Southwestern Public Service Company Local Planning Meeting September 15, 2011 2 Update on Current Construction Projects Dallam-Sherman 115 kV Line LEGEND OKLAHOMA Texhoma Amarillo TEXAS Texas . Sherman County Substation Stratford
Update on Current Construction Projects
2
Dallam-Sherman 115 kV Line
Texhoma
Dalhart
Stratford
Cactus Sunray Dumas Gruver Stinnett Spearman Substation Pringle Substation Moore Co . Substation Sherman County . Substation Dalhart Substation Dallam County Substation
Etter-Rural Substation Dumas
OKLAHOMA TEXAS
RBEC HOGUE SUBSTATION
N S E W
LEGEND
Texas
Amarillo
230 kV LINE 115 kV LINE 69 kV LINE NEW 115 kV LINE 345 kV LINE SUBSTATION
PROPOSED 115 Kv LINE
- APPROX. 35 MI
Line & Subs Completed – ISD Apr 2011 into Hitchland
3
Dallam-Channing-Potter Transmission Project
Am arillo, TX
Hardesty Optima Guymon
Goodwell
Boise City
Texhoma Stratford
Cactus Dumas Gruver Spearman Perryton Booker Darrouzett Follett Higgins Canadian Channing Substation Vega Adrian Fritch Borger Stinnett Sanford Panhandle W hite Deer Claude Groom Pampa Mclean Miami Mobeetie Sham rock
T.C.- T. C
- T. C
.
N .P. N . P . N.P. N.P. N .P. N .P. N.P. N.P . N.P . N.P. N . P . N.P . Spearman Substation N .P. N .P . Pringle Substation Moore County Substation Dumas 19th St Substation Potter County Substation Randall County Substation Coulter Substation East Plant SubstationNichols Sta . Harrington Sta Kirby Sw . Sta . Grapevine Substation Bowers Substation Kingsmill Substation
G.BGray Co . Substation
Riverview
Excell SubstationCole Substation
OKLAHOMA TEXAS
RBEC Hogue SubstationTC- W hiting
W ildorado SubstationHutchinson Co . Substation
Blackhawk Hitchland Substation LEGEND
Texas
Amarillo
230 kV LINE 115 kV LINE 69 kV LINE NEW 230 kV LINE NEW 115 kV LINE 345 kV LINE EXISTING SUBSTATION Ochiltree Co Substation
Dalhart SubstationDallam County Substation Dalhart Cliffside Substation Tascosa Substation Northwest Substation Affected Substations Sunray
Sherman County Substation Lasley Substation Etter Rural Substation Amarillo South Substation Bushland Substation- N. Amarillo
Channing
Vega SubstationConstruct 230kV Dallam to Channing Line, Operated 115 kV Initially. Construct 230kV Channing to Northwest Line, Operated 115 kV Initially.
Dallam-Channing Complete Aug 2011 Potter-Channing ISD Expected Jan 2012 Conversion to 230 kV ISD Expected Dec 2015
4
Moore County to Hitchland 230 kV
Hardesty Optima Guymon
Goodwell
Boise City
Texhoma
Dalhart
Stratford
Cactus Sunray Dumas Gruver Spearman Perryton Follett Higgin Canadian Channing Fritch Borger Stinnett Sanford Miami
.
Spearman Substation Pringle Substation Moore Co . Substation Sherman County . Substation Dalhart Substation Dallam County Substation
Etter-Rural Substation Dumas 19th St.
Riverview
Excell Sub
Cole Substation
OKLAHOMA TEXAS
RBEC HOGUE SUBSTATION
Texas Co . Substation Blackhawk Hitchland Substation
N S E W
LEGEND
Texas
Amarillo
230 kV LINE 115 kV LINE 69 kV LINE NEW 230 kV LINE NEW 115 kV LINE 345 kV LINE SUBSTATION REC OWNED LINE Construct 230 kV line from Hitchland to Moore Co.
ISD Expected - July 2012
5
Hitchland to Ochiltree County ISD Expected - Nov 2012
6
Hobbs Station Maddox Station
MAPCO AMFRAC Higg Russell Pool Taylor Switching Station Gaines Co
Seminole, Texas Hobbs, New Mexico
New Johnson Draw Sw. Station
SPS Substation 230 kV 115 kV 69 kV
Legend
SPS Power Plant New New SPS Sub N S E W 62 62
New Mexico Texas
ISD Expected - June 2012 Lea Co. Cooperative 115 KV Project (Johnson Draw Substation)
7
E d d y C o . N a v a jo A to k a
C o tto n w o o d
P C A S e v e n R iv e rs D u v a l # 2 Z ia
L a k e A rth u r
L a k e w o o d C V E C
E a g le C re e k In te rc h a n g e
N S E W
L E G E N D 2 3 0 k V 1 1 5 k V 6 9 k V S u b s ta tio n / In te rc h a n g e
Eagle Creek Project ISD – May 2011
8
Tenneco Sub
Gaines Co . Interchange Doss Interchange
AHCO2
Seminole
GAINES CO .
Riley Sub Y98 Y86 V94 T16
62 180 385 385
New Legacy Interchange N S E W
Air Port
Convert 69 kV line to 115 kV service . Construct double
- circuit 115 kV line
. Construct single
- circuit 115 kV line
. LEGEND 115 kV 69 kV Substation / Interchange
Legacy Interchange ISD – Aug 2011 9
Tuco – Woodward ISD Expected – May 2014 10
Yoakum Co 230/115 kV – 2nd 150 MVA auto – Oct 2009 Hale County 115/69 kV autos – 84 MVA – June 2010 Cochran County 115/69 kV autos – 84 MVA – June 2010 Lubbock East 115/69 kV autos – 84 MVA – Dec 2009 Wheeler 230/115 kV 250 MVA auto – Aug 2010 Wheeler – Howard 115 kV Line, 115/69 kV 40 MVA auto at
Howard
Clovis – Curry- North Clovis 115 kV Conversion – July 2010 Floyd County – 115 kV bus, 2 – 84 MVA 115/69 kV autos,
Floyd – Cox 115 kV line – April 2009
Other Project Completions
11
Projects have been budgeted Estimated ISD shown
New Transmission Projects
12
ISD Expected – Jun 2013 Rolling Hills (Cherry St Intg)
13
Jones Station
Idalou
SP-Hettler
Vickers
SP-Posey SP-Woodward SP-Union SP-Cooper SP-Woodward SP-Frenship Woodward Intg SP-Frankford SP-Quaker K47
K14
Doud Allen Wheelock Knoxville Globe SP-Upland Murphy Yuma Batton Carlisle
K08
Auburn Indiana Stanton Lewter Planters Carver Clutter Acco Lubbock East Lubbock South
Lubbock, TX
SPS Substation 230 kV 115 kV 69 kV REC Substation 345 kV
Legend
SPS Power Plant
N
ISD Expected – July 1, 2013 Jones Plant Bus Rebuild
14
T29 T28 Z63 Z62 Z64 K41 V72 T67 Y75 V07 Y76 Z18 Y74 V37 K21 T04 Z51 Y91 HAPPY SHAMROCK PUMP TULIA CITY KRESS RURAL SWISHER CO. KRESS PLAINVIEW NORTH COX PLAINVIEW EAST PLAINVIEW SOUTH WESTRIDGE PLAINVIEW WEST PLAINVIEW CITY HALE CO. LAMTON OLTON HART INDUSTRIAL SPRINGLAKE PLANT-X DIMMITT EAST DIMMITT WEST CASTRO CO.
SWISHER COUNTY CASTRO COUNTY HALE COUNTY FLOYD COUNTY LAMB COUNTY
SPS Substation 230 kV 115 kV 69 kV REC Substation 345 kV
Legend
SPS Power Plant Construct a 230/115 kV 252/292 MVA interchange. Construct approximately 19 miles of new 230 kV line from Newhart Interchange to Swisher County Interchange Construct approximately 18 miles
- f new 115 kV line from Newhart
Interchange to Kress Interchange Construct approximately 19 miles
- f new 115 kV line from
Newhart Interchange to Lamton Interchange Construct approximately 24 miles of new 115 kV line from Newhart Interchange to Castro County Interchange Tap the new 115 kV line and construct ~ 1 mile of 115 kV line to Hart Industrial Substation & convert substation to 115 kV service. N S E W
K1 K63
ISD Expected – Dec 2014 Newhart Interchange
15
FLOYD COUNTY
T29 Z63 V72 T67 Y75 V07 Y76 Z18 Y74 KRESS RURAL SWISHER CO. KRESS PLAINVIEW NORTH COX PLAINVIEW EAST PLAINVIEW SOUTH WESTRIDGE PLAINVIEW WEST PLAINVIEW CITY HALE CO.
CASTRO COUNTY HALE COUNTY
SPS Substation 230 kV 115 kV 69 kV REC Substation 345 kV
Legend
SPS Power Plant
Construct a 115/69 kV 84 MVA interchange to be located at the Plainview City Substation. Construct approximately 18 miles of new 115 kV line from Kress Interchange to Plainview City Interchange Convert Kress Rural Substation to 115 kV service
N S E W
K1 K63 NEWHART Convert Plainview North Substation to 115 kV service Construct approximately 10 miles of new 115 kV line from Plainview City Interchange to Cox Interchange
ISD Expected – Dec 2014 Plainview City Expansion
16
ISD Expected – Dec 2014 Pleasant Hill
17
Amarillo South Randall Co. Intg Osage Manhattan East Plant
Harrington Nichols
Amarillo , Texas
SPS Substation 230 kV 115 kV 69 kV 345 kV
Legend
SPS Power Plant New
K62 K19 K62 V67 V04
N
Amarillo, TX
V04
27 40 40
ISD Expected – Apr 2013 Randall County Interchange
18
Randall Co. Intg
T66Kress Intg
V76 V72Edmonson, TX
Swisher Co. K63 K01 Kress RuralC a n y o n , T X
Tulia, TX
T67 Sham rock Pum p Y91 Happy City Sub SCEC SCEC SCEC SCEC SCEC SCEC K63 Spring Draw T03 V05 K11 Canyon East Palo DuroHappy Intg
A m a rillo , T X
27 40 60 27
K41K re s s , T X H a p p y , T X
Potter CoSPS Substation 230 kV 115 kV 69 kV REC Substation 345 kV
Legend
SPS Power Plant
Nichols HarringtonN
ISD Expected – Apr 2012 Randall – Kress Reconductor
19
Bowers – Howard 115 kV Bowers – Howard 115 kV
PROPOSED 115 kV LINEBOWERS SUB HOWARD SUB LEGEND:
SPS EXISTING SUBSTATION 230 KV LINE 115 KV LINE 69 KV LINE 115 KV LINE (PROPOSED)
ISD Expected – June 2014
20
Harrington – Randall 230 kV #2 Harrington – Randall 230 kV #2 ISD Expected – June 2015
21
YOAKUM CO. SUB
380 82 82 62
LEGEND:
SPS EXISTING SUBSTATION 230 KV LINE 115 KV LINE 69 KV LINE
Yoakum 230 kV Bus Rebuild Yoakum 230 kV Bus Rebuild ISD Expected – June 2014
22
Hobbs Area Improvements – ISD 5/2012 Reconductor Maddox-Sanger 115 kV line Reconductor Maddox-Monument 115 kV line Kingsmill 2nd 115/69 kV auto – ISD 3/2013 Portales – Zodiac 115 kV Conversion- ISD 6/2013 Jones 4 GT – ISD 6/2013
Additional Projects
23
New Generation Interconnection Projects
Projects have been budgeted Estimated ISD shown
24
SPP Gen-2008-051 Spinning Spur Wind Farm – 160/322 MW
ISD Expected – Dec 2012
25
SPP Gen-2006-044 Novus 1 Wind Farm (Hitchland) – 250/370 MW ISD Expected – Dec 2011
26
SPP Gen-2008-018 Buffalo Dunes Wind – 369/405 MW ISD Expected – Dec 2012 (tentative)
27
SPP Gen-2006-045 Happy White Face East - 240 MW ISD Expected – Dec 2013
28
Questions?
29
SPS as a member of SPP participates in the submission of data to
the SPP transmission planning model building process.
Powerflow & Dynamic Seasonal Models
April Light (L) Spring Peak (G) Summer Peak (S) Shoulder (SH) Fall Peak (F) Winter Peak (W)
2012 SPP Model Series Set: 19 seasonal models
red = both powerflow & dynamics, underline = short circuit also created
- (5) 2012G, 2012S, 2012SH, 2012F, 2012/13W
- (6) 2013L, 2013G, 2013S, 2013SH, 2013F, 2013/14W
- (3) 2014G, 2014S, 2014W
- (3) 2018L, 2018S, 2018/19W
- (2) 2023S, 2023W
2012 SPP Model Build
30
Powerflow data due to SPP (NERC MOD-010-0 & MOD-012-0 Requirement) 2012 Approved Schedule: http://www.spp.org/publications/MDWG 2012 Series
Schedule and Model Selection.pdf
Due Date: September 29, 2011 If customer wishes that SPS submit the data in Models-On-Demand format along
with SPS submittal. (Data due to SPS)
Power Flow Data Required New & Updated coincident load data for the seasonal models listed above,
have been emailed out.
Generator, Transmission Line, Transformer, Shunt Devices Generators: Manufacturer Electrical Data Sheet, Excitation System Data,
Governor Data
Transmission Lines: R, X, B (100 MVA Base, per-unit), Normal & Emergency
Ratings (MVA)-Summer & Winter, Line Length (miles), and Bus-to-Bus Terminating Points
Transformers: Copy of Transformer Test Report Shunt Devices: MVAR value rated voltage All data shall include BOTH Positive/Zero Sequence Data, AND Ratings
Information.
2012 SPP Model Build Schedule
31
Generator Modeling
Modeling generation on Cooperative, Municipal and Retail systems. Requirements: Transmission topology data connecting the generator to BES. Positive Sequence R, X, B data Zero Sequence R, X, B data Ratings Data (Summer & Winter) Any transformer data (manufacturer’s test report) All machine electrical data, exciter data and governor data. PSS/E Version 32 format if data sheets are unavailable,
- therwise data sheets.
Required for power and dynamics analysis. Pmax, Pmin, Qmax, Qmin (seasonal values if applicable) Generator step-up Manufacturer’s test report.
32
Facility Ratings
Purpose: It’s to ensure that Facility Ratings used in planning and
- perations of the BES are determined based on established methodologies.
Generators, transmission line, transformers, capacitors, reactors, etc.
Facilities Rating Methodology (NERC FAC-008) Each Transmission and Generator owner shall document its
current methodology used for developing a Facility Ratings.
Procedure Manual indicating assumptions and calculations. Establish and Communicate Facility Ratings (NERC FAC-009) Each Transmission and Generator owner shall establish
Facility Ratings for its solely and jointly owned Facilities that are consistent with the FAC-008.
Shall provide Facility Ratings for its Facilities that are
existing, new, modified to the Reliability Coordinator, Planning Authority, Transmission Planner and Operator as scheduled by such requesting entities.
Need communication and tracking documents with each connecting party
Please visit the NERC website for the exact language of each standard. Facility Ratings data is now being managed by the SPS Substation Engineering Design.
Modeling Facility Ratings
33
SPS BA Coincident Peaks
SPS BA Coincident Peaks
4338 4673 4835 5168 5048 5502 5459 5575 5936 4000 4100 4200 4300 4400 4500 4600 4700 4800 4900 5000 5100 5200 5300 5400 5500 5600 5700 5800 5900 6000 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 Peak Load (MW)
SPS BA Coincident Peaks (to August 2, 2011)
34
Load Comparison 2010-2011 Winter
Area Num Area Name Actual Peak Load Date/Hour Actual Real- Time Load Planning Peak Load* MW Difference % Difference eDNA Data Point Notes 502 CLEC 2/2/2011 7:10 2306 2237
- 69
- 3.1%
SPP.EMS.00006598 503 LAFA 1/12/2011 6:20 405 384
- 21
- 5.5%
SPP.EMS.00036694 504 LEPA 2/11/2011 7:00 183 172
- 10
- 6.1%
SPP.EMS.00008044 515 SPA 1/12/2011 7:20 1246 1224
- 22
- 1.8%
SPP.EMS.00008939 Includes SPRM, AECC (10%) 520 CSWS|AEPW 2/1/2011 18:40 8104 8049
- 54
- 0.7%
SPP.EMS.00006775 Includes OMPA (25%), AECC (90%) 523 GRDA 1/12/2011 7:20 727 719
- 8
- 1.0%
SPP.EMS.00007327 524 OKGE 2/1/2011 18:20 4876 4756
- 121
- 2.5%
SPP.EMS.00008570 Includes OMPA (70%) 525 WFEC 2/10/2011 7:00 1525 1356
- 170
- 12.5%
SPP.EMS.00009409 Includes OMPA (5%) 526 SPS 2/8/2011 20:30 4242 3917
- 325
- 8.3%
SPP.EMS.00008973 534 SECI 2/1/2011 11:10 761 699
- 63
- 8.9%
SPP.EMS.00008879 Includes MKEC 536 WR 2/8/2011 18:30 4629 4368
- 261
- 6.0%
SPP.EMS.00009470 Includes MIDW 540 MPS 2/10/2011 7:20 1591 1555
- 36
- 2.3%
SPP.EMS.00008345 541 KCPL 2/8/2011 18:50 2719 2633
- 86
- 3.3%
SPP.EMS.00009828 542 KACY 2/8/2011 18:30 381 364
- 18
- 4.9%
SPP.EMS.00007704 544 EDE 2/10/2011 7:10 1160 1149
- 11
- 1.0%
SPP.EMS.00006934 545 INDN 2/8/2011 18:40 190 174
- 17
- 9.5%
SPP.EMS.00006668 640 NPPD 2/1/2011 10:20 2656 2486
- 170
- 6.9%
SPP.CALC.NPPDMKTL 645 OPPD 2/1/2011 18:10 1838 1742
- 95
- 5.5%
SPP.EMS.00018125 650 LES 2/1/2011 18:00 575 519
- 56
- 10.8%
SPP.EMS.00018105 *Note: Planning Peak Load is Load + Losses to compare to the Actual Load reported via ICCP in real-time. Southwest Power Pool Criteria 3.3.3 - 2010/11 Winter Peak Area Actual Peak & Planning Peak Load Comparison
35
SPP Priority Projects
36
SPP Conceptual Expansion
37
Clean Line DC Lines Plains and Eastern (TVA)– 2015? 2 phases 1700 MW each phase Grain Belt Express Spearville, KS to Ameren in Missouri – 2016? Tres Amigas Eastern New Mexico Project Multi Grid capable
Independent Transmission Projects
38
Clean Line Plains – Eastern (TVA) Line
39
Tres Amigas
40
Questions?
41
Current Addresses SPS Planning Website http://www.xcelenergy.com/About_Us/Transmissi
- n/About_Transmission/Planning_for_the_SPS_T
ransmission_System
Pages will be updated with meeting presentations
as soon as possible
“Power for the Plains” Website http://www.powerfortheplains.com/
SPS Planning and other Websites
42
Planning Information http://www.spp.org/section.asp?pageID=128 High level page to their planning information Generation Interconnection Studies and Queue
Status, Aggregate Transmission Service Studies
http://sppoasis.spp.org/documents/swpp/transmi
ssion/studies.cfm
SPP Web Site Links
43
Compliance Update
Compliance Issues
New Standards - 2011 New Standards - October 2011 Compliance Application Notices Event Analysis Process
45
New Standards - 2011
BAL-006-2 Inadvertent Interchange 4/1/2011 BA CIP-001-1a Sabotage Reporting 2/2/2011 RC, BA, TOP, GOP, LSE CIP-005-3a Cyber Security – Electronic Security Perimeters) 2/2/2011 RC, BA, IA, TSP, TO, TOP, GO, GOP, LSE, NERC, RE INT-003-3 Interchange Transaction Implementation 4/1/2011 BA IRO-005-2a RC – Current Day Operations 5/26/2011 RC, BA, TSP, TOP, GOP, LSE, PSE IRO-006-5 RC – Transmission Loading Relief 7/1/2011 RC, BA IRO-006-EAST-1 Transmission Loading Relief Procedure for the Eastern Interconnection 7/1/2011 RC MOD-001-1a Available Transmission System Capability 4/1/2011 TSP, TOP MOD-004-1 Capacity Benefit Margin 4/1/2011 LSE, RP, TSP, TA, TP MOD-008-1 Transmission Reliability Margin Calculation Methodology 4/1/2011 TOP MOD-021-1 Documentation of the Accounting Methodology for the Effects of Demand-Side Management in Demand and Energy Forecasts 4/1/2011 LSE, TP, RP MOD-028-1 Area Interchange Methodology 4/1/2011 TOP, TSP MOD-029-1 Rated System Path Methodology 4/1/2011 TOP, TSP MOD-030-1 Flowgate Methodology 4/1/2011 TOP, TSP PER-004-2 RC – Staffing 4/1/2011 RC PER-005-1 System Personnel Training 4/1/2011 RC, BA, TOP TOP-005-1.1a Operational Reliability Information 5/26/2011 RC, BA, TO, PSE
46
New Standards – October 2011
CIP-001-2a Sabotage Reporting RC, BA, TOP, GOP, LSE EOP-002-3 Capacity & Energy Emergency RC, BA, LSE FAC-002-1 Coordination of Plans for New Gen, Trans, End-User Facilities GO, TO, DP, LSE, TP, PA IRO-002-2 RC - Facilities RC IRO-004-2 RC – Operations Planning BA, TSP, TOP IRO-005-3a RC – Current Day Operations RC, BA, TSP, TOP IRO-008-1 RC – Operational Analyses and Real-time Assessments RC IRO-009-1 RC – Action to Operate within IROLs RC IRO-010-1a RC – Data Specification and Collection RC, BA, IA, GO, GOP, LSE, TOP, TP TOP-003-1 Planned Outage Coordination RC, BA, GOP, TOP TOP-005-2a Operational Reliability Information BA, PSE, TOP TOP-006-2 Monitoring System Conditions RC, BA, TOP, GOP VAR-001-2 Voltage and Reactive Control TOP, PSE, LSE
47
Compliance Application Notices
Provide Transparency to Industry Establish Consistency 15 Current CANs 5 Posted for Comments Many More in Development
48
Event Analysis Process
Purpose Indentify What Transpired Understand Cause of Events Indentify Corrective Actions Disseminate Lessons to Industry Required Forms Appendix A – Brief Report Template Appendix D – Lessons Learned Template Appendix G – Compliance Analysis Template
49
Distribution Connected Generation Interfacing with SPP
50
Need:
Increasing number of small QF wind developers
requesting interconnection to SPS’s distribution lines.
SPS is seeing more and more requests at locations
where generation will EXCEED substation load at low-load levels.
Any generation beyond substation load
requirements will back-feed to the SPS transmission system.
51
Problem:
SPP is the Regional Transmission Organization,
mandated by FERC to ensure reliable supplies of power and adequate transmission infrastructure.
TX and NM regulatory commissions have jurisdiction
- ver SPS’s distribution system. The SPP does not.
Therefore, the SPP cannot require a transmission
impact study of a possible interconnected distribution generator back-feeding the transmission system.
TX and NM do allow the utility to conduct additional
studies needed when studying distribution interconnection.
52
SPS Requirement:
SPS now requires that generation exceeding load by
a mega-watt or more to be studied by SPP.
SPS will request that SPP perform all studies needed
at the cost of the interconnecting customer.
A $30,000 deposit per interconnection must be
provided by customer in advance before request is submitted.
Impact studies are performed by the SPP starting in
April and October of each year and take between 60 and 120 days to complete.
53
SPP Integrated Transmission Update
54
Integrated Transmission Plan – new process to
integrate 20 year, 10 year, and near term (~6 year) planning process
ITP20 - 20 year – economic plan, high level
transmission plan > 230 kV
ITP10 - 10 Year – transmission/economic
reliability plan, folding in 20 year results
ITPNT – Near Term Plan – reliability plan – similar
to old STEP studies
New estimating process and proposed design
standards for regionally recovered projects
SPP ITP Process and Status
55
ITPNT Schedule
1.
Build models – February - April
2.
Perform contingency analysis - April
3.
Distribute results of contingency analysis – April/May
4.
Receive stakeholder feedback - May
5.
Identify solutions – May-August
6.
Summit – Mid July
7.
Draft ITPNT Report - October
8.
Draft STEP Report – November
9.
Deliver STEP Report to TWG for Approval - December
56
ITP10 Schedule
ITP 10 Key Milestones Approximate Completion Date Status
Scoping 1/12/2011
- Futures Review and Approval
4/12/2011
- Steady‐State Model development
4/28/2011
- Constraint assessment
5/30/2011 In‐progress Economic Model development 6/3/2011 In‐progress Metric Selection 6/27/2011 ESWG ‐ about to start ITP Manual Update 6/27/2011 In‐progress Economic assessment 7/14/2011 Reliability assessment 7/14/2011 Per Future Solution development 7/28/2011 Reliability/Economic/Stability Assessment Phase 2 9/8/2011 Benefit calculation 9/26/2011 2011 ITP10 Draft Report 9/26/2011 Refinements to 2011 ITP10 Plans and Report Dec 2011 2011 ITP10 Final Report Dec 2011
57
SPPITPNT/ITP10 Key Dates
September 21-22, 2011 – Planning Summit – Dallas ITPNT Report – November 15, 2011 ITP10 Report – October 1, 2011 SPP BOD Approvals – 3rd Week of January 2012 NTCs/ATP – 2nd week February 2012 ATP – Authority to Plan
58
Proposed ITP Near Term Solutions
2012 Summer Projects Bushland 50 Mvar Cap bank Several 69 kV normal open point changes 2013 Eddy County 230/115 KV 252 MVA Auto #2 2014 Drinkard 14.4 Mvar Cap bank Etter Rural 2nd 14.4 Mvar Cap bank NE Hereford 2nd 115/69 kV auto Cedar Lake 115/69 KV Substation Happy 115/69 KV auto upgrades
59
- 2015
Spearman 115/69 KV auto upgrade
- 2016
Graham 2nd 115/69 kV auto addition
- 2017
Grassland 115/69 kV auto upgrade
- 2022
Wolfforth-Grassland 230 kV line Artesia – 115/69 KV auto upgrades Bailey – Curry 115 kV line addition Canyon E – Canyon W 115 kV – line upgrade Canyon E – Randall 115 kV line addition Carlisle – Wolfforth 230 kV line addition Chaves – Sampson 115 kV – 795 MCM re-conductor Tuco – Stanton 345 kV line and 300 MVA 345/115 kV auto
Proposed ITP Near Term Solutions
60
Proposed ITP10 Solutions (2022 F1 and F2)
Bushland – Hereford Center 230 kV line and new
230/115 kV 252 MVA substation for north Hereford area
Tolk – Tuco 345 kV line Tuco-Yoakum 345 kV line Hitchland 2nd 230/115 kV 252 MVA auto And everything listed previously in the ITPNT list Still working on these cases – may need to be re-run