San Bruno Grade Separation Project Community Meeting Belle Air - - PowerPoint PPT Presentation

san bruno grade separation project
SMART_READER_LITE
LIVE PREVIEW

San Bruno Grade Separation Project Community Meeting Belle Air - - PowerPoint PPT Presentation

San Bruno Grade Separation Project Community Meeting Belle Air School 450 3 rd Avenue September 30, 2010 6:30 p.m. Overview Project Goals Enhance safety for motorists & pedestrians Eliminate a traffic bottleneck Improve access


slide-1
SLIDE 1

San Bruno Grade Separation Project

Community Meeting Belle Air School 450 3rd Avenue September 30, 2010 6:30 p.m.

slide-2
SLIDE 2

Overview

slide-3
SLIDE 3

Project Goals

  • Enhance safety for motorists & pedestrians
  • Eliminate a traffic bottleneck
  • Improve access to Belle Air School & Lions Field

Park

  • Reduce automobile congestion and emissions
  • Support San Bruno downtown revitalization

efforts

slide-4
SLIDE 4

Auto & Pedestrian Safety

* One pedestrian-only underpass at each of the above locations

  • Sylvan Avenue
  • At New Station Location
  • Euclid Avenue

Pedestrian-only Underpasses*

  • Angus Avenue
  • San Mateo Avenue
  • San Bruno Avenue

Vehicular Crossings

slide-5
SLIDE 5

Project Schedule

December 2011 – Summer 2012 Grade Separation Construction December 2010 June 2011 Street Closures October 2010 – Summer 2011 Shoofly Construction Awarded July 2010 Grade Separation Construction Contract March – June 2010 Construction Contract Procurement Period Completed September 2010 Box Culvert Construction & Underground Utility Work

slide-6
SLIDE 6

Project Schedule Detail*

4 months Late October 2010 Temporary Station Construction 2 separate weekend closures December 2010 Reconstruct Scott Street San Bruno Ave. – 1 day San Mateo Ave. – 1 weekend Angus Ave. – 1 week June 2011 Staged Street Closures 2 months June 2012 Posy Park Construction December 2012 August 2012 December 2011 July 2011 December 2010 Mid-October 2010

Start

2 months 4 months 8 months 6 months 6 months 2 months

Duration Activity

Project Closeout Road Improvements & Parking Lot Construction Grade Separation & Station Construction Excavation & Foundation Work Shoofly Construction Site Clearance, Shoring, Trenching & Signal Work

*Project schedule assumes a Caltrain two-track structure only. The schedule may shift due to site conditions and operational constraints.

slide-7
SLIDE 7

Construction Impacts

  • Street closures
  • Temporary removal of parking on the West side of

1st Avenue and other locations

  • 1st Avenue will become a cul-de-sac at Melody

Toyota

  • Pedestrian detours
  • Noise from pile driving and foundation work
  • Night work for track shifts, reconstruction of Scott

Street, and street paving

slide-8
SLIDE 8

Construction Phasing

slide-9
SLIDE 9
slide-10
SLIDE 10
slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13

Station Pedestrian Undercrossing

slide-14
SLIDE 14
slide-15
SLIDE 15

Posy Park

slide-16
SLIDE 16
slide-17
SLIDE 17
slide-18
SLIDE 18
slide-19
SLIDE 19
slide-20
SLIDE 20

Project Renderings

slide-21
SLIDE 21

Posy Park

slide-22
SLIDE 22

San Mateo Avenue and Posy Park Looking North

slide-23
SLIDE 23

First Avenue Looking North

slide-24
SLIDE 24

San Mateo Avenue Looking South

slide-25
SLIDE 25

Southbound Platform Looking North

slide-26
SLIDE 26

Northbound Platform Looking South

slide-27
SLIDE 27

Northbound Platform Looking South – 4 Track Option

slide-28
SLIDE 28

Key Features

  • Colored, textured paving at Posy

Park

  • Variable surface finishes for the

grade separation structure

  • Decorative street furniture and

waste/recycling receptacles

  • Enhanced lighting under bridges

and underpasses

  • Water Feature at Posy Park
  • Straightening of Angus Avenue
  • Drought resistant plantings
  • Station elevators
slide-29
SLIDE 29

Contact

Caltrain Office of Public Affairs Attn: Todd McIntyre Address: 1250 San Carlos Avenue PO Box 3006 San Carlos, CA 94040-1306 Phone: 650.622.7845 Email: sbgradesep@caltrain.com

Project information can be found on the Caltrain website at: http://www.caltrain.com/projectsplans/Projects/Caltrain_Capital_Program Click on the “San Bruno Grade Separation” link

slide-30
SLIDE 30

Questions?