supplier selection
play

Supplier Selection Sue Hurrell, Value Wales What am I covering? - PowerPoint PPT Presentation

Simplifying Supplier Selection Sue Hurrell, Value Wales What am I covering? Background Supplier Selection what we set out to achieve SQuID what is it? The risk-based approach Summary of content The project


  1. Simplifying Supplier Selection Sue Hurrell, Value Wales

  2. What am I covering? • Background • “Supplier Selection” – what we set out to achieve • SQuID – what is it? • The risk-based approach • Summary of content • The project – where we are now • Questions

  3. Bit of background • Perennial question – how can we reduce barriers to entry, especially for SMEs? • Barriers to procurement opportunities report - 2009 • Pre-qual always the main culprit • Seen as over-complex, bureaucratic, opaque etc – but buyers have to: – Manage risk and process costs – Be fair, transparent and operate within the law.

  4. Other “Barriers” recommendations • Need for wider advertising, particularly of lower-value contracts. • Greater clarity around the assessment process. • Better feedback and communication generally.

  5. Supplier Selection Selection – are they capable? Research, specification, Award – advert etc – what’s the what do we Shortlisting – can best offer? want? we narrow the field down a bit?

  6. Selection rules • Treaty principles – all procurement • Regulations – application depends on contract value and market • No muddling or duplication of selection and award questions • Law is restrictive about what can be asked at each stage. • Transparency of requirements and assessment at all stages is essential.

  7. The problem: • Common mistake – including requests for info “just in case” or “because we’ve used it before”, in the belief it “covers all the bases”. • But if you don’t know: – why you’re asking for the info; – what you will do with it; and – how you will assess or score it… • …you waste everyone’s time, and • …risk a legal challenge.

  8. Costs of supplier selection • based on on-going survey of (~ 40) suppliers, Sell2Wales and Bravo data. (statistical significance?) • Average cost for completing a PQQ is approx £1600 for non-construction and £2700 construction (too conservative?) • An average of 16 PQQ responses are completed per procurement. • At least £20m is spent annually, in Wales by suppliers , on PQQs for OJEU procurements alone . • Approx 20% of this cost is incurred by suppliers simply trying to figure out whether or not to bid.

  9. Key objectives • More standardisation AND more tailoring! • Efficiency for both public sector and bidders • Consistency of approach • Minimise legal risk of challenge • Better feedback leading to improved tenders • Increase competitiveness in all markets… • … and especially of Welsh SMEs – maximising economic benefit of procurement in Wales.

  10. Some principles We wanted to encourage buyers to: • think about specific contract requirements and associated risks; • favour YES/NO (pass/fail) questions and thresholds that enable non-compliant suppliers to self-deselect ; • reduce use of open- ended “exam questions”; • reduce use of essay questions to back up a yes/no answer; • reduce focus on policies and statements of intent; and • increase focus on facts - past experience and performance.

  11. What is SQuID ? • Supplier Qualification Information Database – although it’s not a database yet! • A common core set of questions • NOT a standard form/template • Risk-based tool for buyers

  12. What is SQuID? (2) • Currently rather a lot of paper! – Part 1, introduction – Part 2, guidance for buyers – Part 3, the question set • Similar documents for construction-specific • Work underway on the on-line version on www.sell2wales.co.uk, which will – summarise Part 2 into a single “wizard” (to be used for every new project) – Store suppliers’ data in “answer pots” for re -use.

  13. How was it developed? • Long-list of questions based on some standard PQQs in use • Groups of experts (public and private sector) looking at categories: – Finance – Capacity and capability – Management (quality, PM) – Equality – Sustainability – Health and Safety • Long-list down to shortlist • A year’s “active consultation” – feedback and 400 (mainly public sector) staff trained. • An identical parallel construction exercise

  14. How is SQuID used by buyers? • Use the risk-based guidance (Part 2 of paper doc, or “wizard” on the on -line version): to – analyse requirement and the associated risks, and choose questions that address them – leave out questions that are not relevant • Add in any necessary project-specific questions • Include guidance for bidders • Issue your PQQ (using the system) and receive responses – assess off-line.

  15. How is SQuID used by suppliers? • Paper version – read the guidance and answer the questions as usual. • Sell2Wales version (when we have it): – Log on and complete your full profile (your “Master answer pot”) at any time – Respond to an advertised opportunity and fill in the PQQ using your stored data – Store your new answers as an “answer pot” – Manage your answer pots to update your “Master answer pot”.

  16. When can SQuID be used ? For any formal tendering: • Open procedure – as first part (selection) of invitation to tender • Restricted procedure – as PQQ at selection/qualification stage • Sub-threshold procurements 16

  17. Risk-based approach • What are we doing at selection? – Minimising the risks associated with a supplier failing to deliver or causing some other cost or embarrassment. • Most organisational procedures based around value, not risk.

  18. Assessment tool - risk of supplier failure Very High None = 0 Low = 1 Moderate = 2 High = 4 =8 Penalties or costs incurred Near to or Around Around Less than £5,000 Around £10,000 by the buyer if supplier over £25,000 £50,000 failed £100,00 Moderate High impact Some impact Very limited impact on on public; Goodwill / reputational on public; No external impact on public; public; significant impact on Buyer of small negative impact on failed public perception moderate negative supplier failing; impact on impact on contract. unlikely to be negative impact impact on public and consumers. public affected. on public public perception. perception. perception. Incremental cost of Near to or providing a temporary Around Around Less than £5,000 Around £10,000 over alternative £25,000 £50,000 £100,00 service/capability Procurement costs associated with buying a Near to or Around Around temporary and/or Less than £5,000 Around £10,000 over £25,000 £50,000 alternative service or £100,00 capability 0 - 3 points (up to approx £35k impact): no check of financial standing 4 – 7 points (approx £35-85k impact): light-touch check of financial standing 8 or more points (approx £100k impact and over): in-depth check of financial standing

  19. • Scenario 1 – prescribing software – Software to support critical [Prescribing/Social Services] function. – Value £75k. – Mainly “off the shelf” product but some bespoking needed. – Term: 3 years with option to extend to 5. – Maintenance and support required over contract term. – Several suppliers in the market but business- critical and would take 5-6 months to replace. – Installation required (including some time working on purchasing body’s premises).

  20. • Scenario 2 - Staff uniforms – Term: 3 years fixed. – Value £60k. Purchase only. – These are basic, widely available garments which only require finishing in the appropriate colours and the purchasing body’s logo and wording to be attached. – Relatively easy to re-procure and non-critical because of stock held. – However – garments manufactured in Far East (though finished in EU) and purchasing body’s policies require sustainability and labour policy / conditions to be scrutinised closely.

  21. Low-risk financial appraisal • Light touch check: • Profitability over 2 years (opportunity for losses to be explained, or put into the context of available assets) • Acid-test ratio (short-term liabilities and assets) • Credit checks or D&B “risk of failure”? Possible concerns around transparency.

  22. High-risk financial appraisal • Comprehensive analysis of accounts by experts – in-house or third party. – Balance sheet of bidding company (and parents) – Historical cash and profitability – Other structural issues, market context etc • Opportunity for mitigating steps (bonds, guarantees)

  23. Capacity and capability • Experience (answers may not be “storeable”) • Record of successful delivery (deductions for damages, cancelled contracts) • Turnover (relevant) • Certification/qualifications/skills/capacity

  24. The other sections • Management (quality), equality, sustainability, H&S • Treated similarly: – Do you have convictions? – What have you done to put things right since? – Do you check the credibility of sub-contractors? – Do you have a third-party accredited system (ISO9001, ISO14001 or equivalents etc)? – If not, do you have your own process? Does it include the elements we need? Can we see a copy please? – What’s your record (H&S)?

  25. What’s next? • Finalising the question sets and guidance – summer • Getting them in use on current systems and built into our e-tendering system (Bravo) • Building the new functionality on Sell2Wales (end of the year?) • Data sharing with other systems • Include other supplementary question sets (social care, food, local transport?)

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend