FEASIBILITY STUDY AND CONCEPTUAL DESIGN FOR SENIOR CENTER AND CITYWIDE RECREATION CENTER City Council Presentation 1/12/2016 A. Active Adult Center concept B. Revised Citywide Recreation Center concept C. Gather input D. Seek


slide-1
SLIDE 1

SENIOR CENTER AND

CONCEPTUAL DESIGN FOR FEASIBILITY STUDY AND

CITYWIDE RECREATION CENTER

slide-2
SLIDE 2

TODAY’S AGENDA

City Council Presentation – 1/12/2016 A. Active Adult Center concept B. Revised Citywide Recreation Center concept C. Gather input D. Seek direction on sales tax election E. Seek direction on design schedule

slide-3
SLIDE 3

ACTIVE ADULT CENTER

slide-4
SLIDE 4

ACTIVE ADULT CENTER SITE

slide-5
SLIDE 5

FLOOR PLAN ACTIVE ADULT CENTER

slide-6
SLIDE 6

ENTRY ACTIVE ADULT CENTER

slide-7
SLIDE 7

LOOKING NORTHEAST ACTIVE ADULT CENTER

slide-8
SLIDE 8

LOOKING NORTHWEST ACTIVE ADULT CENTER

slide-9
SLIDE 9

PATIO ACTIVE ADULT CENTER

slide-10
SLIDE 10

LOOKING SOUTHWEST ACTIVE ADULT CENTER

slide-11
SLIDE 11

LOOKING SOUTHWEST ACTIVE ADULT CENTER

slide-12
SLIDE 12

PRELIMINARY BUDGET

68,000 SF Active Adult Center

BUILDING COSTS $23,900,000 SITE COSTS $3,300,000 SOFT COSTS $10,600,000

Assumptions:

  • Escalated to Mid 2018
  • 20% Contingency

TOTAL PROJECT $37,700,000

NOTE:

Consultant’s estimate was from 2015 and anticipated a 2018 construction schedule.

slide-13
SLIDE 13

PRELIMINARY BUDGET

Active Adult Center Arlington The Summit Grand Prairie NRH Centre North Richland Hills Completion

2018 2010 2012

Square Footage

68,000 57,000 85,000

Actual Construction Cost

$19.6M $21.6M

Adjusted Construction Cost (mid-2018)

$23.9M $30.6M $31.9M

Cost per square foot

$351 $536 $376

NOTE: Consultant’s estimate was from 2015 and anticipated a 2018 construction schedule.

slide-14
SLIDE 14

CITYWIDE RECREATION CENTER

slide-15
SLIDE 15

OVERALL SITE PLAN VANDERGRIFF PARK

slide-16
SLIDE 16

OVERALL SITE PLAN VANDERGRIFF PARK

slide-17
SLIDE 17

AERIAL VIEW VANDERGRIFF PARK

slide-18
SLIDE 18

MAIN ENTRY VANDERGRIFF PARK

slide-19
SLIDE 19

VIEW LOOKING SOUTHWEST VANDERGRIFF PARK

slide-20
SLIDE 20

VIEW LOOKING SOUTHEAST VANDERGRIFF PARK

slide-21
SLIDE 21

VIEW LOOKING EAST VANDERGRIFF PARK

slide-22
SLIDE 22

EVENT ENTRY VANDERGRIFF PARK

slide-23
SLIDE 23

APPROACH VANDERGRIFF PARK

slide-24
SLIDE 24

PHASE 1 – FIRST FLOOR PLAN VANDERGRIFF PARK

slide-25
SLIDE 25

PHASE 1 + PHASE 2 – FIRST FLOOR PLAN VANDERGRIFF PARK

slide-26
SLIDE 26

PHASE 1 + PHASE 2 – SECOND FLOOR PLAN VANDERGRIFF PARK

slide-27
SLIDE 27

NEXT STEPS AND SCHEDULE

slide-28
SLIDE 28

NEXT STEPS & SCHEDULE

1. City Council Presentation – January 26

  • a. Present Proforma / Business Plan
  • b. Gather input

2. Final Report Delivered / Study Complete – February 29 3. Sales Tax Election Date Determination 4. Design Considerations/Implications for Active Adult Center

November 8th Election August 2 – First Reading May 7th Election January 26 – First Reading