55th ANNUAL MEETING – Celebrating Concrete Victories! – NOV 27-29, 2018
Shear Cracking Phenomena / Solutions
John M. Becker, P.E. ACPA Pennsylvania Chapter
Shear Cracking Phenomena / Solutions John M. Becker, P.E. ACPA - - PowerPoint PPT Presentation
Shear Cracking Phenomena / Solutions John M. Becker, P.E. ACPA Pennsylvania Chapter 55 th ANNUAL MEETING Celebrating Concrete Victories! NOV 27-29, 2018 The Definition of a Good Presentation A Go Good Beg Begin innin ing An And Ho
55th ANNUAL MEETING – Celebrating Concrete Victories! – NOV 27-29, 2018
John M. Becker, P.E. ACPA Pennsylvania Chapter
In this example there are six 30-inch tie-bars per 15-foot long slab (tie-bars are equally spaced 30-inches apart)
15”
This was the tie-bar design standard in Pennsylvania (prior to circa 2008-10) #5 tie-bars, 30-inches long (either Grade 40 or Grade 60)
15”
Typically placed in warmer months
Note: Many causes, including high-friction, high-strength bases,
Mainline placed in warmer months
Dominant Joint (typically every third to fifth joint opens up first)
Note: Ambient (seasonal) temperatures often different between mainline paving and shoulder paving.
Mainline placed in warmer months Typically placed in cooler months Dominant joints typically open up even wider with cooler temperatures First joint to open up in shoulder does not necessarily line up with mainline dominant joint
Note: Edge restrained from closing by tiebars, base friction, and/or mortar intrusion.
Sinusoidal Shaped Shear Crack Cracks Initiate over Dowels
None (that C/S was aware of) One project (mortar intrusion sometimes cited as root cause) Occasionally
Source: Survey of ACPA Chapter/State Executives, October/November 2018
Alaska Hawaii
6-inches
Adjacent joints opening up resulting in loss of aggregate interlock Long-term performance of expansion joint material Constructability; how to slip form with DBI Has never been tried in the U.S. for preventing shear cracking
(2004 ACPA R&T Update)
30” 30”
(2004 ACPA R&T Update)
120” 60”
(2004 ACPA R&T Update)
30” 30”
Full-Depth Sawing of Shoulder allows Room for Mainline to Expand
Mainline dominant joint Sawcut Full-Depth the Shoulder to Match the Width of the Dominant Joint in the Travel Lane
This option works ONLY for Un-Dowelled Shoulders
Other Options (Done on One Project in 2004)
(Other Options)
Observations are that this is not consistently being done No more duct tape
Observations are that this is rarely being done
We will eliminate one additional tie bar at dominant joints when placing concrete pavement adjacent to slab previously placed or any slab placed Criteria still TBD
When temperature for second placement is below 50F OR when delta temperature for second placement is 35F below first placement OR simply between October 1 and March 1
Joints in second placement parallel to dominant joints may be saw-cut using an early entry saw or by other means to “encourage” the first cracks in the second placement to line-up with first placement dominant joints
Tie-bar design will be re-evaluated as part of our Department /Industry Jointing Group for standard slabs /thicknesses
Seven #4 bars? Four #6 bars? Placement of tie-bar any closer than 30” from transverse joints off the table Other materials (e.g., FRP?)
Tie-bar spacings for non-standard slabs also to be evaluated
12x12 slabs 6x6x6 slabs
Keeping it simple is an objective!
Drill 2-inch diameter stress relief hole and fill with flexible material Cross-stitch crack Cut tie-bars to eliminate stress
55th ANNUAL MEETING – Celebrating Concrete Victories! – NOV 27-29, 2018
Philadelphia/King of Prussia
Pavement Design
Pavement Design
55th ANNUAL MEETING – Celebrating Concrete Victories! – NOV 27-29, 2018
John M. Becker, P.E., President ACPA Pennsylvania Chapter 800 N. 3rd Street, Suite 503 Harrisburg, PA 17102 Jbecker@pavement.com 717-215-0509 www.LongerLifePavement.com