t n e m u c
play

t n e m u c - Central Section - o D Fixed Installation Noise - PowerPoint PPT Presentation

t n e m u c - Central Section - o D Fixed Installation Noise (D25) y c a Design Process Fixed Plant g e L g EHSG Meeting, July 2012 n i n & r a e L This document is shared for the purposes of learning legacy. It is


  1. t n e m u c - Central Section - o D Fixed Installation Noise (D25) y c a Design Process – Fixed Plant g e L g EHSG Meeting, July 2012 n i n & r a e L This document is shared for the purposes of learning legacy. It is a snapshot in time and hence many of the links within the document will become obsolete over time. Some links/document references will refer to a document storage location that isn't accessible. Users should refer to the learning legacy website where these documents may be published separately.

  2. t n e m u Contents c o • Part 1 D y IPD25 Targets & Status Update c a g • Part 2 e L Engineering & Contractual Context g n • Part 3 i n r a Application of Crossrail Design Criterion to the Design e Process L

  3. t n e m IPD25 – Targets & Status Update u c o D y c a g Part 1 e L g n i n r a e L

  4. t n e m IPD25 – Targets u c o • D25 Targets – BS4142 Approach D y c a g Noise Levels Relative to Background e L g n i 10dB ‘Reasonable Endeavours’ Range n r a -5dB below Background +5dB above Background e ‘Further Endeavours’ ‘Crossrail Assessment Criterion’ L 0dB Background

  5. t n e m IPD25 – Fixed Installations u c o D Main Fixed Plant Noise Sources: y c • Tunnel Ventilation Fans, a g • Mechanical Plant at Crossrail Buildings (e.g. e L ventilation and air conditioning equipment) g • Electrical Trackside Equipment n i n • Power Supply Facilities (e.g. Transformers) r a e L

  6. t n e m IPD25 – Assessment Assumptions u c o • Conservative approach currently adopted D y for Reference Design: c a - IPD25 refers to ‘ normal operation ’ g e - However, FDC assessments are based L on Tunnel vent congested-mode, late g n at night or early morning i n r - In practice, a very unlikely scenario, a e hence considered to be worst-case L - Conventional plant assumed 24/7

  7. t n e m IPD25 – Assessment u c o • Preliminary assessments are based on: D y - BS4142 Rating Method c a - Cumulative impact of site development g e L - Determined at worst-affected receptor g - +5dB character correction in all cases n i n - Typical operational hours over a week r a - Predicted for the worst 5-mins (night) e L - Additional allowances for calculation uncertainty

  8. t n e m IPD25 – Status Update u c o • Engagement of Framework Design D y Consultants (FDCs) c a • Development of Reference Designs by FDCs g e for Power, Portals, Stations and Shafts L • Presently 22 Development Sites have been g n considered i n r • 10 - Forced Ventilation Shaft Sites a e • 12 – Sites with other Fixed Installations L

  9. t n e m IPD25 – Status Update u c o • Development of the Method for Establishing D y Background Noise Levels for IPD25 c a • FDC Background Noise Surveys/Reporting g e using the standard grid of L A90,1hr dB values: L g n i n r a e L

  10. t n e m IPD25 – Status Update u c o • ‘Jointly Established’ & Agreed Background D y Noise Levels with Local Authorities c a • Preliminary D25 Noise Assessments of g e FDC Reference Design – Reviewed by CRL L • Individual D25 Presentations to Local g n Authorities by Station FDCs i n r • Next step: D25 Communication to Local a e Authorities of Preliminary Assessment L Findings (Worst-case Cumulative Levels)

  11. t n e m IPD25 – Status Update u c o • IPD25 Contract Specifications Completed D y and Included in the relevant tender c a packages (ITTs) as follows: g e L 1. Deep-Level Stations g 2. Shafts and Portals n i n 3. Surface Rail and Surface Stations r a e 4. Tunnel Ventilation (Systemwide) L 5. Traction Power Transformers

  12. t n e m u Engineering & Contractual Context c o D y c a Part 2 g e L g n i n r a e L

  13. t n e m u Engineering & Contractual Context c o Context: IPD25 Introduction - Paragraph 1.5 D y “ To avoid a significant noise impact from the tunnel c a forced ventilation fans, noise attenuators will be g e designed and installed on each side of the tunnel L ventilation fans, as necessary to meet the Crossrail g assessment criterion for fixed plant ” n i n The preliminary assessments support the above, r a indicating that the tunnel ventilation fans are the most e L significant fixed installation noise sources on the Crossrail project

  14. t n e m Crossrail - Central Section Works u • Tunnel structures and station, intermediate c o shaft and portal structures & mechanical and D electrical systems y c a g • Systemwide (railway systems, tunnel systems) e L g n • Complexity: i n r – Complex packaging of delivery responsibility a e – Complex project timeline L

  15. t n e m u c o D y c a g e L g n i n r a e L

  16. t n e m High Level Timeline u Now c o Tunnels / Station / Shaft / D Tunnelling / Civil Works Portal Detail Design y c Station / Shaft / Portal Space a Mechanical & Electrical Fit Out proofing g frozen e L Systemwide Reference Systemwide Systemwide Equipment g Design Procurement Detail Design Procurement n i n r Systemwide Installation a e Provisional Demonstration L Findings Reports 2018 2017 2014 2015 2016 2011 2012 2013 2010 2009

  17. t n e m u Summary of Responsibilities c o • C610 – Systemwide Main Works Contract D includes detail design and provision of the y c Tunnel Ventilation System for central section a g e • Station contractors will be responsible for the L buildings’ ventilation and air -conditioning plant g n • Preliminary assessments by station and shaft i n designers indicate that the Tunnel Ventilation r a e System is the fixed installation with the L dominating noise contribution • C610 and station contractors will interface

  18. t n e m u Tunnel Ventilation System c o • Required to: D – Relieve pressure resulting from train movements y c → Draught Relief Shafts a – Remove heat dissipated by running trains g e → Under Platform Extract L – Cool trains stationary in tunnel (Cooling / Congestion) g → Cooling n i – Control smoke from a train fire n r → Smoke Control (Emergency Situation) a – Provide ventilation during tunnel maintenance activities e L → Maintenance Ventilation

  19. t n e m u Draught Relief Shafts c o Draught Draught Draught Relief Relief Relief D Shaft Shaft Shaft Tunnel Entrance Station y c Ground Level Ground Level a g e L • Needed to relieve the pressure generated by g train movements n i n • Provides passive ventilation and cooling r a e L

  20. t n e m Under Platform Extract u c Draught Draught o Relief Relief D Shaft Shaft Station y c Ground Level Ground Level a UPE g e L g • Required to remove heat from trains stopped at n i the station n r a • Provides active cooling of tunnel e L

  21. t n e m u Cooling / Congestion c o Draft Draft Forced Draft Relief Relief Vent Relief D Shaft Shaft Shaft Shaft Tunnel Entrance Station y c Ground Level Ground Level a g e L • Required to cool trains stationary in Tunnel g n • Only required if Train remains stationary in the i n tunnel for more than 6 minutes r a e L

  22. t n e m u Smoke Control - Fire in Tunnel c o Draught Draught Draught Relief Relief Relief D Shaft Shaft Shaft Tunnel Entrance Station y c Ground Level Ground Level a g e L • Required to Control Smoke g n i n r a e L

  23. t n e m u Smoke Extract - Fire in Station c o Draught Draught Forced Draught Relief Relief Vent Relief D Shaft Shaft Shaft Shaft Tunnel Entrance Station y c Ground Level Ground Level a g e L • Required to extract smoke g • Keeps station evacuation routes clear of smoke n i n r a e L

  24. t n e m u Route Map c o D Eleanor Street Liverpool Street Bond Street Fisher Street Stepney Green y c a Mile End Tottenham Court Road Farringdon Whitechapel Paddington g e Limmo L g Canary Wharf Woolwich Intermediate Shaft with No Tunnel Ventilation n Intermediate Shaft with Cooling only i n Station with Cooling & Draught Relief r a Station with Cooling, UPE & Draught Relief e L

  25. Typical Station t n e Section m u c o D y c a g Typical Dimensions: e • Fan Size: 2.8m diameter L • Duct Size: 30m^2 g • Attenuator Dimensions: n • 3m long i n • 60m^2 r a e L

  26. t n e m u c Residential receptor o D y c a g e DRS L g FV n i n r Typical a e intake / outlet L arrangement

  27. t n e m u Operational Modes c o • Under Platform Extract (UPE) D y – Cooling of trains running normally c a • Cooling / Congestion (Worst Case Noise) g e – Cooling of stationary trains in tunnel L • Maintenance g n – Ventilation of tunnel maintenance activities i n r – Tunnel Ventilation System test a e • Smoke Control L – Noise not considered because emergency response

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend