Scott Hansen, P.E. 2019 Master/Expansion Plan Efforts 19005- - - PowerPoint PPT Presentation
Scott Hansen, P.E. 2019 Master/Expansion Plan Efforts 19005- - - PowerPoint PPT Presentation
Clark County Water Reclamation District Upcoming Projects January 16, 2020 Scott Hansen, P.E. 2019 Master/Expansion Plan Efforts 19005- Preliminary and Primary Treatment Major Project elements Modification of Inlet Box New Bar Screen
2019 Master/Expansion Plan Efforts
19005- Preliminary and Primary Treatment
Major Project elements
- Modification of Inlet
Box
- New Bar Screen Facility
- 4 Grit Basins
- New Blower facility
- Odor Control Biofilters
- 3 Primary Clarifiers
- Primary Sludge Pump
- Reliability Centered
Design
19007- Secondary Treatment
Major Project elements
- Tie-in at PEPS
- 3 aeration basins
- 3 secondary clarifiers
- Blower facility
- Electrical building
- Tie-in at secondary
effluent structure
- Reliability Centered
Design
CMAR Project Delivery Method
30% Design (Prepared) Evaluate Proposals Select Design Consultant
Negotiate GMP per NRS 338.1697 (Binding) General Manager Acceptance of GMP
Construction Cost Estimating, Value Engineering, Constructability Reviews
Exit Ramp
CMAR Input
Advertise for RFP per NRS 338.1692
BOT Approval of Panel Recommendation per NRS 338.1693 BOT Preconstruction Services Approval of Agreement YES NO
CMAR OPCC (Non-Binding) 90% Design Design to 60% 100% Design Reconcile OPCC
18003 Owner (with optional Owner Advisor) Owner, CMAR, Engineer Design Consultant CMAR
BOT Award of Construction Contract Bid per NRS 338.1385
This path requires repackaging and a bid process. It will add approximately 6-9 months. Prepare GMP
NRS 338.1692
NRS 338.1692
CMAR Evaluation and Selection
Short List Between 2 and 5 applicants will be invited for interviews CMAR Applicant will be required to submit more information (including fee), if selected for interview
CMAR Pre-construction Services Agreement CMAR Construction Services Agreement
Cost Estimates Primary - $126 to $144 million Secondary - $140 to $180 million
Primary Schedule Advertise – Jan. 2020 Tour – Feb. 2020 Due – Mar. 2020 Interviews – Apr. 2020 BOT – Jun. 2020 BOT – Jul. 2020
Secondary Schedule Advertise – Mar. 2020 Tour – Apr. 2020 Due – May 2020 Interviews – Jun. 2020 BOT – Aug. 2020 BOT – Sep. 2020
Design-Bid-Build Opportunities
17012- Sandhill Interceptor
- Feb. 2020
$37.6 – $43.9 M
Major Project Elements
- 60-inch pipe
- Tunneling
- Junction structures
- Large, Short Bypass
18001- Manhole & Pipe Rehabilitation
- Apr. 2020
$15 M
Major Project Elements
- 275 locations
- Pipe Replacements
- Cast-in-place pipe
lining
- MH Coatings &
Replacement
19010- Preloading
- Sep. 2020
$5.3 M
Major Project Elements
- Dirt Hauling &
Compacting
- Monitoring
- Site Restoration
19002- Demolition
- Nov. 2020
$45 M
Major Project Elements
- Utility Relocations
- Construction Access
Road
- Demolition
19003- Chemical Facility
- Dec. 2020
$12 M
Major Project Elements
- Building Str.
- 11 chemical tanks
- Containment
- Pumps
- Piping
- Demolition
19104- Moapa Valley Lift Station & Force Main
- Mar. 2021
$14 M
Major Project elements
- New 1 MGD Lift
Station
- 7,000 ft 8-inch FM (2)
- 7,000 FT 4-inch
Waterline
- Demolition
19008- FWRC Electrical System Rehab.
- Apr. 2021
$10 M
Major Project elements
- Several New
Electrical Feeders
- Breakers & Switches
- Fiber Conduit Runs
- Cart Charging
Stations
19011- FWRC DAFT 5
- Dec. 2021
$12 M
Major Project elements
- 64’ DIA, 12’ Depth
- Utility Connections
- Polymer Feed
- Reliability Center Design
19102 – Sludge Thickening
- Feb. 2022
$48 M
Major Project elements
- Sludge Screening
- 4 Clarifiers/Settling Basins
- Sludge Pump
- Odor Control Biofilter
- Reliability Centered Design
Upcoming Bid Opportunities
https://w /www.cleanwater ertea eam.com http://www.Dem emandStar.com
- m