SAN FRANCISCO INTERNATIONAL AIRPORT Presentation to the Capital - - PowerPoint PPT Presentation

san francisco international airport
SMART_READER_LITE
LIVE PREVIEW

SAN FRANCISCO INTERNATIONAL AIRPORT Presentation to the Capital - - PowerPoint PPT Presentation

SAN FRANCISCO INTERNATIONAL AIRPORT Presentation to the Capital Planning Committee December 12, 2016 Introduction Action Items: Approval authorizing the Airport Commission to: Issue up to $4.36 B in Revenue Bonds (& secure related


slide-1
SLIDE 1

SAN FRANCISCO INTERNATIONAL AIRPORT

December 12, 2016

Presentation to the Capital Planning Committee

slide-2
SLIDE 2

Introduction

2

Action Items: Approval authorizing the Airport Commission to:

  • Issue up to $4.36 B in Revenue Bonds (& secure related supplemental appropriation)
  • Increase the Commercial Paper program to $500 M from $400 M

Action Overview

  • Funds a significant portion of the 5-Yr Capital Improvement Program (CIP)
  • CIP was approved by CPC on July 11, 2016
  • Reviewed by the Airport’s Financial Advisory Committee (Sept 2016)
  • Approved by Commission (Nov 2016)
slide-3
SLIDE 3

3

Source: Actual- Airport Commission records; Forecast: LeighFisher report prepared for financial planning in FY2015 and FY2016. San Francisco Airport Commission; Federal Aviation Administration air traffic statistics. OAG Aviation Worldwide Ltd, OAG Analyser database

SFO Enplanements Forecast vs. Historical Comparison Passenger Traffic (millions)

27.8 25.4 29.8 30.9 33.7 35.1 36.1 37.6 39.7

9.3 7.9 8.5 9.1 9.3 9.6 10.1 10.6 11.7

5 10 15 20 25 30 35 40 45 50 55

2008 2009 2010 2011 2012 2013 2014 2015 2016 Fiscal Year

Domestic International

Robust growth driving immediate CIP needs

  • In FY2016, SFO had a record 51.4 million total passengers
  • Since 2007, traffic has increased by 56%
  • FY2016 enplanements were forecast in 2014 to be achieved in FY2021
  • Passenger traffic expected to continue to grow over the next 5 years

16 18 20 22 24 26 28 30 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 (Millions) Fiscal Year 2014 Forecast (2015-2021): 1.7% 2016 Forecast (2016-2022): 2.2% Actual (2006-2016): 4.5% 2013 Forecast (2014-2019): 1.8%

slide-4
SLIDE 4

Bond Authorization Summary

4

Funding Need Amount

CIP Project Need* $4,239 Financing Costs + CSA Auditor Allocation 1,020 Total Funding Need $5,260 Less existing authorization (excluding hotel)** (901) Authorization Requested Amount $4,359

($ in millions) * Need excludes: (1) the On-Airport Hotel; (2) CIP projects that have not yet received environmental review; and (3) CIP needs funded through the Sept 2016 bond issuance. ** Total existing authorization including the On-Airport Hotel project authorization is $1,144 M.

slide-5
SLIDE 5

Supplemental Appropriation Summary

5

Project Uses Amount Terminal Projects $2,871 Airport Support Projects 580 Groundside Projects 473 Utility Projects 218 Airfield Projects 97 Total CIP Project Uses (need)* $4,239 Less existing project appropriation (427) Total Project Appropriation $3,812 Other Uses Amount Financing Costs $1,013 CSA Auditor Allocation (0.2%) 7.6 Total Other Uses Appropriation $1,020 TOTAL Appropriation Amount $4,832

($ in millions) * Need excludes: (1) the On-Airport Hotel; (2) CIP projects that have not yet received environmental review; and (3) CIP needs funded through the Sept 2016 bond issuance.

slide-6
SLIDE 6

Commercial Paper Program

6

Seeking approval to increase Commercial Paper Program from $400 M to $500 M

  • Airport practices “just in time” financing
  • Commercial paper for interim funding of projects at a lower

borrowing cost

  • Issue long-term debt as needed, optimizing market timing
  • Increase could save $30+ M in present value debt service costs
  • ver next 5 yrs
slide-7
SLIDE 7

Financial Considerations

7

No impact to the City’s debt limit or property taxes

  • Bonds are supported solely by Airport revenues

No impact to the Annual Service Payment (ASP)

  • ASP payments are based on non-airline revenues

Cost per Enplanement (CPE) expected to remain competitive

  • Noted by Credit Rating Agencies in most recent rating reports (Sept 2016)

Sensitivity analysis using 10% drop in passenger traffic shows:

  • Rate covenant requirements would still be met
  • Debt service coverage would not be materially different given Airport’s

residual rate setting methodology

  • CPE increases, but is still expected to remain competitive
slide-8
SLIDE 8

8

APPENDIX

slide-9
SLIDE 9

Project Need

9

Authorization funds current CIP Need

  • Excludes CIP projects that do not have environmental review
  • Excludes On-Airport Hotel
  • Accounts for recent bond issuance

Need Amount

5-Year CIP Project Total $5,705 Less Projects w/o CEQA (808) Less Airport Hotel (222) Less Sept Bond Issuance (436) CIP Project Need $4,239

($ in millions)

slide-10
SLIDE 10

Authorization Need

10

Funding Need Amount

CIP Project Need* $4,239 Financing Costs + CSA Auditor Allocation 1,020 Funding Need $5,260

Available Authorization Amount

Existing Bond Authorization $1,144 Less Hotel Authorization (243) Remaining Bond Authorization $901

Authorization Request Amount

Authorization Request (Funding Need – Remaining Authorization) $4,359

($ in millions)

* Need excludes: (1) the On-Airport Hotel; (2) CIP projects that have not yet received environmental review; and (3) CIP needs funded through the Sept 2016 bond issuance.

slide-11
SLIDE 11

Appropriation & Authorization Overview

11

Existing Request Total

Bond Authorization $901* $4,359 $5,260 Supplemental Appropriation 427 $4,832 $5,260

*excludes existing Hotel Bond Authorization

Total need when factoring in project need & costs of issuance (COI) is $5,260

  • Project Need ($4,239) + COI ($1,020) = $5,260
slide-12
SLIDE 12

 Terminal 1 – replace 1960’s facilities to Terminal 2 standards

 24+ gates in 2020, with Boarding Area C refresh completed in

2023.

 Necessity for seismic upgrades, modernization and state of good

repair.

 Terminal 3 West – reconfiguration of the western side of T3

 Redesigned layout will improve passenger flow and meet SFO’s

standards of customer service

 Necessity for seismic upgrades

 New Long Term Parking Garage

Existing Long-Term Parking facility at or near capacity

Adds 3,000 spaces to inventory

12

Major Upcoming Capital Projects

Terminal 3 West Terminal 1 2nd Long Term Parking Garage

slide-13
SLIDE 13

Other Major Programs & Projects

13

Consolidated Admin Campus Airfield Improvements New Rental Car Facility Gate Enhancement Program Airtrain Extension Water & Wastewater Improvements Security Improvements International Terminal Improvements Technology Improvements

slide-14
SLIDE 14

Major CIP Projects

14

slide-15
SLIDE 15

5-Yr CIP Summary

15

Airport Cost Center Five-Year Plan %

Terminal 3,311.1 58.0% Groundside 1,052.0 18.4% Airport Support 750.7 13.2% Airfield 208.8 6.7% Utilities 382.7 3.7% Total $5,705.3 CIP Approvals & Reviews

  • Presented to the Airport’s Financial Advisory Committee (April 2016 )
  • Reviewed by the Airlines (April 2016)
  • Adopted by Airport Commission (June 2016)
  • Approved by CPC (July 2016)
  • Reviewed with Rating Agencies (Aug/Sept 2016)

($ in millions)