technical presentation to city of victoria council june
play

Technical Presentation to City of Victoria Council June 14, 2010 - PowerPoint PPT Presentation

Technical Presentation to City of Victoria Council June 14, 2010 With: Stafford Bandlow | Jonathan Yardley Architects | Wilkinson Eyre Architects | H.W. Lochner| Advicas Quantity Surveyors| Sharp and Diamond | CN Ryzuk & Associates


  1. Technical Presentation to City of Victoria Council June 14, 2010 With: Stafford Bandlow | Jonathan Yardley Architects | Wilkinson Eyre Architects | H.W. Lochner| Advicas Quantity Surveyors| Sharp and Diamond | CN Ryzuk & Associates

  2. Presentation Outline • Project Requirements – Project Objectives – Seismic Considerations – Rail Considerations – Lane Considerations • Replacement Option • Rehabilitation Option • Technical Questions • Costs • Economic Impact • Summary 6/13/2010 2

  3. Project Objectives – 1 • Replace or rehabilitate the JSB to provide for safe and long-lasting infrastructure and as a traffic calmed corridor • Provide 2-lanes outbound and 1-lane inbound • Provide on-street bike lanes • Provide pedestrian walkway (south side) • Provide multi-use path (north side) • Provide dedicated rail crossing • Improve navigation channel to be in accordance with current standards 6/13/2010 3

  4. Project Objectives – 2 • Provide improved cycling/pedestrian/vehicular access at bridge heads to minimize conflict & improve safety • Integration with existing and proposed pathways • Seismic performance to M8.5 earthquake • 100 year service life • Maintain traffic flow during construction (vehicles, marine, pedestrians, bikes) • Meet historic guideline requirements including “ Standards and Guidelines for the Conservation of Historic Places in Canada” and “City of Victoria Old Town Guidelines”. 6/13/2010 4

  5. Seismic Considerations • 35% probability of major quake (M7.0 to M7.9) in next 50 years • Recent earthquake in Washington (2001) was M6.8 • Existing Johnson Street Bridge will collapse in less than M6.5 earthquake (2009 Condition Assessment) • Point Ellice Bridge upgraded in 2001 to not collapse in a M6.5 earthquake but repairs would be needed. No Emergency Access after M6.5. • Required seismic performance driven by life safety, disaster response, protection of investment, post- disaster economic recovery. 6/13/2010 5

  6. Seismic Considerations* Seismic Design After M6.5 After M8.5 Category Earthquake Earthquake Lifeline No damage No collapse Repair needed Other No collapse Replacement needed Repair needed * Earthquake magnitudes (M) have been referenced rather than design seismic events to provide a point of reference for non-technical audience 6/13/2010 6

  7. Seismic Considerations • Recommendation: Replacement bridge be designed for M8.5 earthquake • Recommendation: Rehabilitated bridge be designed for M8.5 earthquake Note: Potential for loss of major investment if seismic performance is reduced below M8.5. 6/13/2010 7

  8. Railway Considerations • Base options for replacement & rehabilitation include railway bridge with station on downtown side • Significant savings realized in all options if railway terminated in Victoria West • Existing rail bridge could be converted to multi-use trail with rehabilitation option • Replacement bridge could be narrowed • Corridor for potential future commuter rail should be preserved 6/13/2010 8

  9. Roadway Bridge - Lane Considerations • Base options for replacement & rehabilitation include 2 westbound and 1 eastbound lanes of traffic • Trip growth of at least 40% expected by 2026 per Regional Growth Strategy & Travel Choices • Elimination of 1 westbound lane results in LOS F with queuing/congestion past Government Street and past Yates Street • Emergency responders are concerned that lane reductions and more congestion will increase response times. 6/13/2010 9

  10. Replacement Option 6/13/2010 10

  11. Replacement Option - Scope Establish trail head for Improved navigation Galloping Goose / Trans channel in accordance with Canada Trail current regulations multi-use trail with Main bridge with 3 lanes, on Elimination of “S” curve and connection to street bike lanes, rail. install traffic signal Galloping Designed as a traffic calmed Goose/ENR Trail corridor. Improved downtown approaches including Integration with Harbour sidewalks along west of Pathway Wharf St. Pedestrian Sidewalk with connections to adjacent pathways Consolidated green space New Railway Station 6/13/2010 11

  12. Replacement Option - Scope Multi-Use Sidewalk Road/Train/On-Street Bike Deck Trail 5.0 m 3 -3.0 m 1.8 m 1.8 m 2.5 m 5.0 m 6/13/2010 12

  13. Replacement Option - Scope 6/13/2010 13

  14. Replacement Option - Scope 6/13/2010 14

  15. Replacement Option - Scope • New bridge to north of existing • “S” curve removed with new signal added at Harbour and Esquimalt • 30 km/h retained and landscaping added to provide traffic calming • Vehicle traffic flow maintained during construction (no closures) • 2-lanes outbound; 1-lane inbound • On-street bike lanes • Pedestrian walkway (south side) • Multi-use pathway (north side) 6/13/2010 15

  16. Replacement Option - Scope • Dedicated rail crossing • Integration with existing pathways on east and west • Upgraded navigation channel • No collapse after M 8.5 earthquake • 100 year design life • Meets historic / aesthetic guidelines 6/13/2010 16

  17. Replacement Option – Schedule* Year Activity 2011 Complete design & tender 2012 Remove rail bridge & procure/fabricate long lead time components; foundations 2013 Continue construction 2014 Complete construction & open new bridge 2015 Remove old roadway bridge * Based on conventional delivery (Design-Bid-Build) 6/13/2010 17

  18. Replacement Option – Staging 2011/2012 Early 2015 2013/2014 Under Construction 6/13/2010 18

  19. Rehabilitation Option 6/13/2010 19

  20. Rehabilitation Option - Scope Navigation channel width is Establish trail head for limited by existing bridges Galloping Goose / Trans Canada Trail New multi-use trail bridge with Rehabilitated railway bridge connection to Green space remains “Land- Galloping Locked” (similar on east) Goose/ENR Trail Existing railway station Existing downtown Rehabilitated existing road approach roads with No dedicated on-street bike bridge with improved deck improved sidewalk along lanes for bikes; new sidewalk Wharf Street decking Existing “S” curve 6/13/2010 20

  21. Rehabilitation Option - Scope Multi-Use Sidewalk Trail Rail Deck 2.5m Road Deck, Bridge 5 m 3-3 m lanes 5 m 6/13/2010 21

  22. Rehabilitation Option - Scope 6/13/2010 22

  23. Rehabilitation Option - Scope 6/13/2010 23

  24. Rehabilitation Option – Scope • New 5 m wide multi-use trail bridge to the north • Replace all electrical/mechanical systems • Upgrade road and railway bridges to withstand M8.5 earthquake • Repair corrosion and repaint for road and railway bridges • New non-skid riding surface on road bridge for on-street bikes • Existing pedestrian walkway on south side of road bridge improved with new non-slip deck 6/13/2010 24

  25. Rehabilitation Option - Scope 6/13/2010 25

  26. Rehabilitation Option – Future Maintenance Repair* Frequency Starting ** Paint touch-up and steel repairs 5 years 2020 Repaint and steel repairs 15 15 years 2030 years Approach span concrete deck Once 2035 replacement * Full closures of several month durations are anticipated for future rehabilitation works ** Assuming completion of construction in 2015 6/13/2010 26

  27. Future Maintenance – Both Options Repair Frequency of Repairs (years) Rehabilitation Replacement Existing New Multi-Use Bridges Trail Bridge Annual Maintenance annually annually annually Engineering Inspections bi-annual bi-annual bi-annual Paint Touch-Up 10 5 10 Repairs to wearing surface 5 5 --- Electrical Mechanical Repairs once once once Repaint 20 15 20 Approach Span deck replacement --- once --- Repave 15 15 --- 6/13/2010 27

  28. Rehabilitation Option – Schedule* Year Activity 2011 Complete design & tender 2012 Procurement/fabrication of long lead time components, site preparation, foundations 2013 Construct new multi-use trail bridge and continue with upgrade to existing bridge foundations 2014 Rehabilitate railway bridge 2015 Rehabilitate road bridge Early 2016 Open * Based on conventional delivery (Design-Bid-Build) 6/13/2010 28

  29. Rehabilitation Option – Staging 2015 2011/2012 2013 Early 2016 2014 Under Construction Detour 6/13/2010 29

  30. Rehabilitation Option – Construction Impacts • Traffic limited to 2-lanes for 1 year with Multi- Use Trail Bridge available for detour.* • Transit, commercial vehicles, trucks, pedestrian & bike access reduced during construction * Note: 12 month full closure if Multi-Use Trail Bridge is not available for detour. 6/13/2010 30

  31. Technical Questions 6/13/2010 31

  32. Replacement Option ($ millions) Cost Item 2008 Estimate Class “C” Difference Estimate Construction Items* Mobilization, site preparation, traffic 1 3 +2 management 3 3 0 Demolition of existing bridges 44 48 +4 New bridge Civil works (includes Telus duct, 5 6 +1 contaminated soil) Subtotal Construction 53 60 +7 Contingency (15%) 4 9 +5 Engineering 6 8 +2 Property 0 1 +1 Escalation, Financing, taxes 0 11 +11 Total Estimated Cost 63 89 +26 * General conditions provided in detailed estimate distributed to other construction items to reflect bid numbers 6/13/2010 32

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend