Supplier Selection Sue Hurrell, Value Wales What am I covering? - - PowerPoint PPT Presentation
Supplier Selection Sue Hurrell, Value Wales What am I covering? - - PowerPoint PPT Presentation
Simplifying Supplier Selection Sue Hurrell, Value Wales What am I covering? Background Supplier Selection what we set out to achieve SQuID what is it? The risk-based approach Summary of content The project
What am I covering?
- Background
- “Supplier Selection” – what we set out to
achieve
- SQuID – what is it?
- The risk-based approach
- Summary of content
- The project – where we are now
- Questions
Bit of background
- Perennial question – how can we reduce
barriers to entry, especially for SMEs?
- Barriers to procurement opportunities
report - 2009
- Pre-qual always the main culprit
- Seen as over-complex, bureaucratic,
- paque etc – but buyers have to:
– Manage risk and process costs – Be fair, transparent and operate within the law.
Other “Barriers” recommendations
- Need for wider advertising, particularly of
lower-value contracts.
- Greater clarity around the assessment
process.
- Better feedback and communication
generally.
Supplier Selection
Research, specification, advert etc – what do we want? Selection – are they capable? Award – what’s the best offer? Shortlisting – can we narrow the field down a bit?
Selection rules
- Treaty principles – all procurement
- Regulations – application depends on contract
value and market
- No muddling or duplication of selection and
award questions
- Law is restrictive about what can be asked at
each stage.
- Transparency of requirements and assessment
at all stages is essential.
The problem:
- Common mistake – including requests for info
“just in case” or “because we’ve used it before”, in the belief it “covers all the bases”.
- But if you don’t know:
– why you’re asking for the info; – what you will do with it; and – how you will assess or score it…
- …you waste everyone’s time, and
- …risk a legal challenge.
Costs of supplier selection
- based on on-going survey of (~ 40) suppliers,
Sell2Wales and Bravo data. (statistical significance?)
- Average cost for completing a PQQ is approx £1600 for
non-construction and £2700 construction (too conservative?)
- An average of 16 PQQ responses are completed per
procurement.
- At least £20m is spent annually, in Wales by suppliers,
- n PQQs for OJEU procurements alone.
- Approx 20% of this cost is incurred by suppliers simply
trying to figure out whether or not to bid.
Key objectives
- More standardisation AND more tailoring!
- Efficiency for both public sector and bidders
- Consistency of approach
- Minimise legal risk of challenge
- Better feedback leading to improved tenders
- Increase competitiveness in all markets…
- … and especially of Welsh SMEs – maximising
economic benefit of procurement in Wales.
Some principles
We wanted to encourage buyers to:
- think about specific contract requirements and
associated risks;
- favour YES/NO (pass/fail) questions and thresholds that
enable non-compliant suppliers to self-deselect ;
- reduce use of open-ended “exam questions”;
- reduce use of essay questions to back up a yes/no
answer;
- reduce focus on policies and statements of intent; and
- increase focus on facts - past experience and
performance.
What is SQuID ?
- Supplier Qualification Information
Database
– although it’s not a database yet!
- A common core set of questions
- NOT a standard form/template
- Risk-based tool for buyers
What is SQuID? (2)
- Currently rather a lot of paper!
– Part 1, introduction – Part 2, guidance for buyers – Part 3, the question set
- Similar documents for construction-specific
- Work underway on the on-line version on
www.sell2wales.co.uk, which will
– summarise Part 2 into a single “wizard” (to be used for every new project) – Store suppliers’ data in “answer pots” for re-use.
How was it developed?
- Long-list of questions based on some standard PQQs in
use
- Groups of experts (public and private sector) looking at
categories:
– Finance – Capacity and capability – Management (quality, PM) – Equality – Sustainability – Health and Safety
- Long-list down to shortlist
- A year’s “active consultation” – feedback and 400
(mainly public sector) staff trained.
- An identical parallel construction exercise
How is SQuID used by buyers?
- Use the risk-based guidance (Part 2 of paper
doc, or “wizard” on the on-line version): to
– analyse requirement and the associated risks, and choose questions that address them – leave out questions that are not relevant
- Add in any necessary project-specific questions
- Include guidance for bidders
- Issue your PQQ (using the system) and receive
responses – assess off-line.
How is SQuID used by suppliers?
- Paper version – read the guidance and answer
the questions as usual.
- Sell2Wales version (when we have it):
– Log on and complete your full profile (your “Master answer pot”) at any time – Respond to an advertised opportunity and fill in the PQQ using your stored data – Store your new answers as an “answer pot” – Manage your answer pots to update your “Master answer pot”.
When can SQuID be used ?
For any formal tendering:
- Open procedure – as first part (selection) of invitation
to tender
- Restricted procedure – as PQQ at
selection/qualification stage
- Sub-threshold procurements
16
Risk-based approach
- What are we doing at selection?
–Minimising the risks associated with a supplier failing to deliver or causing some other cost or embarrassment.
- Most organisational procedures
based around value, not risk.
Assessment tool - risk of supplier failure
None = 0 Low = 1 Moderate = 2 High = 4 Very High =8 Penalties or costs incurred by the buyer if supplier failed Less than £5,000 Around £10,000 Around £25,000 Around £50,000 Near to or
- ver
£100,00 Goodwill / reputational impact on Buyer of supplier failing; impact on public and consumers. No external impact on failed contract. Very limited impact on public; public perception unlikely to be affected. Some impact
- n public;
small negative impact on public perception. Moderate impact on public; moderate negative impact
- n public
perception. High impact
- n public;
significant negative impact on public perception. Incremental cost of providing a temporary alternative service/capability Less than £5,000 Around £10,000 Around £25,000 Around £50,000 Near to or
- ver
£100,00 Procurement costs associated with buying a temporary and/or alternative service or capability Less than £5,000 Around £10,000 Around £25,000 Around £50,000 Near to or
- ver
£100,00
0 - 3 points (up to approx £35k impact): no check of financial standing 4 – 7 points (approx £35-85k impact): light-touch check of financial standing 8 or more points (approx £100k impact and over): in-depth check of financial standing
- Scenario 1 – prescribing software
– Software to support critical [Prescribing/Social Services] function. – Value £75k. – Mainly “off the shelf” product but some bespoking needed. – Term: 3 years with option to extend to 5. – Maintenance and support required over contract term. – Several suppliers in the market but business- critical and would take 5-6 months to replace. – Installation required (including some time working on purchasing body’s premises).
- Scenario 2 - Staff uniforms
– Term: 3 years fixed. – Value £60k. Purchase only. – These are basic, widely available garments which only require finishing in the appropriate colours and the purchasing body’s logo and wording to be attached. – Relatively easy to re-procure and non-critical because of stock held. – However – garments manufactured in Far East (though finished in EU) and purchasing body’s policies require sustainability and labour policy / conditions to be scrutinised closely.
Low-risk financial appraisal
- Light touch check:
- Profitability over 2 years (opportunity for
losses to be explained, or put into the context of available assets)
- Acid-test ratio (short-term liabilities and
assets)
- Credit checks or D&B “risk of failure”?
Possible concerns around transparency.
High-risk financial appraisal
- Comprehensive analysis of accounts by
experts – in-house or third party.
– Balance sheet of bidding company (and parents) – Historical cash and profitability – Other structural issues, market context etc
- Opportunity for mitigating steps (bonds,
guarantees)
Capacity and capability
- Experience (answers may not be
“storeable”)
- Record of successful delivery (deductions
for damages, cancelled contracts)
- Turnover (relevant)
- Certification/qualifications/skills/capacity
The other sections
- Management (quality), equality, sustainability,
H&S
- Treated similarly:
– Do you have convictions? – What have you done to put things right since? – Do you check the credibility of sub-contractors? – Do you have a third-party accredited system (ISO9001, ISO14001 or equivalents etc)? – If not, do you have your own process? Does it include the elements we need? Can we see a copy please? – What’s your record (H&S)?
What’s next?
- Finalising the question sets and guidance –
summer
- Getting them in use on current systems and built
into our e-tendering system (Bravo)
- Building the new functionality on Sell2Wales
(end of the year?)
- Data sharing with other systems
- Include other supplementary question sets
(social care, food, local transport?)
Is this another white elephant in the making?
- Very widespread buy-in to the principles and current
question sets. WG support, manifesto commitments etc.
- Wide take-up already, and enthusiasm about the
prototype of the on-line system.
- Sell-out courses
- Why?
– We consulted widely – joint ownership of the outcome – There is more risk of challenge out there – It’s a completely flexible solution – What’s not to like?!
- Challenges are getting the on-line system working and
the links with 3rd party systems.
- Scotland and N Ireland developing their own systems