Status of Fukushima Lessons July 31, 2014 David Lochbaum Director, - - PowerPoint PPT Presentation

status of fukushima lessons
SMART_READER_LITE
LIVE PREVIEW

Status of Fukushima Lessons July 31, 2014 David Lochbaum Director, - - PowerPoint PPT Presentation

Status of Fukushima Lessons July 31, 2014 David Lochbaum Director, Nuclear Safety Project Union of Concerned Scientists www.ucsusa.org Status to date * Good My focus today will be on the mitigating strategies order. Many themes are


slide-1
SLIDE 1

Status of Fukushima Lessons

July 31, 2014 David Lochbaum Director, Nuclear Safety Project Union of Concerned Scientists www.ucsusa.org

slide-2
SLIDE 2 2

Status to date

Good

My focus today will be on the mitigating strategies order. Many themes are applicable to

  • ther Fukushima lessons.

*

slide-3
SLIDE 3 3

On the Good Side

Station blackout rule assumed that alternating current power would be restored within the plant-specific coping duration (typically 4 or 8 hours) Mitigating strategies order seeks to provide core, containment and spent fuel cooling for an infinite period.

slide-4
SLIDE 4 4

Original assumption that Fukushima invalidated has been replaced by the assumption that FLEX equipment can be placed and

  • perated in time.

Is this assumption also invalid?

On the Caveat Side

slide-5
SLIDE 5 5

On the Good Side

In general, FLEX provides at least N+1 widgets or connections when N is required for success.

Source: ML13063A063
slide-6
SLIDE 6 6

On the Good Side

Source: ML13063A063 Two spatially separated connection points are provided for FLEX pumps.
slide-7
SLIDE 7 7 Source: ML13063A063 Neither connection point works unless pressure inside the reactor vessel is first lowered because FLEX only uses low pressure (and cheaper) pumps.

On the Caveat Side

slide-8
SLIDE 8 8

0 < N and nature rather than the NRC’s assessment determines the

  • utcome.
Source: ML13063A063

On the Caveat Side

slide-9
SLIDE 9 9 Source: ML13063A063 The FLEX storage sheds at Pilgrim are about 2,400 feet apart.

On the Good Side

slide-10
SLIDE 10 10

NRC assumes that “Should one storage area be lost, the surviving storage area has adequate equipment.”

Source: ML13225A587

On the Caveat Side

Tornado that devastated Moore, OK must not have been aware of the 2,400 foot rule.

Disaster Picture: FEMA
slide-11
SLIDE 11 11

N+3 = N when

  • nly one debris

remover is provided, unless events are “tidy” and

  • nly deposit

debris in designated places.

Source: ML13063A063

On the Caveat Side

slide-12
SLIDE 12 12

NRC technical evaluation report: “The single debris removal equipment identified may not be able to move debris to enable transport of equipment within the 6-9 hour time restriction for the pumps and generators.”

Source: ML13225A587

On the Caveat Side

slide-13
SLIDE 13 13

Equipment

  • ver and

above that provided for B.5.b is now onsite.

Source: ML13063A063

On the Good Side

slide-14
SLIDE 14 14

Equipment heaters protect FLEX equipment from cold weather damage before the BDBEE. NRC Bulletin 79-24 discussed events at nuclear plants where safety-related systems were disabled by cold weather. These systems were monitored and surveilled, yet failed.

On the Caveat Side

slide-15
SLIDE 15 15

NRC requires that workers periodically check air inlet and outlet ventilation ports for dry casks for blockage, but not for FLEX storage pods.

On the Caveat Side

Source: NRC Flickr Gallery
slide-16
SLIDE 16 16 Source: ML13225A587

Pilgrim’s BDBEE Plan

The plan non-conservatively assumes that the reactor vessel pressure gets lowered enough to let FLEX’s low pressure pump(s) provide makeup flow.

slide-17
SLIDE 17 17 Source: ML13225A587

Pilgrim’s BDBEE Plan

The plan non-conservatively assumes that instrumentation not covered by post- Fukushima orders will guide operators into taking proper and timely actions.

slide-18
SLIDE 18 18 Source: ML13225A587

Pilgrim’s BDBEE Plan

The plan non-conservatively assumes that RCIC takes suction from the suppression pool. When RCIC takes suction from its normal and usual source, the suppression pool fills more.

slide-19
SLIDE 19 19

The caveat would shrink if:

  • FLEX employed both high and low

pressure pumps

  • FLEX storage sheds were less

vulnerable to common-mode losses

  • Regulatory requirements governed

FLEX equipment while in storage

  • Non-conservative assumptions that

transform BDBEE into BBDBEE were eliminated

* *

*

slide-20
SLIDE 20

Acronym List

20

BDBEE – one acronym too many in the series of Class 9, severe accident, and Beyond Design Basis External Event labels for bad days FLEX – Diverse and Flexible Mitigation Capability NRC – Nuclear Regulatory Commission RCIC – Reactor core isolation cooling SBO – station blackout where all AC power is unavailable

slide-21
SLIDE 21

Backup Slides

21
slide-22
SLIDE 22 22

Pilgrim’s BDBEE Plan

Source: ML13063A063 “Because the Condensate Storage Tank (CST) is not seismically qualified, it is considered unavailable for the BDBEE. RCIC suction will be manually switched to the Suppression Pool.” Source: ML13225A587
slide-23
SLIDE 23 23

Pilgrim’s BDBEE Plan

Source: ML13063A063 FLEX uses only low pressure
  • pumps. Unless reactor
vessel pressure has been reduced by other means, even N+infinity FLEX pumps won’t work. Source: ML13225A587
slide-24
SLIDE 24 24

Pilgrim’s BDBEE Plan

Source: ML13063A063
slide-25
SLIDE 25 25

Pilgrim’s BDBEE Plan

Source: ML13063A063
slide-26
SLIDE 26 26

Pilgrim’s BDBEE Plan

Source: ML13063A063