Terramin General Update
Matt Daniel – Environment and Community Superintendent Angas Zinc Mine
1
Terramin General Update Matt Daniel Environment and Community - - PowerPoint PPT Presentation
Terramin General Update Matt Daniel Environment and Community Superintendent Angas Zinc Mine 1 Angas Zinc Mine New CEO and CFO Richard Taylor (CEO), Simon Iacopetta is our new CFO Attended SA Investment in Mining and Exploration
Matt Daniel – Environment and Community Superintendent Angas Zinc Mine
1
New CEO and CFO
Richard Taylor (CEO), Simon Iacopetta is our new CFO
Attended SA Investment in Mining and Exploration Conference – see here for
Richards presentation - https://www.terramin.com.au/category/asx- announcements/
Newsletter released includes update on Terramin’s gold strategy Hydrostor - progress
Going through regulatory steps Consultants onsite for planning and design specifications
Environmental Engineering
students
Soil study Hydrochar for soil amendment
from hydrothermal carbonisation of biomass
Grapemark and micro-algy Native grasses
Bird in Hand / Angas Processing Facility
Draft AZM MPL being reviewed by DEM for checks against Ministerial
Determination prior to formal lodgment with BIH ML
Managed Aquifer Recharge bore drilling at BIH has commenced this week –
still waiting for guidance on testwork component from DEM
Tala Hamza Mining lease application being reviewed by government agencies Completion of mining lease application ready to be submitted subject to
joint resolution of the Tala Hamza partners
Continued engagement with the Algerian regulator and government.
Matt Daniel – Environment and Community Superintendent
5
Care and Maintenance air and water monitoring
Regional groundwater Angas River Regional and onsite dust monitoring
Draft MPL for Angas Processing Facility completed and
sent to DEM for checks against Ministerial Determination
Hydrostor have been onsite for planning and design
purposes
Managing Director Greg Allen here tonight
No non-compliances against Lease Conditions for Quarter 2, 2018
Continued instances of higher dust offsite
Agricultural activities through the region
Wind direction towards the North East
All higher dust (Total Insoluble Matter) located north-west of site
Melaleuca lanceolata
Healthy resident water birds
Surface area remained approximately 7000m2 for Q2
Water level is approximately 68.1m RL (compliance is 74.2m RL)
Seepage drains remain at approx. ≈ 1L/min
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 Jan-2016 Feb-2016 Mar-2016 Apr-2016 May-2016 Jun-2016 Jul-2016 Aug-2016 Sep-2016 Oct-2016 Nov-2016 Dec-2016 Jan-2017 Feb-2017 Mar-2017 Apr-2017 May-2017 Jun-2017 Jul-2017 Aug-2017 Sep-2017 Oct-2017 Nov-2017 Dec-2017 Jan-2018 Feb-2018 Mar-2018 Apr-2018
Flow Rate (Litres/minute)
TSF Drain Flow Rates
Drain 1 Drain 2 Drain 3 Drain 4 Drain 5 Total Flow (L/min)
Information on
New strategy New CEO Drilling at Bird in Hand Water test work
Department for Energy and Mining 11 Waymouth Street Adelaide, South Australia 5000 GPO Box 320 Adelaide, South Australia 5001 T: +61 8 8429 2450 M: +61 475 819 262 E: Mark.Stewart2@sa.gov.au