t n e m u c - Central Section - o D Fixed Installation Noise - - PowerPoint PPT Presentation

t n e m u c
SMART_READER_LITE
LIVE PREVIEW

t n e m u c - Central Section - o D Fixed Installation Noise - - PowerPoint PPT Presentation

t n e m u c - Central Section - o D Fixed Installation Noise (D25) y c a Design Process Fixed Plant g e L g EHSG Meeting, July 2012 n i n & r a e L This document is shared for the purposes of learning legacy. It is


slide-1
SLIDE 1
  • Central Section -

Fixed Installation Noise (D25) Design Process – Fixed Plant

EHSG Meeting, July 2012 &

L e a r n i n g L e g a c y D

  • c

u m e n t

This document is shared for the purposes of learning legacy. It is a snapshot in time and hence many of the links within the document will become obsolete over time. Some links/document references will refer to a document storage location that isn't accessible. Users should refer to the learning legacy website where these documents may be published separately.

slide-2
SLIDE 2

Contents

  • Part 1

IPD25 Targets & Status Update

  • Part 2

Engineering & Contractual Context

  • Part 3

Application of Crossrail Design Criterion to the Design Process

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-3
SLIDE 3

IPD25 – Targets & Status Update

Part 1 L e a r n i n g L e g a c y D

  • c

u m e n t

slide-4
SLIDE 4

IPD25 – Targets

  • D25 Targets – BS4142 Approach

+5dB above Background ‘Crossrail Assessment Criterion’ Noise Levels Relative to Background

  • 5dB below Background

‘Further Endeavours’ 10dB ‘Reasonable Endeavours’ Range 0dB Background

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-5
SLIDE 5

IPD25 – Fixed Installations

Main Fixed Plant Noise Sources:

  • Tunnel Ventilation Fans,
  • Mechanical Plant at Crossrail Buildings (e.g.

ventilation and air conditioning equipment)

  • Electrical Trackside Equipment
  • Power Supply Facilities (e.g. Transformers)

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-6
SLIDE 6

IPD25 – Assessment Assumptions

  • Conservative approach currently adopted

for Reference Design:

  • IPD25 refers to ‘normal operation’
  • However, FDC assessments are based
  • n Tunnel vent congested-mode, late

at night or early morning

  • In practice, a very unlikely scenario,

hence considered to be worst-case

  • Conventional plant assumed 24/7

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-7
SLIDE 7

IPD25 – Assessment

  • Preliminary assessments are based on:
  • BS4142 Rating Method
  • Cumulative impact of site development
  • Determined at worst-affected receptor
  • +5dB character correction in all cases
  • Typical operational hours over a week
  • Predicted for the worst 5-mins (night)
  • Additional allowances for calculation

uncertainty

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-8
SLIDE 8

IPD25 – Status Update

  • Engagement of Framework Design

Consultants (FDCs)

  • Development of Reference Designs by FDCs

for Power, Portals, Stations and Shafts

  • Presently 22 Development Sites have been

considered

  • 10 - Forced Ventilation Shaft Sites
  • 12 – Sites with other Fixed Installations

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-9
SLIDE 9

IPD25 – Status Update

  • Development of the Method for Establishing

Background Noise Levels for IPD25

  • FDC Background Noise Surveys/Reporting

using the standard grid of LA90,1hr dB values:

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-10
SLIDE 10

IPD25 – Status Update

  • ‘Jointly Established’ & Agreed Background

Noise Levels with Local Authorities

  • Preliminary D25 Noise Assessments of

FDC Reference Design – Reviewed by CRL

  • Individual D25 Presentations to Local

Authorities by Station FDCs

  • Next step: D25 Communication to Local

Authorities of Preliminary Assessment Findings (Worst-case Cumulative Levels)

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-11
SLIDE 11

IPD25 – Status Update

  • IPD25 Contract Specifications Completed

and Included in the relevant tender packages (ITTs) as follows:

  • 1. Deep-Level Stations
  • 2. Shafts and Portals
  • 3. Surface Rail and Surface Stations
  • 4. Tunnel Ventilation (Systemwide)
  • 5. Traction Power Transformers

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-12
SLIDE 12

Engineering & Contractual Context

Part 2 L e a r n i n g L e g a c y D

  • c

u m e n t

slide-13
SLIDE 13

Engineering & Contractual Context

Context: IPD25 Introduction - Paragraph 1.5 “To avoid a significant noise impact from the tunnel forced ventilation fans, noise attenuators will be designed and installed on each side of the tunnel ventilation fans, as necessary to meet the Crossrail assessment criterion for fixed plant” The preliminary assessments support the above, indicating that the tunnel ventilation fans are the most significant fixed installation noise sources on the Crossrail project

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-14
SLIDE 14

Crossrail - Central Section Works

  • Tunnel structures and station, intermediate

shaft and portal structures & mechanical and electrical systems

  • Systemwide (railway systems, tunnel systems)
  • Complexity:

– Complex packaging of delivery responsibility – Complex project timeline

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-15
SLIDE 15

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-16
SLIDE 16

High Level Timeline

2009 2011 2010 2012 2013 2015 2014 2017 2016 2018

Tunnelling / Civil Works Tunnels / Station / Shaft / Portal Detail Design Station / Shaft / Portal Mechanical & Electrical Fit Out Equipment Procurement Systemwide Detail Design

Space proofing frozen

Systemwide Installation

Now

Systemwide Procurement Systemwide Reference Design

Provisional Findings Demonstration Reports

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-17
SLIDE 17

Summary of Responsibilities

  • C610 – Systemwide Main Works Contract

includes detail design and provision of the Tunnel Ventilation System for central section

  • Station contractors will be responsible for the

buildings’ ventilation and air-conditioning plant

  • Preliminary assessments by station and shaft

designers indicate that the Tunnel Ventilation System is the fixed installation with the dominating noise contribution

  • C610 and station contractors will interface

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-18
SLIDE 18

Tunnel Ventilation System

  • Required to:

– Relieve pressure resulting from train movements

→ Draught Relief Shafts

– Remove heat dissipated by running trains

→ Under Platform Extract

– Cool trains stationary in tunnel (Cooling / Congestion)

→ Cooling

– Control smoke from a train fire

→ Smoke Control (Emergency Situation)

– Provide ventilation during tunnel maintenance activities

→ Maintenance Ventilation

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-19
SLIDE 19

Draught Relief Shafts

  • Needed to relieve the pressure generated by

train movements

  • Provides passive ventilation and cooling

Ground Level Ground Level

Tunnel Entrance Draught Relief Shaft Station Draught Relief Shaft Draught Relief Shaft

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-20
SLIDE 20

Under Platform Extract

Ground Level Ground Level

Station UPE Draught Relief Shaft Draught Relief Shaft

  • Required to remove heat from trains stopped at

the station

  • Provides active cooling of tunnel

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-21
SLIDE 21

Cooling / Congestion

  • Required to cool trains stationary in Tunnel
  • Only required if Train remains stationary in the

tunnel for more than 6 minutes

Ground Level Ground Level

Tunnel Entrance Draft Relief Shaft Station Draft Relief Shaft Draft Relief Shaft Forced Vent Shaft

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-22
SLIDE 22

Smoke Control - Fire in Tunnel

  • Required to Control Smoke

Ground Level Ground Level

Tunnel Entrance Draught Relief Shaft Station Draught Relief Shaft Draught Relief Shaft

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-23
SLIDE 23

Smoke Extract - Fire in Station

  • Required to extract smoke
  • Keeps station evacuation routes clear of smoke

Ground Level Ground Level

Tunnel Entrance Draught Relief Shaft Station Draught Relief Shaft Draught Relief Shaft Forced Vent Shaft

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-24
SLIDE 24

Route Map

Station with Cooling & Draught Relief Station with Cooling, UPE & Draught Relief Intermediate Shaft with Cooling only Intermediate Shaft with No Tunnel Ventilation Paddington Bond Street Tottenham Court Road Fisher Street Liverpool Street Farringdon Whitechapel Stepney Green Mile End Eleanor Street Canary Wharf Limmo Woolwich

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-25
SLIDE 25

Typical Station Section

Typical Dimensions:

  • Fan Size: 2.8m diameter
  • Duct Size: 30m^2
  • Attenuator Dimensions:
  • 3m long
  • 60m^2

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-26
SLIDE 26

Typical intake / outlet arrangement

Residential receptor

FV DRS

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-27
SLIDE 27

Operational Modes

  • Under Platform Extract (UPE)

– Cooling of trains running normally

  • Cooling / Congestion (Worst Case Noise)

– Cooling of stationary trains in tunnel

  • Maintenance

– Ventilation of tunnel maintenance activities – Tunnel Ventilation System test

  • Smoke Control

– Noise not considered because emergency response

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-28
SLIDE 28

Noise Propagation Paths - Under Platform Extract Mode

Ground level Bored Tunnel Draught Relief Shaft Forced Ventilation Shaft Under Platform Extract (UPE) System Side Attenuation Atmosphere Side Attenuation Tunnel Isolation Damper UPE Damper DRS Damper Open Damper Active Fan Bored Tunnel Draught Relief Shaft Under Platform Extract (UPE) Tunnel Isolation Damper UPE Damper DRS Damper Station Plant Receptor Fan Isolation Damper Fan Isolation Damper Fan Isolation Damper Inactive Fan Closed Damper Fan (UPE Duty) Noise Airflow (Piston Effect) Noise Station Plant Noise

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-29
SLIDE 29

Noise Propagation Paths - Cooling Mode (Worst Case Noise)

Ground level Bored Tunnel Draught Relief Shaft Forced Ventilation Shaft Under Platform Extract (UPE) System Side Attenuation Atmosphere Side Attenuation Tunnel Isolation Damper UPE Damper DRS Damper Open Damper Active Fan Bored Tunnel Draught Relief Shaft Under Platform Extract (UPE) Tunnel Isolation Damper UPE Damper DRS Damper Station Plant Receptor Fan Isolation Damper Fan Isolation Damper Fan Isolation Damper Inactive Fan Closed Damper Fan (FV Duty) Noise Station Plant Noise

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-30
SLIDE 30

Noise Propagation Paths - Maintenance Mode (reduced duty)

Ground level Bored Tunnel Draught Relief Shaft Forced Ventilation Shaft Under Platform Extract (UPE) System Side Attenuation Atmosphere Side Attenuation Tunnel Isolation Damper UPE Damper DRS Damper Open Damper Active Fan Bored Tunnel Draught Relief Shaft Under Platform Extract (UPE) Tunnel Isolation Damper UPE Damper DRS Damper Station Plant Receptor Fan Isolation Damper Fan Isolation Damper Fan Isolation Damper Inactive Fan Closed Damper Station Plant Noise Fan (Maintenance Duty) Noise

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-31
SLIDE 31

Frequency of Operation

  • Under Platform Extract (UPE)

– On during operational hours at all stations except Woolwich

  • Cooling / Congestion

– Infrequently (see next slide) to respond to congestion / train fault

  • Maintenance

– Engineering Hours – Depends on tunnel maintenance schedule and type

  • f maintenance activity

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-32
SLIDE 32

Frequency of Operation – Cooling

  • Ventilation Shafts serving 1 Ventilation Section have a 4% probability of activation in cooling mode
  • n any given day

→ Statistical interval between activations in cooling mode is 26 days

  • Ventilation Shafts serving 2 Ventilation Section have a 8% probability of activation in cooling mode
  • n any given day

→ Statistical interval between activations in cooling mode is 13 days

  • Ventilation Shafts serving 3 Ventilation Section have a 12% probability of activation in cooling mode
  • n any given day

→ Statistical interval between activations in cooling mode is 8 days

  • 50% chance of a train being stationary for more than 6 minutes in

a tunnel along the entire Central Section on any given day

  • 4% chance of a train being stationary for more than 6 minutes in

any given ventilation section on any given day

Ventilation Section → Each individual shaft will operate in Cooling / Congestion Mode infrequently.

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-33
SLIDE 33

IPD25 - Crossrail Design Process

Part 3 L e a r n i n g L e g a c y D

  • c

u m e n t

slide-34
SLIDE 34

IPD25 - Crossrail Design Process

Protocol for the Application of Crossrail Design Criterion to the Design of Fixed Installations Section 3 of IPD25 (Assurances 463 & 464) Section 3.2 list seven specific requirements of the protocol

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-35
SLIDE 35

Crossrail Design Process

  • When designing all fixed installations the nominated undertaker will

be required to:

  • D25 Design Protocol (Bullet Point 1)
  • “Incorporate the design criterion into contract documents such

that it will apply to the design of all the fixed installations that are to be installed and operated in any location within the Crossrail development”

CONTRACT REQUIREMENT (+5dB)

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-36
SLIDE 36

Crossrail Design Process

  • D25 Design Protocol (Bullet Point 2)
  • “When designing fixed installations, take the further endeavours

which are referred to in paragraph 2.6 or 2.9 (as the case may be) to reduce the noise below the design criterion in paragraph 2.5”

CONTRACT REQUIREMENT (-5dB)

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-37
SLIDE 37

Crossrail Design Process

  • D25 Design Protocol (Bullet Point 3)
  • “Translate the design criterion into specific requirements in

specifications for the procurement and operation of Crossrail plant, equipment and machinery for fixed installations taking into account the further endeavours referred to in bullet point 2 above”

SPECIFICATIONS

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-38
SLIDE 38

Crossrail Design Process

  • D25 Design Protocol (Bullet Point 4)
  • “Determine the relevant LA90,T levels, to be jointly established with

the relevant local authorities”

BACKGROUND

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-39
SLIDE 39

Crossrail Design Process

  • D25 Design Protocol (Bullet Point 5)
  • “Procure, install and commission plant, equipment and

machinery, including noise attenuation equipment that meets the specific requirements referred to in bullet point 3 above”

IMPLEMENTATION

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-40
SLIDE 40

Crossrail Design Process

  • D25 Design Protocol (Bullet Point 6)
  • “Provide details of the measures undertaken to ensure that, under

all reasonably foreseeable circumstances, the design process and procurement process for fixed installations is adequate to achieve compliance with the design criterion taking into account the endeavours referred to in bullet point 2 above (including proposals for maintenance and monitoring) to the relevant local authority whose comments will be taken into account”

PROCESSES

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-41
SLIDE 41

Crossrail Design Process

  • D25 Design Protocol (Bullet Point 7)
  • “Before the fixed installation may be operated, satisfactorily

complete the standard suite of acceptance tests required for such plant and provide information on those tests to the relevant local authority”

VALIDATION

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-42
SLIDE 42

Crossrail Design Process

  • D25 Design Protocol - Summary
  • 1. Contract Requirement (+5dB)
  • 2. Contract Requirement (-5dB)
  • 3. Specifications
  • 4. Background

5.Implementation

  • 6. Processes
  • 7. Validation

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-43
SLIDE 43

Crossrail Design Process

  • Specific D25 Contract Specifications:

– Inclusion of all IPD25’s Assurances in ITTs including ‘Crossrail Assessment Criterion’ of +5dB and ‘further endeavours’ to achieve -5dB – Inclusion of agreed background noise reports in ITTs (contractual levels) – Inclusion of preliminary FDC assessments in ITTs (information only) – Setting of ‘Noise Design Criteria’ taking account of potential cumulative effects

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-44
SLIDE 44

Crossrail Design Process

Specific D25 Contract Specifications:

  • Tunnel Ventilation:

– Targets of +5dB and -5dB have been set as per IPD25

  • Stations & Facilities:

– Aim where practicable to meet -10dB (i.e. 5dB more onerous than IPD25’s ‘further endeavours’) and be no more than -5dB

The -10dB target is driven by the need to meet IPD25 requirements on a cumulative basis. The specifications require the various contractors to interface with each other and work in a collaborative manner to meet IPD25

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-45
SLIDE 45

Crossrail Design Process

Specific D25 Contract Deliverables:

–‘Fixed Installation Noise Justification’ report, if applicable (i.e. any targets are not met) –‘Fixed Installation Demonstration’ report – Above to be delivered 7&4 months prior to procurement –‘Commissioning & Acceptance Testing’ report to demonstrate compliance

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-46
SLIDE 46

Crossrail Design Process

Information provided to Local Authorities:

–Design information (including above reports) to the relevant local authorities, where -5dB cannot be met, despite further endeavours:

  • Calculated BS4142 Rating Levels
  • Frequency/Duration of Tunnel Ventilation Fans (congested mode)
  • Performance of Noise Mitigation Equipment
  • Limitations to any Further Mitigation being Practicable

–Information on the commissioning and acceptance tests

L e a r n i n g L e g a c y D

  • c

u m e n t

slide-47
SLIDE 47

Delivering a world-class affordable railway safely through effective partnerships

L e a r n i n g L e g a c y D

  • c

u m e n t