SERTP 3 rd Quarter Meeting 2nd RPSG Meeting September 26 th , 2019 - - PowerPoint PPT Presentation

sertp 3 rd quarter meeting
SMART_READER_LITE
LIVE PREVIEW

SERTP 3 rd Quarter Meeting 2nd RPSG Meeting September 26 th , 2019 - - PowerPoint PPT Presentation

2019 SERTP SERTP 3 rd Quarter Meeting 2nd RPSG Meeting September 26 th , 2019 Web Conference 2019 SERTP Process Information The SERTP process is a transmission planning process. Please contact the respective transmission provider for


slide-1
SLIDE 1

SERTP – 3rd Quarter Meeting

2nd RPSG Meeting

September 26th, 2019 Web Conference

2019 SERTP

slide-2
SLIDE 2

Process Information

  • The SERTP process is a transmission planning process.
  • Please contact the respective transmission provider for

questions related to real-time operations or OATT transmission service.

  • SERTP Website Address:

– www.southeasternrtp.com

2

2019 SERTP

slide-3
SLIDE 3

Purposes & Goals of Meeting

  • Economic Planning Studies

– Preliminary Results – Stakeholder Input/Discussion

  • Miscellaneous Updates
  • Next Meeting Activities

3

2019 SERTP

slide-4
SLIDE 4

Economic Planning Studies

4

SERTP Preliminary

Economic Planning Studies

slide-5
SLIDE 5

Economic Planning Studies Process

  • Economic Planning Studies were chosen by the Regional Planning

Stakeholder Group “RPSG” in March at the 2019 SERTP 1st Quarter Meeting.

  • Key study criteria, methodologies, and input assumptions were finalized

in May.

  • These studies represent analyses of hypothetical scenarios requested by

the stakeholders and do not represent an actual transmission need or commitment to build.

5

Economic Planning Studies

slide-6
SLIDE 6

Economic Planning Studies Process

  • SERTP Sponsors identify the transmission requirements needed to move

large amounts of power above and beyond existing long-term, firm transmission service commitments

– Analysis are consistent with NERC standards and company-specific planning criteria

  • Models used to perform the analysis incorporate the load forecasts and

resource decisions as provided by LSEs

– Power flow models are made available to stakeholders to perform additional screens or analysis

6

Economic Planning Studies

slide-7
SLIDE 7

Economic Planning Studies

  • Southern BAA to Santee Cooper Border

– 500 MW (2020 Summer Peak)

  • Duke Energy Carolinas to Santee Cooper Border

– 500 MW (2020 Summer Peak)

  • Southern BAA to Santee Cooper Border

– 800 MW (2020 Summer Peak)

  • Duke Energy Carolinas to Santee Cooper Border

– 500 MW (2024 Winter Peak)

  • Southern BAA to Santee Cooper Border

– 1000 MW (2024 Winter Peak)

7

Economic Planning Studies

slide-8
SLIDE 8

Power Flow Cases Utilized

  • Study Years:

– 2020 and 2024

  • Load Flow Cases:

– 2019 Series Version 2 SERTP Regional Models – Summer Peak and Winter Peak

8

Economic Planning Studies

slide-9
SLIDE 9

Preliminary Report Components

  • The SERTP reported, at a minimum, results on elements of 115 kV and

greater:

– Thermal loadings greater than 90% for facilities that are negatively (+5%) impacted by the proposed transfers – Voltages appropriate to each participating transmission owner’s planning criteria – Overloaded facilities that had a low response to the requested transfer were excluded and issues identified that are local in nature were also excluded

  • For each economic planning study request, the results of that study

include:

  • 1. Limit(s) to the transfer
  • 2. Potential transmission enhancement(s) to address the limit(s)
  • 3. Planning-level cost estimates and in-service dates for the potential

transmission enhancement(s)

9

Economic Planning Studies

slide-10
SLIDE 10

Process Information

  • The following information depicts potential enhancements for the

proposed transfer levels above and beyond existing, firm commitments. Therefore, this information does not represent a commitment to proceed with the recommended enhancements nor implies that the recommended enhancements could be implemented by the study dates (2020 or 2024).

  • These potential solutions only address constraints identified within the

SERTP Sponsors’ areas that are associated with the proposed transfers. Other Balancing Areas were not monitored which could result in additional limitations and required system enhancements.

10

Economic Planning Studies

slide-11
SLIDE 11

Southern BAA to Santee Cooper Border 500 MW

11

Economic Planning Studies – Preliminary Results

Economic Planning Studies

slide-12
SLIDE 12

Study Assumptions

  • Source: Generation within

Southern BAA

  • Sink: Uniform generation

scale within Santee Cooper

  • Transfer Type: Generation to

Generation

  • Year: 2020
  • Load Level: Summer Peak

12

Southern BAA to Santee Cooper – 500 MW

Source Sink

slide-13
SLIDE 13

13

SOURCE SINK FLOWS > 5%

%

Transfer Flow Diagram (% of Total Transfer)

Southern BAA to Santee Cooper – 500 MW

SBAA FRCC SCE&G TVA DEC DEPW DEPE SC MISO OVEC PJM EXTERNAL LG&E/KU AECI SPP PS

2.0 % 0.0 % 4.0 % 1.0 % 1.0 % 1.0 % 0.0 % 2.0 % 1.0 % 2.0 % 9.0 % 1.0 % 8.0 % 0.0 % 1.0 % 29.0 % 19.0 % 26.0 % 17.0 % 1.0 % 1.0 % 3.0 % 24.0 % 23.0% 24.0 % 0.0 % 1.0 % 9.0 % 12.0 % 12.0 % 0.0 % 2.0 % 2.0 % 1.0 % 9.0 % 1.0 % 1.0 % 0.0 % 2.0 % 5 %

slide-14
SLIDE 14

Transmission System Impacts

  • Transmission System Impacts Identified:

– Significant constraints were identified in the following SERTP Balancing Authority Areas:

  • DEC
  • Potential Transmission Enhancements Identified:

– (DEC) Two (2) 100kV Transmission Line Upgrades

SERTP TOTAL ($2019) = $11,000,000

14

Southern BAA to Santee Cooper – 500 MW

slide-15
SLIDE 15

Significant Constraints Identified – DEC

15 Thermal Loadings (%)

Potential Enhancement Limiting Element Rating (MVA) Without Request With Request P1 Bush River Tie – Saluda Hydro 100kV T.L. 79 101.5 107.4 P2 Laurens Tie – Bush River Tie 100kV T.L. 65 93.9 100.1

Table 1: Significant Constraints - DEC

Southern BAA to Santee Cooper – 500 MW

slide-16
SLIDE 16

Potential Enhancements Identified – DEC

16

Item Potential Enhancement Planning Level Cost Estimate P1 Bush River Tie – Saluda Hydro 100kV double circuit T.L.

  • Rebuild the 2.7 miles of Bush River Tie – Saluda Hydro 100kV

double circuit transmission line with 954 ACSR conductors rated to 120˚C $4,900,000 P2 Laurens Tie – Bush River Tie 100kV double circuit T.L.

  • Rebuild approximately 2.8 miles of Laurens Tie – Bush River Tie

100kV double circuit transmission line with 954 ACSR conductors rated to 120˚C. $5,100,000

DEC TOTAL ($2019) $ 11,000,000(1)

(1) Total planning level cost estimate does not include the cost of projects that are included in SERTP Sponsors’ expansion plans and are scheduled to be completed by June 1st of the study year. The studied transfer depends on these projects being in-service, and the cost to support the study transfer could be greater than the total shown above if any of these projects are delayed or cancelled.

Table 2: Potential Enhancements - DEC

Southern BAA to Santee Cooper – 500 MW

slide-17
SLIDE 17

Potential Enhancement Locations – DEC

17

P1 P2

Southern BAA to Santee Cooper – 500 MW

slide-18
SLIDE 18

Significant Constraint (P1) – DEC

18

Southern BAA to Santee Cooper – 500 MW

slide-19
SLIDE 19

Potential Enhancement (P1) – DEC

19

Southern BAA to Santee Cooper – 500 MW

slide-20
SLIDE 20

Significant Constraint (P2) – DEC

20

Southern BAA to Santee Cooper – 500 MW

slide-21
SLIDE 21

Potential Enhancement (P2) – DEC

21

Southern BAA to Santee Cooper – 500 MW

slide-22
SLIDE 22

Transmission System Impacts – SERTP

22

Balancing Authority Planning Level Cost Estimate

Associated Electric Cooperative (AECI) $0 Duke Carolinas (DEC) $11,000,000 Duke Progress East (DEPE) $0 Duke Progress West (DEPW) $0 Louisville Gas & Electric and Kentucky Utilities (LG&E/KU) $0 PowerSouth (PS) $0 Southern (SBAA) $0 Tennessee Valley Authority (TVA) $0

SERTP TOTAL ($2019) $11,000,000

Table 3: Transmission System Impacts - SERTP

Southern BAA to Santee Cooper – 500 MW

slide-23
SLIDE 23

Duke Energy Carolinas to Santee Cooper Border 500 MW

23

Economic Planning Studies – Preliminary Results

Economic Planning Studies

slide-24
SLIDE 24

Study Assumptions

24

Duke Energy to Santee Cooper – 500 MW

Source Sink

  • Source: Generation within

Duke Energy Carolinas

  • Sink: Uniform generation

scale within Santee Cooper

  • Transfer Type: Generation to

Generation

  • Year: 2020
  • Load Level: Summer Peak
slide-25
SLIDE 25

25

SOURCE SINK FLOWS > 5%

%

Transfer Flow Diagram (% of Total Transfer)

Duke Energy to Santee Cooper – 500 MW

SBAA FRCC SCE&G TVA DEC DEPW SC MISO OVEC PJM EXTERNAL LG&E/KU AECI SPP PS

1.0 % 0.0 % 1.0 % 1.0 % 2.0 % 0.0 % 0.0 % 0.0 % 0.0 % 0.0 % 0.0 % 1.0 % 0.0 % 0.0 % 13.0 % 7.0 % 11.0 % 8.0 % 1.0 % 0.0 % 1.0 % 15.0 % 24.0 % 28.0% 35.0 % 2.0 % 2.0 % 34.0 % 2.0 % 1.0 % 1.0 % 0.0 % 0.0 % 0.0 % 0.0 % 1 .0 % 8.0 %

DEPE

3.0 % 3.0 % 1.0 %

slide-26
SLIDE 26

Transmission System Impacts – SERTP

  • Transmission System Impacts Identified:

– Significant constraints were identified in the following SERTP Balancing Authority Areas:

  • DEC
  • Potential Transmission Enhancements Identified:

– (DEC) Two (2) 100kV Transmission Line Upgrades

SERTP Total ($2019) = $11,000,000

26

Duke Energy to Santee Cooper – 500 MW

slide-27
SLIDE 27

Significant Constraints Identified – DEC

27 Table 4: Significant Constraints - DEC

Duke Energy to Santee Cooper – 500 MW

Thermal Loadings (%)

Potential Enhancement Limiting Element Rating (MVA) Without Request With Request P1 Bush River Tie – Saluda Hydro 100kV T.L. 79 101.5 108 P2 Laurens Tie – Bush River Tie 100kV T.L. 65 93.9 100.2

slide-28
SLIDE 28

Potential Enhancements Identified – DEC

28

(1) Total planning level cost estimate does not include the cost of projects that are included in SERTP Sponsors’ expansion plans and are scheduled to be completed by June 1st of the study year. The studied transfer depends on these projects being in-service, and the cost to support the study transfer could be greater than the total shown above if any of these projects are delayed or cancelled.

Table 5: Potential Enhancements - DEC

Duke Energy to Santee Cooper – 500 MW

Item Potential Enhancement Planning Level Cost Estimate P1 Bush River Tie – Saluda Hydro 100kV double circuit T.L.

  • Rebuild the 2.7 miles of Bush River Tie – Saluda Hydro 100kV

double circuit transmission line with 954 ACSR conductors rated to 120˚C $4,900,000 P2 Laurens Tie – Bush River Tie 100kV double circuit T.L.

  • Rebuild approximately 2.8 miles of Laurens Tie – Bush River Tie

100kV double circuit transmission line with 954 ACSR conductors rated to 120˚C. $5,100,000

DEC TOTAL ($2019) $ 11,000,000(1)

slide-29
SLIDE 29

Potential Enhancement Locations – DEC

29

Duke Energy to Santee Cooper – 500 MW

P1 P2

slide-30
SLIDE 30

Significant Constraint (P1) – DEC

30

Duke Energy to Santee Cooper – 500 MW

slide-31
SLIDE 31

Potential Enhancement (P1) – DEC

31

Duke Energy to Santee Cooper – 500 MW

slide-32
SLIDE 32

Significant Constraint (P2) – DEC

32

Duke Energy to Santee Cooper – 500 MW

slide-33
SLIDE 33

Potential Enhancement (P2) – DEC

33

Duke Energy to Santee Cooper – 500 MW

slide-34
SLIDE 34

Transmission System Impacts – SERTP

34

Balancing Authority Planning Level Cost Estimate

Associated Electric Cooperative (AECI) $0 Duke Carolinas (DEC) $11,000,000 Duke Progress East (DEPE) $0 Duke Progress West (DEPW) $0 Louisville Gas & Electric and Kentucky Utilities (LG&E/KU) $0 PowerSouth (PS) $0 Southern (SBAA) $0 Tennessee Valley Authority (TVA) $0

SERTP TOTAL ($2019) $11,000,000

Table 6: Transmission System Impacts - SERTP

Duke Energy to Santee Cooper – 500 MW

slide-35
SLIDE 35

Southern BAA to Santee Cooper Border 800 MW

35

Economic Planning Studies – Preliminary Results

Economic Planning Studies

slide-36
SLIDE 36

Study Assumptions

  • Source: Generation within

Southern BAA

  • Sink: Uniform generation

scale within Santee Cooper

  • Transfer Type: Generation to

Generation

  • Year: 2020
  • Load Level: Summer Peak

36

Southern BAA to Santee Cooper – 800 MW

Source Sink

slide-37
SLIDE 37

37

SOURCE SINK FLOWS > 5%

%

Transfer Flow Diagram (% of Total Transfer)

Southern BAA to Santee Cooper – 800 MW

SBAA FRCC SCE&G TVA DEC DEPW DEPE SC MISO OVEC PJM EXTERNAL LG&E/KU AECI SPP PS

2.0 % 1.0 % 4.0 % 1.0 % 1.0 % 1.0 % 0.0 % 2.0 % 1.0 % 2.0 % 9.0 % 1.0 % 8.0 % 0.0 % 1.0 % 29.0 % 19.0 % 26.0 % 17.0 % 1.0 % 1.0 % 3.0 % 24.0 % 23.0 % 24.0 % 0.0 % 1.0 % 9.0 % 12.0 % 12.0 % 0.0 % 2.0 % 2.0 % 1.0 % 9.0 % 1.0 % 1.0 % 0.0 % 2.0 % 5.0 %

slide-38
SLIDE 38

Transmission System Impacts – SERTP

  • Transmission System Impacts Identified:

– Significant constraints were identified in the following SERTP Balancing Authority Areas:

  • DEC
  • SBAA
  • Potential Transmission Enhancements Identified:

– (DEC) Two (2) 100kV Transmission Line Upgrades – (SBAA) One (1) 115kV Transmission Line Rebuild

SERTP Total ($2019) = $22,000,000

38

Southern BAA to Santee Cooper – 800 MW

slide-39
SLIDE 39

Significant Constraints Identified – DEC

39 Table 7: Significant Constraints - DEC

Southern BAA to Santee Cooper – 800 MW

Thermal Loadings (%)

Potential Enhancement Limiting Element Rating (MVA) Without Request With Request P1 Bush River Tie – Saluda Hydro 100kV T.L. 79 101.5 110.8 P2 Laurens Tie – Bush River Tie 100kV T.L. 65 93.9 103.1

slide-40
SLIDE 40

Potential Enhancements Identified – DEC

40

(1) Total planning level cost estimate does not include the cost of projects that are included in SERTP Sponsors’ expansion plans and are scheduled to be completed by June 1st of the study year. The studied transfer depends on these projects being in-service, and the cost to support the study transfer could be greater than the total shown above if any of these projects are delayed or cancelled.

Table 8: Potential Enhancements - DEC

Southern BAA to Santee Cooper – 800 MW

Item Potential Enhancement Planning Level Cost Estimate P1 Bush River Tie – Saluda Hydro 100kV double circuit T.L.

  • Rebuild the 2.7 miles of Bush River Tie – Saluda Hydro 100kV

double circuit transmission line with 954 ACSR conductors rated to 120˚C $4,900,000 P2 Laurens Tie – Bush River Tie 100kV double circuit T.L.

  • Rebuild approximately 2.8 miles of Laurens Tie – Bush River Tie

100kV double circuit transmission line with 954 ACSR conductors rated to 120˚C. $5,100,000

DEC TOTAL ($2019) $ 11,000,000(1)

slide-41
SLIDE 41

Potential Enhancement Locations – DEC

41

Southern BAA to Santee Cooper – 800 MW

P1 P2

slide-42
SLIDE 42

Significant Constraint (P1) – DEC

42

Southern BAA to Santee Cooper – 800 MW

slide-43
SLIDE 43

Potential Enhancement (P1) – DEC

43

Southern BAA to Santee Cooper – 800 MW

slide-44
SLIDE 44

Significant Constraint (P2) – DEC

44

Southern BAA to Santee Cooper – 800 MW

slide-45
SLIDE 45

Potential Enhancement (P2) – DEC

45

Southern BAA to Santee Cooper – 800 MW

slide-46
SLIDE 46

Significant Constraints Identified – SBAA

46 Thermal Loadings (%)

Potential Enhancement Limiting Element Rating (MVA) Without Request With Request P1 Baxley – Pine Grove 115kV T.L. 114 99 104

Table 9: Significant Constraints - SBAA

Southern BAA to Santee Cooper – 500 MW

slide-47
SLIDE 47

Potential Enhancements Identified – SBAA

47

Item Potential Enhancement Planning Level Cost Estimate P1 Baxley – Hazelhurst 115kV Transmission Line Rebuild

  • Rebuild approximately 11.2 miles of Baxley – Hazelhurst 115kV

Transmission Line with 100˚C 795 ACSR $11,000,000

SBAA TOTAL ($2019) $ 11,000,000(1)

(1) Total planning level cost estimate does not include the cost of projects that are included in SERTP Sponsors’ expansion plans and are scheduled to be completed by June 1st of the study year. The studied transfer depends on these projects being in-service, and the cost to support the study transfer could be greater than the total shown above if any of these projects are delayed or cancelled.

Table 10: Potential Enhancements - SBAA

Southern BAA to Santee Cooper – 500 MW

slide-48
SLIDE 48

Potential Enhancement (P1) Location – SBAA

48

P1

Southern BAA to Santee Cooper – 800 MW

slide-49
SLIDE 49

Significant Constraint (P1) – SBAA

49

Baxley – Pine Grove 115 kV Transmission Line

Southern BAA to Santee Cooper – 800 MW

slide-50
SLIDE 50

Potential Enhancement (P1) – SBAA

50

Southern BAA to Santee Cooper – 800 MW

(P1) Baxley – Hazlehurst 115 kV Transmission Line

slide-51
SLIDE 51

Transmission System Impacts – SERTP

51

Balancing Authority Planning Level Cost Estimate

Associated Electric Cooperative (AECI) $0 Duke Carolinas (DEC) $11,000,000 Duke Progress East (DEPE) $0 Duke Progress West (DEPW) $0 Louisville Gas & Electric and Kentucky Utilities (LG&E/KU) $0 PowerSouth (PS) $0 Southern (SBAA) $11,000,000 Tennessee Valley Authority (TVA) $0

SERTP TOTAL ($2019) $22,000,000

Table 11: Transmission System Impacts - SERTP

Southern BAA to Santee Cooper – 800 MW

slide-52
SLIDE 52

Duke Energy Carolinas to Santee Cooper Border 500 MW

52

Economic Planning Studies – Preliminary Results

Economic Planning Studies

slide-53
SLIDE 53

Study Assumptions

53

Duke Energy to Santee Cooper – 500 MW

Source Sink

  • Source: Generation within Duke

Energy Carolinas

  • Sink: Uniform generation scale

within Santee Cooper

  • Transfer Type: Generation to

Generation

  • Year: 2024
  • Load Level: Winter Peak
slide-54
SLIDE 54

54

SOURCE SINK FLOWS > 5%

%

Transfer Flow Diagram (% of Total Transfer)

Duke Energy to Santee Cooper – 500 MW

4.0 %

SBAA FRCC SCE&G TVA DEC DEPW SC MISO OVEC PJM EXTERNAL LG&E/KU AECI SPP PS

1.0 % 0.0 % 1.0 % 1.0 % 2.0 % 0.0 % 0.0 % 0.0 % 0.0 % 0.0 % 0.0 % 1.0 % 0.0 % 0.0 % 15.0 % 7.0 % 12.0 % 9.0 % 1.0 % 0.0 % 1.0 % 15.0 % 24.0 % 28.0 % 33.0 % 2.0 % 1.0 % 34.0 % 1.0 % 1.0 % 1.0 % 0.0 % 0.0 % 0.0 % 0.0 % 1.0 %

DEPE

0.0 %

GULF

0.0 % 0.0 % 0.0 % 8.0 % 3.0 %

slide-55
SLIDE 55

Transmission System Impacts – SERTP

  • Transmission System Impacts Identified:

– Significant constraints were identified in the following SERTP Balancing Authority Areas:

  • DEPE
  • Potential Transmission Enhancements Identified:

– (DEPE) One (1) Substation Upgrade

SERTP Total ($2019) = $6,500,000

55

Duke Energy to Santee Cooper – 500 MW

slide-56
SLIDE 56

Significant Constraints Identified – DEPE

56 Thermal Loadings (%)

Potential Enhancement Limiting Element Rating (MVA) Without Request With Request P1 Wateree 115/100kV Transformers 150 93 103

Table 12: Significant Constraints - DEPE

Duke Energy to Santee Cooper – 500 MW

slide-57
SLIDE 57

Potential Enhancements Identified – DEPE

57

Item Potential Enhancement Planning Level Cost Estimate P1 Wateree 115/100kV Transformers

  • Replace existing 150 MVA 115/100kV transformer bank with

336 MVA 115/100kV transformer bank $6,500,000

DEPE TOTAL ($2019) $6,500,000 (1)

(1) Total planning level cost estimate does not include the cost of projects that are included in SERTP Sponsors’ expansion plans and are scheduled to be completed by winter of the study year. The studied transfer depends on these projects being in-service, and the cost to support the study transfer could be greater than the total shown above if any of these projects are delayed or cancelled.

Table 13: Potential Enhancements - DEPE

Duke Energy to Santee Cooper – 500 MW

slide-58
SLIDE 58

Potential Enhancement Locations – DEPE

58

Duke Energy to Santee Cooper – 500 MW

P1

slide-59
SLIDE 59

Significant Constraints (P1) – DEPE

59

Duke Energy to Santee Cooper – 500 MW

Overloads existing Wateree 150 MVA 115/100 kV transformers

slide-60
SLIDE 60

Potential Enhancement (P1) – DEPE

60

Duke Energy to Santee Cooper – 500 MW

Replace existing Wateree 150 MVA 115/100 kV transformers with 336 MVA 115/100 kV transformers

slide-61
SLIDE 61

Transmission System Impacts – SERTP

61

Balancing Authority Planning Level Cost Estimate

Associated Electric Cooperative (AECI) $0 Duke Carolinas (DEC) $0 Duke Progress East (DEPE) $6,500,000 Duke Progress West (DEPW) $0 Gulf Power (GULF) $0 Louisville Gas & Electric and Kentucky Utilities (LG&E/KU) $0 PowerSouth (PS) $0 Southern (SBAA) $0 Tennessee Valley Authority (TVA) $0

SERTP TOTAL ($2019) $6,500,000

Table 14: Transmission System Impacts - SERTP

Duke Energy to Santee Cooper – 500 MW

slide-62
SLIDE 62

Southern BAA to Santee Cooper Border 1000 MW

62

Economic Planning Studies – Preliminary Results

Economic Planning Studies

slide-63
SLIDE 63

Study Assumptions

  • Source: Generation within

Southern BAA

  • Sink: Uniform generation

scale within Santee Cooper

  • Transfer Type: Generation to

Generation

  • Year: 2024
  • Load Level: Winter Peak

63

Southern BAA to Santee Cooper – 1000 MW

Source Sink

slide-64
SLIDE 64

64

SOCO – Santee Cooper 1000 MW

SOURCE SINK FLOWS > 5%

%

Transfer Flow Diagram (% of Total Transfer)

Southern BAA to Santee Cooper – 1000 MW

SBAA FRCC SCE&G TVA DEC DEPW DEPE SC MISO OVEC PJM EXTERNAL LG&E/KU AECI SPP PS

2.0 % 0.0 % 3.0 % 2.0 % 1.0 % 1.0 % 0.0 % 1.0 % 1.0 % 2.0 % 8.0 % 1.0 % 7.0 % 1.0 % 1.0 % 31.0 % 19.0 % 26.0 % 16.0 % 1.0 % 1.0 % 3.0 % 23.0 % 23.0 % 23.0 % 1.0 % 1.0 % 8.0 % 11.0 % 11.0 % 0.0 % 2.0 % 2.0 % 1.0 % 8.0 % 0.0 % 1.0 % 1.0 % 2.0 %

GULF

1.0 % 0.0 % 1.0 % 5.0 %

slide-65
SLIDE 65

Transmission System Impacts – SERTP

  • Transmission System Impacts Identified:

– No significant constraints were identified in the SERTP Balancing Authority Areas

  • Potential Transmission Enhancements Identified:

– None Required

SERTP Total ($2019) = $0

65

Southern BAA to Santee Cooper – 1000 MW

slide-66
SLIDE 66

Miscellaneous Updates

SERTP

66

2019 SERTP

slide-67
SLIDE 67

Regional Planning Update

  • Version 2 SERTP Regional Models available on SERTP Website
  • Plan in place to facilitate the exchange of the latest transmission models

for the ten year planning horizon with FRCC

– FRCC models will be incorporated into subsequent regional power flow models

  • SERTP Sponsors beginning analyses on regional models including

assessment to identify and evaluate potential regional transmission projects

67

2017 Regional Transmission Analyses 2019 Regional Transmission Analyses

slide-68
SLIDE 68

Preliminary List of Alternative Regional Transmission Projects

68

Alternative Regional Transmission Projects Miles From To

BAA (State) BAA (State)

Paradise – Hardin Co 345kV

65 TVA (KY) LG&E/KU (KY)

Trinity – Miller 500kV

68 TVA (AL) SBAA (AL)

Clay – Wansley 500kV

90 SBAA (AL) SBAA (GA)

South Hall – Branch 500kV

78 SBAA (GA) SBAA (GA)

Farley – Sinai 500kV

50 SBAA (AL) Gulf (FL)

2019 Regional Transmission Analyses

slide-69
SLIDE 69

Preliminary List of Alternative Regional Transmission Projects

69

2019 Regional Transmission Analyses

Paradise – Hardin Co 345kV Trinity – Miller 500kV South Hall – Branch 500kV Clay – Wansley 500kV Farley – Sinai 500kV

slide-70
SLIDE 70

Planning Study Updates

  • Coordination study currently on-going to assess the impact of the

proposed tie line between FPL and Gulf Power with a 850MW transfer between FPL and Gulf Power

  • A coordination study group has started to prepare for Vogtle 3 and 4

coming online.

70

2017 Regional Transmission Analyses

2019 SERTP

slide-71
SLIDE 71

SERC Regional Model Development Update

71

  • SERC is one of the six regional

electric reliability councils under the North American Electric Reliability Corporation authority (NERC).

  • SERC oversees the implementation

and enforcement of Reliability Standards among the bulk power system (BPS) users, owners, and

  • perators.

2019 SERTP

slide-72
SLIDE 72

SERC Regional Model Development Update

  • SERC Regional Model Development

– SERC Long-Term Working Group (LTWG)

  • Analyze the performance of the members’ transmission systems and

identify limits to power transfers occurring non-simultaneously among the SERC members.

  • Evaluate the performance of bulk power supply facilities under both

normal and contingency conditions for future years. – Data Bank Update (DBU)

  • The DBU is held to conduct an annual update of power flow models for

the SERC Region to be used for operating and future year studies.

72

2019 SERTP

slide-73
SLIDE 73

SERC Regional Model Development Update

  • SERC Regional Model Development

– Multi-regional Modeling Work Group (MMWG)

  • The models created by the SERC LTWG are incorporated into the power

flow models of the interconnected regions and updated annually by MMWG

  • Responsible for developing a library of solved power flow models of the

Eastern Interconnection

  • MOD-32 Compliance (Data for Power System Modeling and Analysis)
  • The updated Regional MMWG Models serve as the starting point model

for the SERTP Regional Power Flow Models

73

2019 SERTP

slide-74
SLIDE 74

SERC Regional Model Development Update

  • SERC Regional Model Development

– LTWG Schedule of Events for 2019

  • Data Bank Update (DBU) was performed in June
  • Power flow cases were finalized in June
  • Future Study Year Case: 2024 Summer Peak Load

– Nonpublic Study and Report to be completed in October – Steering Committee Report review

  • Final Report Scheduled for completion on December 6th

– MMWG Schedule of Events for 2019

  • MMWG Model Update performed from August – September
  • Power flow cases finalized in October

74

2019 SERTP

slide-75
SLIDE 75

Next Meeting Activities

  • 2019 SERTP 4th Quarter Meeting – Annual Transmission Planning

Summit & Input Assumptions Meeting – Location: MEAG Headquarters in Atlanta, GA – Date: December 12th, 2019 – Purpose:

  • Final Economic Planning Study Results
  • Final Regional Transmission Plan
  • Regional Analyses Results
  • 2020 Assumptions Input Session

75

2019 SERTP

slide-76
SLIDE 76

Questions?

www.southeasternrtp.com

2019 SERTP

76