Senate Bill 100 Information Filing Presentation December 18, 2008 - - PowerPoint PPT Presentation

senate bill 100 information filing presentation
SMART_READER_LITE
LIVE PREVIEW

Senate Bill 100 Information Filing Presentation December 18, 2008 - - PowerPoint PPT Presentation

Senate Bill 100 Information Filing Presentation December 18, 2008 Agenda Introduction and purpose Energy Resource Zones Transmission Planning Process Transmission Projects Next Steps 2 Purpose of Information Filing


slide-1
SLIDE 1

Senate Bill 100 Information Filing Presentation

December 18, 2008

slide-2
SLIDE 2

2

Agenda

Introduction and purpose Energy Resource Zones Transmission Planning Process Transmission Projects Next Steps

slide-3
SLIDE 3

3

Purpose of Information Filing

Provide Commission and stakeholders with an update of Public Service’s SB-100 activities Provide an interim plan for Commission input Provide additional transparency into the planning efforts under SB-100 Opportunity to focus next steps

slide-4
SLIDE 4

4

SB-100 Informational Filing

Section I: A description of the stakeholder process Public Service has conducted since the spring of 2008 related to its activities under SB 07-100 Section II: A description of the current identified Energy resource Zones(“ERZs” ) Section III: A description of Public Service’s overall transmission planning process Section IV: The transmission plans that Public Service has prepared pursuant to SB 07-100 Section V: Next steps

slide-5
SLIDE 5

5

  • I. Stakeholder process
slide-6
SLIDE 6

6

SB-100 Process

March 2007:Senate Bill 100 become law in CO. Oct 31, 2007: PSCo submits first filing to PUC which includes the establishment of Energy Resource Zones and submits a CPCN for Pawnee to Smoky Hill(SH)345 kV line. Feb 2008: Hearing on CPCN Pawnee-SH 345 kV line. Feb 2008: PSCo agrees to accelerate SB-100 2008 process. March 4, 2008: Kickoff Meeting for 2008 SB-100 process. April – July 2008: Transmission Study Group meets. Sept 26, 2008: Stakeholder meeting to discuss transmission plans to all 5 energy resource zones. Nov 5-6th, 2008: Rehearing on CPCN(Pawnee –SH 345). Nov 24, 2008: Informational filing with PUC on energy zones and transmission plans for each zone.

slide-7
SLIDE 7

7

  • II. Energy Resource Zones
slide-8
SLIDE 8

8

Determination of Energy Resource Zones

2007 Process Generator interconnection requests

  • Bids received in response to the 2005 All Source

RFP

  • More detailed wind modeling by county
  • Stakeholder suggestions
  • Note: SB07-91 Report was not made public until

early 2008

slide-9
SLIDE 9

9

Energy Resource Zones -- 2007

slide-10
SLIDE 10

10

Changes for 2008

South central CO and some of the GDAs were not represented in a Zone Created Zone 5

  • Western portions of Zone 3 and the eastern

portion of Zone 4

  • Boone, Walsenburg and Comanche

interconnection in Zone 5

  • Access to Wind GDA 8 and the Solar GDA South

and Southeast of Pueblo

Positive feedback from stakeholders

slide-11
SLIDE 11

11

Zo Zone 4 ne 4 Zo Zone 5 ne 5 Zo Zone 1 ne 1 Zo Zone 2 ne 2 Zo Zone 3 ne 3

2008 Energy Resource Zones with GDA’s

slide-12
SLIDE 12

12

Wind GDA’s (Generator Development Areas)

SB-091

slide-13
SLIDE 13

13

Solar GDA’s

SB-091

slide-14
SLIDE 14

14

1

Legend

X X Wind Interconnection on PSCo Transmission Solar Interconnection on PSCo Transmission 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 39 40 41 42 43 44 45 Updated November 7, 2008 - SJG 46 47 48 49 50 X Gas/Coal Interconnection on PSCo Transmission 51 52 53 54

slide-15
SLIDE 15

15

  • III. Transmission Planning
slide-16
SLIDE 16

16

Transmission Map

slide-17
SLIDE 17

17

Planning Objectives

Maintain reliable electric service. Improve the efficiency of electric system

  • perations, including the provision of open and

non-discriminatory access to its transmission facilities. Identify and promote new investments in transmission infrastructure in a coordinated, open, transparent, and participatory manner. Comply with FERC 890 principles.

slide-18
SLIDE 18

18

Coordinated Planning Process

Calendar FERC 890 coordinated planning SB-100 open stakeholder process Regional and sub regional coordination

slide-19
SLIDE 19

19

Planning Calendar

May Jun Jan Feb Mar Apr Aug Sep Jul Oct Nov

5 year capital budget studies CCPG Long Range Tariff Studies

Dec

SB100 Studies CCPG 3/25/08 CCPG 8/22/08 CCPG 12/16/08 890 3/11/08 890 12/2/08 Resource Plan 10 year transmission plan 20 year transmission vision

slide-20
SLIDE 20

20

FERC 890 Process

Compliance filing Oct 15, 2008 Open Stakeholders meetings twice a year Open, transparent and coordinated transmission planning process

slide-21
SLIDE 21

21

Colorado Coordinated Planning Group

Forum for joint transmission planning Recognized WECC Sub-Region Three Open Meetings/Year

April, August, December (Joint with SWAT/Sierra)

Denver TSGT Offices Multiple Subcommittee and Work Group meetings throughout the year Open to All Interested Stakeholders Meeting Notices/Materials Posted at:

www.westconnect.com

slide-22
SLIDE 22

22

  • IV. Transmission Plans for Each Energy

Zone

slide-23
SLIDE 23

23

Overview of Plans

Midway to Waterton 345 kV Pawnee to Smoky Hill 345 kV Short term solutions Plans for each ERZ

slide-24
SLIDE 24

24

Midway to Waterton 345 kV Project

CPCN issued in September 2007 Premise of CPCN was deliver 500 MW from the Squirrel creek project Squirrel creek Project Cancelled Midway to Waterton needed to delivery resources from energy zones 3, 4 and 5 to Denver load Center Proposal to have in service 2012.

slide-25
SLIDE 25

25

Pawnee to SH 345 kV CPCN

October 31, 2007: Filed CPCN for new 345 kV line Hearing on Feb 27-28, 2008 94 mile 345 kV line to access renewables from Zone 1 Cost estimated to be $120 million in 2008 $ Scheduled ISD year end 2013 Transfer approximately 500 MW of renewable resources to Denver load center Rehearing on Nov 5-6, 2008 Expect final ruling end of 2008

slide-26
SLIDE 26

26

Short term Solutions

Upgraded the Pawnee to Smoky Hill and the Pawnee to Daniel Park 230 kV lines to allow for maximum simultaneous operation of existing resources in the Pawnee region. Both 230 kV lines upgraded to 636 MVA in 2008 Both 230 kV lines will be further upgraded to 735 MVA by end of 2009.

slide-27
SLIDE 27

SB-100 Overall Transmission Plan

  • Zo

Zone 4 ne 4 Zo Zone 5 ne 5 Zo Zone 1 ne 1 Zo Zone 2 ne 2 Zo Zone 3 ne 3

Vilas Calumet Missile Site Ault Cherokee Pawnee Smoky Hill Daniels Park Comanche Lamar

345kV 230kV

27

slide-28
SLIDE 28

28

Proposed Senate Bill 100 Projects

Project Description Generation injection Cost Energy Zone Priority Pawnee – Daniels Park– 345 kV line Second circuit 345 kV line in Energy zone 1. 300-500 MW $65,000,000 1 Medium -1 Ault to Cherokee 230 kV New mile 230kV line in energy Zone 1. 300-600 MW $64,000,000 1 Medium -2 Missile Site 345/230 kV switching station on Pawnee to Daniel Park line in energy zone 2. 200-500 MW $13,500,000 2 High-2 Lamar to Comanche 345 kV line and Lamar New 345kV lines to access energy zone 3. 800-1000 MW $240,000,000 3 High -3 Lamar to Vilas 345 kV line New 345kV line in Energy Zone 3 to access wind rich area. $27,000,000 3 Low San Luis – Calumet – Comanche Line Double circuit 230 kV line( SLV to Calumet) and double 345 kv line( Calumet to Comanche). 600-1000 MW $150,000,000 4 and 5 High -1 Total

$559,500,000 generation values are non simultaneous

slide-29
SLIDE 29

29

  • V. Next Steps
slide-30
SLIDE 30

30

Policy Considerations

Seeking approval of transmission under SB 100 consistent with CPCN rules

Approving transmission in advance of new generation Streamline the CPCN approval process Providing guidance on prioritizing projects

Future Transmission Planning

10 year horizon vs longer

Joint Planning/Projects

High Plains Express

slide-31
SLIDE 31

31

Next Steps

Dec 18, 2008 CPUC workshop on SB-100 plans to allow stakeholder input and feedback on priority. Jan 12, 2009 CPUC workshop for stakeholder response Feedback from CPUC on priority of CPCN’s on transmission plans Future CPCN process for SB-100 projects

slide-32
SLIDE 32

32

Questions