SLAM Project Update October 29, 2012 We Have a Project A New Building: Collocate Library Archives and Museum functions in a state of the art facility Provide appropriate protection for our States treasures Staff Integration:


slide-1
SLIDE 1

SLAM Project Update October 29, 2012

slide-2
SLIDE 2
slide-3
SLIDE 3

We Have a Project A New Building:

  • Collocate Library Archives and Museum functions in a state of the art facility
  • Provide appropriate protection for our State’s treasures

Staff Integration:

  • Provide better access to the combined collections
  • Create efficiencies that allow for increased statewide outreach

Digital Archives

  • Create a common digital archive protocol
  • Create improved digital access and a new digital portal
slide-4
SLIDE 4

SLAM Project Overlay in Willoughby District

slide-5
SLIDE 5

Collaborations – Removing Barriers

slide-6
SLIDE 6

Mitigation of Historic Resources

slide-7
SLIDE 7

Mitigation –Alaska Purchase Sesquicentennial

slide-8
SLIDE 8

Mitigation – Alaska Purchase Sesquicentennial

slide-9
SLIDE 9

BUILDING QUALITY

  • New building location
  • On board with CBJ Willoughby District Land Use p

High performance building envelope. High performance environmental management systems. High quality installation. High quality finishes.

slide-10
SLIDE 10

BUILDING DIAGRAM

slide-11
SLIDE 11

MUSEUM EXHIBITS PUBLIC BACK OF HOUSE SECURE COLLECTIONS MECH/ELECT

BUILDING DIAGRAM

slide-12
SLIDE 12

LIBRARY PUBLIC BACK OF HOUSE SECURE STORAGE MECH/ELECT BACK OF HOUSE BACK OF HOUSE

BUILDING DIAGRAM

slide-13
SLIDE 13

BUILDING QUALITY

slide-14
SLIDE 14

BUILDING QUALITY

slide-15
SLIDE 15

BUILDING QUALITY

slide-16
SLIDE 16

Funding

  • Currently funded at $81.45M
  • Additional $50M is required to complete the project.
  • Project is fully negotiated and priced, all phases, for a

turnkey facility.

  • Construction costs, for all phases of work, are

guaranteed by our construction contractor through July 2013.

slide-17
SLIDE 17

Project Schedule - 3.5 Years

slide-18
SLIDE 18

Phased Construction Staging

slide-19
SLIDE 19

Phase 2A

slide-20
SLIDE 20

Artifact Transfer

slide-21
SLIDE 21

Museum Demo

slide-22
SLIDE 22

Phase 2B

slide-23
SLIDE 23

Traffic Control

Project Site: See Site Plans

PHASE 2A ROUTE PHASE 2B ADDITIONAL ROUTE

Southeast Lot Construction Parking

~OCEAN~

Southwest Lot Office Trailers Egan

  • W. Willoughby

Glacier Whittier

slide-24
SLIDE 24

Offsite Storage Location

Museum Site Offsite Laydown

slide-25
SLIDE 25

Risks and Challenges

  • Confined Site
  • Hazmat
  • Project Phasing
  • Logistics
  • Weather
  • Tidal Influence
  • Level of Finishes
slide-26
SLIDE 26

Tidal Influence Graph

Bottom of Excavation

2’ Below Slab

Bottom of Slab

slide-27
SLIDE 27

Design Considerations for Tidal Influence

slide-28
SLIDE 28

Upcoming Activities