Staying at Zero with Affine Processes
An Application to Term Structure Modelling Alain Monfort1,2 Fulvio Pegoraro1,2 Jean-Paul Renne2 Guillaume Roussellet1,2,3
1CREST 2Banque de France 3Dauphine University
Staying at Zero with Affine Processes An Application to Term - - PowerPoint PPT Presentation
Staying at Zero with Affine Processes An Application to Term Structure Modelling Alain Monfort 1 , 2 Fulvio Pegoraro 1 , 2 Jean-Paul Renne 2 Guillaume Roussellet 1 , 2 , 3 1 CREST 2 Banque de France 3 Dauphine University 5 th Conference on Fixed
1CREST 2Banque de France 3Dauphine University
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
2 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
1990 1995 2000 2005 2010 2015 2 4 6 8 U.S. Fed Bank of Japan Bank of England ECB Policy Rates (in %)
3 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
1 2 3 1995 2000 2005 2010 2015
Dates Yields (in %, annual basis)
Maturity (in years) 0.5 1 2 4 7 10
4 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
0.00 0.05 0.10 0.15 100 200 300 400 500
Periods
Simulation of an ARGo process
0.00 0.25 0.50 0.75 1.00 0.00 0.05 0.10 0.15
Values Probability
Cumulative distribution function
7 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
8 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
9 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
10 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix A mixture of affine distributions
1
2
11 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix A mixture of affine distributions
+ ∞
12 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix A mixture of affine distributions
+ ∞
12 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix A mixture of affine distributions
+ ∞
12 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix A mixture of affine distributions
13 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Properties and extensions
14 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Properties and extensions
15 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
16 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
1 2 3 1995 2000 2005 2010 2015
Dates Yields (in %, annual basis)
Maturity (in years) 0.5 1 2 4 7 10
17 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Short-rate specification and the affine framework
i Xt).
t (Xt+1)
t (Xt+1)
18 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Short-rate specification and the affine framework
t
t
j = 1, βP and βQ lower-triangular (identification).
19 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Short-rate specification and the affine framework
20 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Short-rate specification and the affine framework
21 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Short-rate specification and the affine framework
22 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Short-rate specification and the affine framework
0.0 0.5 1.0 1.5 0.0 0.5 1.0 1.5 2−years yield 10−years yield 1995 2000 2005 2010 2015
Dates Yield volatility proxies (for yields in %, annual basis)
Model EGARCH(1,1) GARCH(1,1) Rolling window (60 days)
23 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Short-rate specification and the affine framework
24 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Advantages of an affine framework
25 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
26 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix State-space formulation
27 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Estimation results
2 4 1 2 3 4 0.0 2.5 5.0 7.5 1 2 3 4 5
Factor n°1 Factor n°2 Factor n°3 Factor n°4
1995 2000 2005 2010 2015
Dates
28 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Estimation results
4 6 8 10 0.0 0.2 0.4 0.6
(a) Factor loadings of yields
Loadings Maturities (in years)
Second factor Third factor Fourth factor
4 6 8 10 0.000 0.004 0.008
(b) Factor loadings of conditional variances
Loadings Maturities (in years)
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Estimation results
2−year yield 10−year yield 0.00 0.02 0.04 0.06 1995 2000 2005 2010 2015 1995 2000 2005 2010 2015
Dates Conditional variance proxy
fitted 3−month ahead 10−year yield 12−month ahead 10−year yield
2 3 4 1995 2000 2005 2010 2015 1995 2000 2005 2010 2015
Dates Forecast Surveys (in %, annual basis)
30 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix Estimation results
0.00 0.25 0.50 0.75 0.0 0.5 1.0 1.5 1 2 3
6−month yield 2−year yield 7−year yield
1995 2000 2005 2010 2015
Dates Yields (in %, annual basis)
0.00 0.25 0.50 0.75 1.00 0.0 0.5 1.0 1.5 2.0 1 2 3
1−year yield 4−year yield 10−year yield
1995 2000 2005 2010 2015
Dates
fitted
31 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
32 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
33 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
2−years ahead 5−years ahead 0.0 0.2 0.4 0.6 0.8 0.00 0.25 0.50 0.75 1.00 lambda = 0 lambda = 25 bps 1995 2000 2005 2010 2015 1995 2000 2005 2010 2015
Dates Probabilities
34 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
lambda = 0 lambda = 25 bps 0.00 0.25 0.50 0.75 1.00 1 2 3 4 5 1 2 3 4 5
Forecast horizon Probabilities
2007−11−30 2014−05−30 Q probability P probability
35 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
36 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
37 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
38 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
39 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
P-parameters Q-parameters Estimates Std. Estimates Std. α4 3.2455 0.1118 3.2347 0.1113 β1,1 0.9663 0.0078 0.9794 0.0042 β2,2 0.9978 0.0005 0.9957 0.0006 β3,3 0.9486 0.0044 0.9705 0.0023 β4,4 0.9967 0.0005 0.9933 0.0003 β2,1 0.0308 0.0041 0.0308 0.0041 β3,2 0.1094 0.0059 0.1120 0.0061 β4,3 3.88·10−4 2.28·10−5 3.87·10−4 2.27·10−5 µ1 1 – 1.0135 0.0040 µ2 1 – 0.9980 0.0005 µ3 1 – 1.0231 0.0023 µ4 1 – 0.9967 0.0003 Other Parameters δ1 0.0030 0.0003 θ1
0.0039 θ2 0.0020 0.0005 θ3
0.0022 θ4 0.0033 0.0003 σR 0.0407 0.0003 σV 3 · 10−3 − σS 0.15 − 40 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
41 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
u→−∞ϕt,h(0, . . . , 0, u)
u→−∞ϕt,h(u, . . . , u)
42 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
′
′
′
43 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
44 / 30
Introduction The ARG0 process The NATSM Estimation Assessing lift-off dates Conclusion Appendix
45 / 30