San Bruno Grade Separation Project
Community Meeting Belle Air School 450 3rd Avenue September 30, 2010 6:30 p.m.
San Bruno Grade Separation Project Community Meeting Belle Air - - PowerPoint PPT Presentation
San Bruno Grade Separation Project Community Meeting Belle Air School 450 3 rd Avenue September 30, 2010 6:30 p.m. Overview Project Goals Enhance safety for motorists & pedestrians Eliminate a traffic bottleneck Improve access
Community Meeting Belle Air School 450 3rd Avenue September 30, 2010 6:30 p.m.
* One pedestrian-only underpass at each of the above locations
Pedestrian-only Underpasses*
Vehicular Crossings
December 2011 – Summer 2012 Grade Separation Construction December 2010 June 2011 Street Closures October 2010 – Summer 2011 Shoofly Construction Awarded July 2010 Grade Separation Construction Contract March – June 2010 Construction Contract Procurement Period Completed September 2010 Box Culvert Construction & Underground Utility Work
4 months Late October 2010 Temporary Station Construction 2 separate weekend closures December 2010 Reconstruct Scott Street San Bruno Ave. – 1 day San Mateo Ave. – 1 weekend Angus Ave. – 1 week June 2011 Staged Street Closures 2 months June 2012 Posy Park Construction December 2012 August 2012 December 2011 July 2011 December 2010 Mid-October 2010
Start
2 months 4 months 8 months 6 months 6 months 2 months
Duration Activity
Project Closeout Road Improvements & Parking Lot Construction Grade Separation & Station Construction Excavation & Foundation Work Shoofly Construction Site Clearance, Shoring, Trenching & Signal Work
*Project schedule assumes a Caltrain two-track structure only. The schedule may shift due to site conditions and operational constraints.
Station Pedestrian Undercrossing
Posy Park
Posy Park
San Mateo Avenue and Posy Park Looking North
First Avenue Looking North
San Mateo Avenue Looking South
Southbound Platform Looking North
Northbound Platform Looking South
Northbound Platform Looking South – 4 Track Option
Park
grade separation structure
waste/recycling receptacles
and underpasses
Caltrain Office of Public Affairs Attn: Todd McIntyre Address: 1250 San Carlos Avenue PO Box 3006 San Carlos, CA 94040-1306 Phone: 650.622.7845 Email: sbgradesep@caltrain.com
Project information can be found on the Caltrain website at: http://www.caltrain.com/projectsplans/Projects/Caltrain_Capital_Program Click on the “San Bruno Grade Separation” link