction towards operational area all day, not away from

  • perational area

No activities being undertaken at AZM

No southerlys, south-westerlys, or south-easterlys

65km/ hr onsite

0.00% 2.00% 4.00% 6.00% 8.00% 10.00% 12.00% N NE E W NW 0-5 5-10 10-15 15-20 20-25 25-30 30-35 35-40 40-45 >50

slide-9
SLIDE 9

Tailings S torage Facility

S urface area remains at approximately <5000m2

Water level is approximately 67.68m RL (compliance is 74.2m RL)

S eepage drains remain lowest they’ ve been in last 2 years – approx. ≈ 1L/ min

Cadmium spike in TS F B and D reviewed by ATC Williams and unrelated to TS F

0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 Jan-2016 Mar-2016 May-2016 Jul-2016 S ep-2016 Nov-2016 Jan-2017 Mar-2017 May-2017 Jul-2017 S ep-2017 Nov-2017 Jan-2018

Flow Rate (Litres/ minute)

TS F Drain Flow Rates

Drain 1 Drain 2 Drain 3 Drain 4 Drain 5 Tot al Flow (L/ min)

slide-10
SLIDE 10

Closure Plan Fact S heets

Up in Visitor’s Viewing Platform at AZM

Copies available for Community Access areas (actions outstanding from last meeting)

See Matt after meeting to

  • btain a set
slide-11
SLIDE 11

Questions?

slide-12
SLIDE 12

Hydrostor A-CAES System Basics

slide-13
SLIDE 13

Terramin Zinc Mine A-CAES System

slide-14
SLIDE 14

Benefits for Australia

Fossil Plant Replacement

  • Repurpose decommissioned thermal plants and defer

remediation costs

  • Re-use of existing interconnection and infrastructure
  • Synchronous generation for reliability, without emissions

Transmission Deferral

  • Non-wires alternatives to defer grid network investment
  • Alleviates grid congestion during peak periods
  • Locatable reliable power for critical areas and infrastructure

Renewable Integration

  • Provide dispatchable, base loaded renewables
  • Optimize solar/wind project economics through time-shifting
  • Reduce curtailment

Mines / Large Industrial

  • Ability to eliminate fuel costs & logistics (off-grid)
  • Improve reliability and reduce electricity grid charges (on-grid)
  • Re-use legacy mining infrastructure

14