8/10/2020 SLIM Presentation 1
SLIM: Short Cycle Time and Low Inventory in Manufacturing at - - PowerPoint PPT Presentation
SLIM: Short Cycle Time and Low Inventory in Manufacturing at - - PowerPoint PPT Presentation
SLIM: Short Cycle Time and Low Inventory in Manufacturing at Samsung Electronics Corp., (SEC) 8/10/2020 SLIM Presentation 1 Introductions Prof. Rob Leachman, UCB IEOR Dept., technical author and SLIM project manager Dr. Jeenyoung Kang,
8/10/2020 SLIM Presentation 2
Introductions
- Prof. Rob Leachman, UCB IEOR Dept., technical
author and SLIM project manager
- Dr. Jeenyoung Kang, Leachman & Associates LLC,
technical author (UCB IEOR PhD ‘96)
- Dr. Vincent Lin, Leachman & Associates LLC,
technical author (UCB IEOR PhD ‘99)
- Mr. J. W. Kim, SEC Executive VP Semiconductor
Manufacturing, SLIM project sponsor
8/10/2020 SLIM Presentation 3
Introduction to SEC
- Market share leader in DRAMs, SRAMs,
TFT-LCDs
- Design and fabrication of integrated circuits
centered in Kiheung, Korea
– 11 large fab lines, 20,000 employees – 500,000 wafers per month
8/10/2020 SLIM Presentation 4
SEC in Kiheung, Korea
8/10/2020 SLIM Presentation 5
The business problem
- 1995: DRAM manufacturers enjoy record
profits
- At end of 1995, DRAM market changed
from seller’s market to buyer’s market
- Urgent need to reduce manufacturing cycle
time
8/10/2020 SLIM Presentation 6
The business problem
8/10/2020 SLIM Presentation 7
The project
- SLIM project initiated in March, 1996
- Ground rules:
– joint effort of SEC and outside IE/OR experts – cycle time reduction as early as possible – consensus approval and credibility of solutions – no diminution of yields or productivity
8/10/2020 SLIM Presentation 8
Some fab terminology
- Cycle time (a.k.a. lead time or flow time)
- WIP (work-in-process)
- Fab-out schedule
- Steppers (photolithography machines,
usually the fab bottleneck)
8/10/2020 SLIM Presentation 9
The challenge
Fabrication of advanced memory devices
- Re-entrant manufacturing process
- Fragile manufacturing process
8/10/2020 SLIM Presentation 10
The challenge (cont.)
Device Step Qualified Steppers XC 1.0 #2, #5, #68 ZB 1.0 #1, #2, #5 UC 1.0 #8, #9 SB 1.0 #1 XC 5.0 #61, #65, #86
8/10/2020 SLIM Presentation 11
SLIM scheduling principles
8/10/2020 SLIM Presentation 12
Conventional paradigm: lot-based dispatching
- Scheduling objects: lots
- Paradigm: when machine is idle, select suitable lot
with the highest priority
- Determine efficient priority rules
– Most commonly, priority is given to lots determined to be behind schedule
8/10/2020 SLIM Presentation 13
Problems with conventional lot dispatching
A-1 B-1 A-2 B-0 A-1 B-1 Machine M1 Machine M2 Start of shift
Note: “A-1” denotes a lot of device A with a slack score = 1.
Time Lot dispatching systems schedule too many changeovers.
8/10/2020 SLIM Presentation 14
More problems with lot dispatching
Cycle time to fab out A-1 A-4 A-3 A-2 B-3 B-2 B-1 3 2 1
Note: “A-1” denotes a lot of device A with slack = 1
A-1 is the wrong choice! Lot due dates become stale because
- f lots passing one another, changes to the fab out schedule,
and downstream yield losses.
8/10/2020 SLIM Presentation 15
SLIM paradigm: manage WIP
- Scheduling objects: device/steps
- Paradigm: determine how many lots of each step of
each device should be completed this shift, and allocate to machines intelligently
- Maintain target WIP profile, maximize bottleneck
throughput, and control frequency of recipe changes
- Schedule non-production work, not just production
8/10/2020 SLIM Presentation 16
SLIM schedules
A-1 A-1 A-2 B-0 B-1 B-1 Machine M1 Machine M2 Start of shift Time
8/10/2020 SLIM Presentation 17
Fab out schedule
SLIM works to a target fab out schedule
- Expressed through continuous-time for every
device
- Analyzed to be capacity-feasible and consistent
with the WIP
8/10/2020 SLIM Presentation 18
Target cycle time
- The target cycle time for each device is established
according to standard learning curves:
1 1.5 2 2.5 1 2 3 4 5 6 7 8 9 10
Months since qualification Cycle time / mature cycle time Similar technology Different Very different
8/10/2020 SLIM Presentation 19
Target cycle time for steps
- The process time plus material handling time for each
step is termed the standard cycle time (sct).
- The difference between the target cycle time and the
total standard cycle time for a device is its total buffer time (TBT).
- A key strategy of SLIM concerns how one allocates
TBT among steps of the process flow...
8/10/2020 SLIM Presentation 20
Allocating buffer time
WIP profile when there is no process or equipment trouble: Photo Layer 1 Photo Layer 2 Photo Layer 3 Photo Layer 4
Fab process
8/10/2020 SLIM Presentation 21
Allocating buffer time
Photo Layer 1 Photo Layer 2 Photo Layer 3 Photo Layer 4
Fab process
Process trouble WIP profile when there is process trouble: Layer 3 photo WIP running out
8/10/2020 SLIM Presentation 22
Target cycle time for steps
- SLIM allocates TBT to steps according to statistics
- n actual cycle time.
- Non-bottleneck steps are not allocated buffer time.
- Bottleneck steps are allocated buffer time in
proportion to the discrepancy between the upstream actual cycle time and the standard cycle time ...
8/10/2020 SLIM Presentation 23
Target cycle time for steps
where ,
ij ij ij
bt sct tct + =
, device
- n
step bottleneck For i j
( )
( )
i NB j ij ij ij ij ij
TBT SCT ACT SCT ACT bt
i
∑
=
− − =
1
. and 1 steps bottleneck between time cycle standard total the is and time cycle actual average the is CT and j j SCT A
ij ij
−
Target cycle time for steps (cont.)
- Alternatively, if we have data on the standard
deviation of layer cycle times, we could use that data to set target buffer times:
8/10/2020 SLIM Presentation 24
( )
i NB j ij ij ij
TBT bt
i
∑
=
=
1
σ σ
. product
- n
and 1 steps bottleneck between time cycle actual
- f
deviation standard the is and i j j
ij
− σ
8/10/2020 SLIM Presentation 25
Target cycle time proposed by others
- Use a common multiple of theoretical cycle time, or
- Set target proportional to actual or simulated average cycle
time
- Targets set this way average over events when the WIP is
dislocated from where it is needed. They do not try to concentrate as much WIP in front of bottleneck steps downstream from trouble spots as does SLIM, and consequently they require more WIP to achieve a target level of utilization.
8/10/2020 SLIM Presentation 26
Ideal production quantity
1 2 3 4 5 6 7 8 9 Fab out schedule Target cycle time to fab out
- IPQ of a device/step = how many units need to be
completed by the end of the shift to meet the target cycle time and the target fab outs
8/10/2020 SLIM Presentation 27
Ideal production quantity
- IPQ = (Target fab outs due until the target cycle time
to fab out plus one shift)
- (actual fab outs to date)
- (actual downstream WIP)
1 2 3 4 5 6 7 8 9 Fab out schedule Target cycle time to fab out
8/10/2020 SLIM Presentation 28
Ideal production quantity
( )( )
− − =
∑ ∫ ∫
+ = + ∞ − ∞ − ik N j k ik TCTFO i i ij ij
AW FY dt t AFO dt t TFO FY IPQ
i ij
1 33 .
) ( ) ( 1
- IPQ = (Target fab outs due until the target cycle time
to fab out plus one shift) - (actual fab outs to date)
- (actual downstream WIP)
8/10/2020 SLIM Presentation 29
Schedule score
- SS of device/step = how many days early or late is
the current production of this device/step
- SS = - IPQ / (Avg. fab out rate over cycle time to out)
- SLIM prioritizes device/steps by SS, and strives to
complete the IPQ for each device/step
8/10/2020 SLIM Presentation 30
SS vs. Least slack (“Delta days”)
FAB 6: U27YJ
WAFER START PADOX 20 NITRIDE DEP 20 DUV PHOTO 20 INSITU DRY ETCH 20 STI OXIDATION 20 STI NITRIDE DEP 20 STI RINSE 20 TEOS DEP 02 BOE/STRIP PIRANHA WET NIT STRIP/SC1 15 I-LINE PHOTO 15 PIRANHA/HF CLN 50 SACOX CLN 35 I-LINE PHOTO 50 GATEOX 2 50 GATEOX 2 RPN 50 POLY DEP 22 I-LINE PHOTO 23 I-LINE PHOTO NWELL IMP 2 P+ POLY IMP 23 POST-IMP HF/SC1 33 DUV PHOTO 50 NIT BUFF CMP 50 DUV PHOTO 50 FIRST PART ETCH 50 HF/WAPM CLN 50 FRST PART NIT DEP 50 LAST PART ETCH 50 SEL SDOX WAPM CLN 50 SELECTIVE SDOX 39 DUV PHOTO 34 I-LINE PHOTO 50 NIT SPACER DEP 50 NIT SPACER HF CLN 36 I-LINE PHOTO 37 I-LINE PHOTO 37 PIRANHA/HF CLN S/D ANNEAL 37 POST-IMP HF CLN 41 NITRIDE DEP 41 BPSG REFLOW 41 SON BPSG CMP 41 DUV PHOTO 41 POLY SQ2 CLN 41 POLY DEP 40 TEOS DEP 40 DUV PHOTO 40 OXIDE DRY ETCH 55 NITRIDE CAP DEP 55 DUV PHOTO 55 INSITU DRY ETCH 55 HF/WAPM CLN 55 NIT SPACER DEP 49 BPSG REFLOW 49 DUV PHOTO 49 POLY SQ2 CLN 49 POLY DEP 42 NITRIDE DEP 42 PSG DEP 42 DUV PHOTO 42 OXIDE DRY ETCH 42 CNT CMBO POLY DEP 42 CONT ANNEAL 42 CONT AL2O3 DEP 52 SFD TIN DEP 52 CELL POLY DEP 52 PRE-WSIX HF CLN 52 INSITU DRY ETCH 60 BPSG DEP 60 DUV PHOTO 60 OXIDE DRY ETCH 60 PREMTL SQ2 CLN 60 CVD TIN DEP 60 W CMP 91 ILD DEP 91 DUV PHOTO 61 COPPER DUV PHOTO 92 COPPER DUV PHOTO 92 CU PLATING 92 CU ANNEAL 82 PASS NITRIDE DEP 82 BKSIDE NIT FLP DN 82 BKSIDE NIT DEP 82 CU POLYIMIDE CURE 82 CU OXIDE DRY ETCH TO PROBE 9000-LOGIN PROBE PRB BOND PAD METAL PLATING MACRO INSP1.05 1.75 1.20 1.00 2.10 1.15 1.44 2.93 2.86 1.18 1.59 1.92 1.04 1.71 1.21 2.45 1.08 3.23 1.05 1.03 10.00
100 200 300 400 500 600 700 800 900
Wafers
- 10
- 8
- 6
- 4
- 2
2 4 6 8 10
Days
3750 3824 3348 3471 3752 3677 3015 3459 4278 3889 3823 4019 3814 3615 4096 3769 3242 3814 1895 1475 Wafers w/in MTTS week Wafers DUE in week
- .53 Mean Delta .8583 Mean CR
35013 Total Wafers 08/11/06 09:06 AM - Inventory current as of 08/11/06 07:48 AM
Base: FAB 6 U27YJ Inc.: FAB 6 U27YJ RWK: Yes HOLD: Yes HOT: Yes RUN: Yes Max MTAS : 10 WIP Labels: > 150 Start: End: Lot # Filter: LIKE '*' PC Filter: LIKE '*' PC Rt. Filter: LIKE '*'
- Trav. Filter: LIKE '*'
Part Filter: LIKE '*'
- Des. Filter: LIKE '*'
- Ven. Filter: LIKE '*'
Cycle Time-66 Line Yield-97%
Scheduling Score Delta
8/10/2020 SLIM Presentation 31
Balance index
According to BI, step B should be dispatched first
Step B Next photo step
Downstream WIP situation:
Step A Next photo step
8/10/2020 SLIM Presentation 32
Balance index
- BI of non-bottleneck step = score indicating relative
surplus or deficit of actual WIP vs. target WIP downstream up to next bottleneck step: BI = (AW – TW)/TW where AW is the actual WIP summed over all steps up to the next bottleneck step and TW is the target WIP up to the next bottleneck step
- SLIM also considers BI in addition to SS when
prioritizing device/steps.
8/10/2020 SLIM Presentation 33
Photo Diffusion Thin Films Etch Fab In Fab Out SLIM - S
- Schedule scanners
so as to complete IPQs and for maximum utilization
SLIM - I
- Control fab-ins
according to target WIP levels and stepper capacity
SLIM - D
- Form batches
- f device/steps with
low SS and low BI WIP
SLIM – E,T
- Schedule
device/steps with low SS and low BI
SLIM scheduling
8/10/2020 SLIM Presentation 34
SLIM logic
- Make a shift schedule, with on-line updates
- Prioritize device/steps by SS and BI
- First pass: Assign WIP to complete IPQs by
end of shift
– Choose machine based on setup avoidance, least candidate WIP, etc.
- Second pass: Assign remaining WIP
– Save changeovers where possible
8/10/2020 SLIM Presentation 35
SLIM-S schedule
8/10/2020 SLIM Presentation 36
SLIM planning
- A sophisticated linear programming model
(“SLIM-O”) is utilized to identify specific bottlenecks for fab-out demands
- SLIM-O is utilized to plan the ramp-up of new
devices (“capacity simulation”)
– how many machines to install and when – which machine/steps to qualify when
8/10/2020 SLIM Presentation 37
SLIM planning
SLIM-O models the inter-step arrangement constraints:
Step Qualified machines
1.0 #04 #37 #39 5.0 #44, #46 #44, #45 #01, #03 9.0 #44, #46, #57 #44, #45, #57 #01, #03, #57
SLIM-O optimizes the routing of WIP through the machines
8/10/2020 SLIM Presentation 38
Key ideas of SLIM
- We can reduce total WIP and cycle time by wisely
positioning the buffer WIP
– Concentrate buffer WIP at the bottleneck steps following the troublesome portions of the process flow – Then we can lower the overall factory WIP and still achieve the same fab throughput
- Good scheduling can increase area throughput for the
same level of WIP
– Then we can lower overall WIP some more
8/10/2020 SLIM Presentation 39
SLIM implementation
8/10/2020 SLIM Presentation 40
SLIM teams
- SLIM project teams for pairs of fab lines
– First team formed in March, 1996 for Lines 4 and 5 – Team for Lines 6 and 7 started March, 1997 – Ultimately, 8 SLIM teams were formed
8/10/2020 SLIM Presentation 41
SLIM steering committee
8/10/2020 SLIM Presentation 42
SLIM teamwork
- Inter-disciplinary team membership
– including several with graduate OR/MS training
- Developed SLIM database and SLIM modules
- Trained 3,000 people in SLIM logic & use
8/10/2020 SLIM Presentation 43
SLIM training
8/10/2020 SLIM Presentation 44
SLIM results
8/10/2020 SLIM Presentation 45
SEC DRAM cycle times
20 30 40 50 60 70 80 90 100
Dec-95 Jun-96 Dec-96 Jun-97 Dec-97 Jun-98 Dec-98 Jun-99
- Avg. fab cycle time (days)
4M 16M 64M 128M
SLIM begins SLIM begins Standard cycle time SLIM begins
- n all lines
8/10/2020 SLIM Presentation 46
Benefits of SLIM
- Faster rate of yield improvement
- Reduction of late production deliveries
Before After At Die out 30% 4% At Test out 26% 3%
- Reduced lead times to customers
- Higher selling prices ...
8/10/2020 SLIM Presentation 47
Financial impact of SLIM
- Sales revenues for the DRAM output of the
Kiheung fab lines March, 1996 - December 2000 were tallied: $21.9 billion
- Sales revenues were re-computed assuming
fab cycle times had stayed at 80 days
8/10/2020 SLIM Presentation 48
DRAM selling prices
0.00 20.00 40.00 60.00 80.00 100.00 120.00 140.00 160.00 180.00 200.00 Mar-96 Sep-96 Mar-97 Sep-97 Mar-98 Sep-98 Mar-99 Sep-99
Average selling price ($)
4M 16M 64M 128M
8/10/2020 SLIM Presentation 49
Financial impact of SLIM
- The result: SLIM increased DRAM sales
revenues by US $954 million
– Including non-DRAM production, the revenue gain was $1.1 billion just during the project, billions more in subsequent years
- Market share up from 18% to 22%, later up
to 34%
8/10/2020 SLIM Presentation 50
Competitive impact of SLIM
- Japanese companies retrench from DRAM
market, IBM and TI exit market
- Hynix effectively bankrupted, Micron and
Infineon suffer heavy losses
- SEC becomes most profitable
semiconductor manufacturer
8/10/2020 SLIM Presentation 51
Adoption of Methodology
- SLIM ported to SEC’s LCD factories
- After publication, SLIM methodology
increasingly adopted by other semiconductor manufacturers and influencing commercial software vendor
- fferings and customer choices
8/10/2020 SLIM Presentation 52
Summary of SLIM
- Target cycle time methodology
- On-line scheduling
- Simulation
- Advanced LP planning
- Trained 3,000 people