san francisco international airport
play

SAN FRANCISCO INTERNATIONAL AIRPORT Presentation to the Capital - PowerPoint PPT Presentation

SAN FRANCISCO INTERNATIONAL AIRPORT Presentation to the Capital Planning Committee December 12, 2016 Introduction Action Items: Approval authorizing the Airport Commission to: Issue up to $4.36 B in Revenue Bonds (& secure related


  1. SAN FRANCISCO INTERNATIONAL AIRPORT Presentation to the Capital Planning Committee December 12, 2016

  2. Introduction Action Items: Approval authorizing the Airport Commission to: Issue up to $4.36 B in Revenue Bonds (& secure related supplemental appropriation) • Increase the Commercial Paper program to $500 M from $400 M • Action Overview • Funds a significant portion of the 5-Yr Capital Improvement Program (CIP) • CIP was approved by CPC on July 11, 2016 • Reviewed by the Airport’s Financial Advisory Committee (Sept 2016) • Approved by Commission ( Nov 2016 ) 2

  3. Robust growth driving immediate CIP needs Passenger Traffic (millions) SFO Enplanements Forecast vs. Historical Comparison 55 Domestic International 30 50 2016 Forecast 11.7 (2016-2022): 2.2% 45 28 10.6 2014 Forecast 10.1 40 9.6 (2015-2021): 1.7% 9.3 26 9.1 35 8.5 9.3 Actual (2006-2016): 4.5% 30 24 7.9 (Millions) 2013 Forecast 25 (2014-2019): 1.8% 22 20 39.7 37.6 36.1 35.1 33.7 30.9 20 15 29.8 27.8 25.4 10 18 5 16 0 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2008 2009 2010 2011 2012 2013 2014 2015 2016 Fiscal Year Fiscal Year In FY2016, SFO had a record 51.4 million total passengers • Since 2007, traffic has increased by 56% • FY2016 enplanements were forecast in 2014 to be achieved in FY2021 • Passenger traffic expected to continue to grow over the next 5 years • 3 Source: Actual- Airport Commission records; Forecast: LeighFisher report prepared for financial planning in FY2015 and FY2016. San Francisco Airport Commission; Federal Aviation Administration air traffic statistics. OAG Aviation Worldwide Ltd, OAG Analyser database

  4. Bond Authorization Summary Funding Need Amount CIP Project Need * $4,239 Financing Costs + CSA Auditor Allocation 1,020 Total Funding Need $5,260 Less existing authorization (excluding hotel) ** (901) Authorization Requested Amount $4,359 ($ in millions) * Need excludes: (1) the On-Airport Hotel; (2) CIP projects that have not yet received environmental review; and (3) CIP needs funded through the Sept 2016 bond issuance. ** Total existing authorization including the On-Airport Hotel project authorization is $1,144 M. 4

  5. Supplemental Appropriation Summary Project Uses Amount Terminal Projects $2,871 Airport Support Projects 580 Groundside Projects 473 Utility Projects 218 Airfield Projects 97 Total CIP Project Uses (need)* $4,239 Less existing project appropriation (427) Total Project Appropriation $3,812 Other Uses Amount Financing Costs $1,013 CSA Auditor Allocation (0.2%) 7.6 Total Other Uses Appropriation $1,020 TOTAL Appropriation Amount $4,832 ($ in millions) 5 * Need excludes: (1) the On-Airport Hotel; (2) CIP projects that have not yet received environmental review; and (3) CIP needs funded through the Sept 2016 bond issuance.

  6. Commercial Paper Program Seeking approval to increase Commercial Paper Program from $400 M to $500 M Airport practices “just in time” financing • Commercial paper for interim funding of projects at a lower • borrowing cost Issue long-term debt as needed, optimizing market timing • Increase could save $30+ M in present value debt service costs • over next 5 yrs 6

  7. Financial Considerations No impact to the City’s debt limit or property taxes Bonds are supported solely by Airport revenues • No impact to the Annual Service Payment (ASP) ASP payments are based on non-airline revenues • Cost per Enplanement (CPE) expected to remain competitive Noted by Credit Rating Agencies in most recent rating reports (Sept 2016) • Sensitivity analysis using 10% drop in passenger traffic shows: Rate covenant requirements would still be met • Debt service coverage would not be materially different given Airport’s • residual rate setting methodology CPE increases, but is still expected to remain competitive • 7

  8. APPENDIX 8

  9. Project Need Authorization funds current CIP Need Excludes CIP projects that do not have environmental review • Excludes On-Airport Hotel • Accounts for recent bond issuance • Need Amount 5-Year CIP Project Total $5,705 Less Projects w/o CEQA (808) Less Airport Hotel (222) Less Sept Bond Issuance (436) CIP Project Need $4,239 ($ in millions) 9

  10. Authorization Need Funding Need Amount CIP Project Need* $4,239 Financing Costs + CSA Auditor Allocation 1,020 Funding Need $5,260 Available Authorization Amount Existing Bond Authorization $1,144 Less Hotel Authorization (243) Remaining Bond Authorization $901 Authorization Request Amount Authorization Request (Funding Need – Remaining Authorization) $4,359 ($ in millions) * Need excludes: (1) the On-Airport Hotel; (2) CIP projects that have not yet received environmental review; and (3) CIP needs funded through the Sept 2016 bond issuance. 10

  11. Appropriation & Authorization Overview Existing Request Total Bond Authorization $901 * $4,359 $5,260 Supplemental Appropriation 427 $4,832 $5,260 *excludes existing Hotel Bond Authorization Total need when factoring in project need & costs of issuance (COI) is $5,260 Project Need ($4,239) + COI ($1,020) = $5,260 • 11

  12. Major Upcoming Capital Projects Terminal 1  Terminal 1 – replace 1960’s facilities to Terminal 2 standards  24+ gates in 2020, with Boarding Area C refresh completed in 2023.  Necessity for seismic upgrades, modernization and state of good repair. Terminal 3 West  Terminal 3 West – reconfiguration of the western side of T3  Redesigned layout will improve passenger flow and meet SFO’s standards of customer service  Necessity for seismic upgrades 2 nd Long Term Parking Garage  New Long Term Parking Garage Existing Long-Term Parking facility at or near capacity  Adds 3,000 spaces to inventory  12

  13. Other Major Programs & Projects Gate Enhancement Program New Rental Car Facility Consolidated Admin Campus Airtrain Extension Water & Wastewater Improvements Airfield Improvements International Terminal Improvements Security Improvements Technology Improvements 13

  14. Major CIP Projects 14

  15. 5-Yr CIP Summary Airport Cost Center Five-Year Plan % Terminal 3,311.1 58.0% Groundside 1,052.0 18.4% Airport Support 750.7 13.2% Airfield 208.8 6.7% Utilities 382.7 3.7% Total $5,705.3 ($ in millions) CIP Approvals & Reviews Presented to the Airport’s Financial Advisory Committee (April 2016 ) • Reviewed by the Airlines (April 2016) • Adopted by Airport Commission (June 2016) • Approved by CPC (July 2016) • Reviewed with Rating Agencies ( Aug/Sept 2016 ) 15 •

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend