SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN IMPLEMENTATION - - PowerPoint PPT Presentation

SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN IMPLEMENTATION Public Workshop June July, 2017 http://resources.ca.gov/salton-sea/ 1 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year plan? Our Partners


slide-1
SLIDE 1

1

Public Workshop

June – July, 2017

SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN IMPLEMENTATION

http://resources.ca.gov/salton-sea/

slide-2
SLIDE 2

2

OVERVIEW

 State Obligations under the SSMP  What is the Phase I ten-year plan?  Our Partners  Our Projects  Implementation Plan  Air Quality  Future plans: area of focus, schedule, and funding

slide-3
SLIDE 3

3

 Legislative  Contractual  Section 2940 Fish and Game Code  Salton Sea Task Force  CNRA and DOI Memorandum of Understanding (MOU)

STATE OBLIGATIONS UNDER SSMP

slide-4
SLIDE 4

4

 Phase I of SSMP  Meet Task Force goals by 2028  Concentrate design and construction for habitat

and dust mitigation

 Implement longer term solution at the Sea  Enhance coordination among stakeholders

SSMP PHASE I TEN YEAR PLAN

slide-5
SLIDE 5

5

slide-6
SLIDE 6

6

 Current projects

 New River East – (SCH)  Red Hill Bay  Torres Martinez/SSA Wetland

 Proposed 2018 and 2019

 New River West  Whitewater River

NEAR-TERM DESIGN & CONSTRUCTION

slide-7
SLIDE 7

7

New River East New River West

slide-8
SLIDE 8

8

SPECIES CONSERVATION HABITAT (SCH) PHASE 1

slide-9
SLIDE 9

9

Geothemal access Buried water pipeline Berms (of various size) Water surface elevation Water movement Island

0 0.25 0.50 0.75 1.0 km

N Salt water intake forced main Fresh water intake and settling basins

Red Hill Bay Habitat Improvement Project

Conceptual Design

Salton Sea Alamo River Vail 3A drain Fresh water inlet Vail 3 drain Fresh water inlet

  • 228
  • 230.5

2250 ft

  • 230.5

Submersible pump with forced main line delivering Salton Sea water to the mixing basin

Fresh/Salt water mixing basin

Hazard drain Fresh water inlet

  • 243

(sea floor)

  • 233

(WSE 2016)

  • 230

playa 775 ft

slide-10
SLIDE 10

10

TORRES MARTINEZ WETLAND PROJECT

slide-11
SLIDE 11

11

 Introduction and background  Criteria for water backbone delivery infrastructure  Criteria for habitat and later phases  Adaptive design, monitoring and contingencies  Public input and transparency  Projected cost and funding  Implementation

PHASE I: 10-YEAR PLAN OVERVIEW (WORK PLAN)

slide-12
SLIDE 12

12

ACREAGE GOALS

Waterless dust control (as needed) Wet Habitat

10,000 20,000 30,000 40,000 50,000 2018 2020 2022 2024 2026 2028 Area (acres) Cumulative Exposed Area Cumulative Proposed Construction

slide-13
SLIDE 13

13

AIR QUALITY

 Obligations:

 Task Force  Contractual obligation under the QSA

 Dust mitigation projects in coordination with partners

 Waterless and water dependent measures  Planning and Implementation

 East and West shores of the Salton Sea in 2018

slide-14
SLIDE 14

14

AIR QUALITY – CURRENT EFFORTS

 Methods

 Surface roughening  Vegetation Enhancement  Surface Stabilizer

slide-15
SLIDE 15

15

AIR QUALITY

 Resources

 http://www.iid.com/water/library/qsa-water-

transfer/mitigation-implementation/air-quality-mitigation

 http://www.water.ca.gov/saltonsea/  http://www.co.imperial.ca.us/AirPollution/  https://www.arb.ca.gov/desig/adm/basincnty.htm

slide-16
SLIDE 16

16

 10-Year plan focuses on key components and

locations

 New River East & West  Whitewater River  Alamo River North & South

 Priorities because of proximity to water

sources & completed environmental clearance

 Water delivery infrastructure

FOCUS AREAS

slide-17
SLIDE 17

17

PRIORITIES

2018 – 2023 2023 – 2028

slide-18
SLIDE 18

18

PRIORITIES

slide-19
SLIDE 19

19

CONSTRUCTION SCHEDULE

slide-20
SLIDE 20

20

1.

Continue developing water management design criteria

2.

Evaluate habitat locations & types

3.

Refine conceptual design options for playa land uses

4.

Refine assessment tools for SSMP playa treatments

5.

Evaluate SSMP environmental compliance needs

6.

Compare & evaluate habitat designs to existing draft Habitat Conservation Plans (HCPs)

7.

Plan & implement air quality projects

8.

Plan & implement harbor & ancillary facilities

10-YEAR PLAN IMPLEMENTATION STRATEGY

slide-21
SLIDE 21

21

 Draft Plan

Late Summer

 Next Workshop

Early Fall

 Comment Period

Fall

 Final Implementation Plan

End of 2017

IMPLEMENTATION PLAN TIMELINE

slide-22
SLIDE 22

22

 Water Bond (Proposition 1)  Wildlife Conservation Board (Proposition 50)  U.S. Department of Agriculture

AVAILABLE FUNDING

slide-23
SLIDE 23

23

 Water Transfer Joint Powers Authority  DOI/CNRA MOU  EPA  Philanthropic Organizations  Water Resource Development Act Funding  USDA Partnerships & Funding  Additional State & Local Funding

POTENTIAL FUNDING SOURCES

slide-24
SLIDE 24

24

http://resources.ca.gov/salton-sea