SLIDE 2 ER LPE Presentation
Slips…. Cont.
State Transportation Improvement Plan (STIP) Refer to Local Agency Guideline Manual (LAG) 12.4
- Among other documents ‐ To authorize federal R/W funds ‐ R/W Phase must be shown in the STIP
- STIP covers 4 year programming period; Updated Annually
- Local Programs / Federal Highways (FHWA) can authorize these funds if R/W Phase is in any of the 4 years.
- SRTC has 2 year programming window for authorization by internal policy
Typical Reasons why R/W Phase not in the STIP
- Funds not reasonably identified to support the R/W Phase within a 4 year programming period
- Early Project Scoping didn’t identify the need for property rights
- During Project Development/Design, R/W needs are discovered
- Lack of communication ‐ Programming staff not told that the project will be built in the coming year
- Was in previous year’s STIP, but Agency forgot to carry it forward into next years STIP, etc.
Adding Project and/or R/W Phase through an Amendment can delay project 1.5 to 2.5 months. Depending on timing of Amendment‐ Could cost agency a construction season.
Trips that can CostYou‐ Big Time
Local Agency funded R/W phase (Assuming fed money in Construction Phase)
- Potential of less involvement or oversight by LPO early in the process
- Make LPO aware of intent, and involve Terri early
- Must follow the Uniform Relocation Act to acquire property
- Must have approved R/W Procedures
- To Certify, Terri must review and approve R/W Plan, Relocation Plan, Appraisals, PFE, and Parcel Files (Provide as you go)
- Must be Certified before requesting Construction funds.
When does the R/W Phase Begin?
- Once R/W funds are authorized – R/W Phase Begins with Offers.
- But Before Offers are made, must have:
- Approved R/W of Procedures
- Your Offer letter(s) reviewed and approved by Terri
Trips that can CostYou‐ Big Time….. Cont.
Temporary Construction Easements (TCE), and Temporary Construction Permits (TCP)
- If TCE’s purchased too early, may expire prior to construction or completion of the project
- Temporary Construction Permits (TCP) vs. TCE’s (LAG 25, Appendix 25.174 & 175)
- Meet with LPO if you’re thinking all you need are TCP’s to construct your project…. May not be the case.
- TCP’s – Review 49 CFR 24.101(c)(2) – Basically – Work done through mutual agreement for the sole benefit of the property owner
- If Project just needs TCP’s or General Permit from another Governmental Agency, No R/W Cert Required
When Willing Sellers become Unwilling Sellers
- Eminent Domain – Condemnation. Many LA’s are reluctant to use this tool to meet project timelines..
- With Condemnation comes Possession and Use Hearings, Court dates, etc.
- Non use of Eminent Domain – Can lead to Protracted Acquisition Process
- Be very aware of Project Agreement End Date (LAG 22.1)
- Be very aware of other time sensitive funding commitments
- Communicate with Project Manager on R/W process timelines
- Directly affects project schedule milestones; R/W Cert, Advertisement Date; CN Start
2