Emissions Reduction Fund Safeguard Mechanism
Consultation Paper March 2015
Safeguard Mechanism Consultation Paper March 2015 The ERF has - - PowerPoint PPT Presentation
Emissions Reduction Fund Safeguard Mechanism Consultation Paper March 2015 The ERF has three key elements: Crediting Purchasing Safeguard 2 Consultation Submissions are invited on the safeguard consultation paper prior to midday, 27 April
Consultation Paper March 2015
Crediting Purchasing Safeguard
2
Emissions Reduction Fund Green Paper Dec 2013 Emissions Reduction Fund White Paper Apr 2014 Nov 2014 March 2015 Oct 2015 July 2015 Emissions Reduction Fund legislation enacted Safeguard mechanism consultation paper Safeguard mechanism draft legislative rules Safeguard mechanism final legislative rules Safeguard mechanism commences July 2016
Submissions are invited on the safeguard consultation paper prior to midday, 27 April 2015. For further information, please email: Emissions-Reduction- Submissions@environment.gov.au
3
4
ERF White Paper CFI Amendment Act
Coverage
emissions of more than 100 kt CO2-e per year
the person with operational control of the facility.
excluded from coverage.
Baselines for existing facilities
set at highest emissions over the period 2009/10 to 2013/14.
Baselines for new investments
to achieve and maintain best practice.
Emissions management and compliance
emissions.
ERF projects to avoid double counting abatement.
penalty and/or injunction.
5
Source: Departmental estimate based on emissions in 2013-14 from likely covered facilities.
Metal manufacturing 10.4% Coal mining 9.7% Other Manufacturing 8.0% Oil and gas 7.5% Transport 3.7% Metal ore mining 3.2% Waste 0.6%
Electricity emissions 57% Other safeguard emissions 43% Around 140 businesses (or 330 facilities) are expected to be covered by the mechanism in 2016/17.
6
7
YES Breach threshold after 1 July 2020 Breach threshold before 1 July 2020 Best Practice Benchmark 5 years of NGER data between 2009-10 and 2013-14 OR 3 years over 100,000 tCO2-e during this time Historical Baseline Highest emissions between 2009-10 and 2013-14. Independent Assessment Approach OR Facility elects to use historical data between 2009-10 and 2013-14, where available. NO
8
Facility meets criteria as a new entrant or significant expansion Facility estimates highest production level and associated EI for the first three years over 100kt/after expansion Facility submits application along with a limited assurance engagement conclusion from a registered NGER auditor CER makes baseline determination according to the application Baseline is revised after the three year period based on actual production high point
9
Year 1 Year 2 Year 3 Year 4 Year 5
Initial Baseline (emissions) Revised Baseline (emissions)
Estimated Production x Estimated Emissions Intensity Actual Production x Estimated Emissions Intensity
Baseline reflects application submitted by the facility, including a limited assurance engagement report from a registered NGER Auditor.
10 Estimated Estimated
Estimated
Actual Actual Actual Actual Actual
Estimated production Actual production
Year 1 Year 2 Year 3 Year 4 Year 5
Initial Baseline (emissions) Revised Baseline (emissions)
Estimated Production x Best Practice Benchmark Emissions Intensity Actual Production x Best Practice Benchmark Emissions Intensity
Baseline established using best practice benchmark, based on average emissions-intensity of top 10 per cent of industry peers. 11
Estimated production Actual production
Estimated
Estimated Estimated Actual Actual Actual Actual Actual
Baselines could be changed in some circumstances, such as:
12
13
Apply for a multi-year monitoring period Apply for an exemption, for example due to natural disaster Apply for significant expansion Baseline
Baseline setting period: Baseline reflects highest emissions between 2009/10 and 2013/14.
Emissions above baseline
Safeguard mechanism
Baseline 3 year average Expansion Baseline Revised baseline
Surrender eligible offsets
Baseline Offsets
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
Baseline 3 year average
This would allow averaging of emissions over time, helping to accommodate natural variability in emissions. Applications could be assessed by the Clean Energy Regulator, having regard to:
previously met all of its safeguard requirements; and
provided satisfactory evidence that the emissions could be returned to baseline levels over the extended period.
15
Significant expansions could be defined as an increase in production capacity
equipment.
Capacity Capacity Capacity Capacity Capacity
Year 1 Year 2 Year 3 Year 4 Year 5
More than 20% increase in capacity Baseline revised based on new investment policy
Revised Baseline Baseline
16
Year 1 Year 2 Year 3 Offsets Year 3 - Net Emissions
Credits issued under the Emissions Reduction Fund— also known as Australian Carbon Credit Units or ACCUs—will be eligible
surrendered at any time. (Section 22XM of the Act)
17
increases linked to an exceptional event if reasonable steps were taken to mitigate the risk of the increase. Exceptional events are:
such as:
...are not proposed as eligible for exemption.
18
Emissions (if no project) Emissions number (after project) Emissions reductions (actual) ACCUs surrendered
19
Emissions (if no project) Applicable emissions number (after surrendering ACCUs from project) Net emissions Emissions reductions (actual) ACCUs surrendered ACCUs added to baseline
ACCUs issued are added to the emissions number in the relevant financial year . The emissions number is then reduced when the ACCUs are surrendered or sold to the Government under an ERF contract.
20
Apply for an extended monitoring period, significant expansion or exemption Surrender offsets Infringement notice Injunction Civil penalty
Options available to the facility before an excess emissions situation exists Enforcement options available to the Clean Energy Regulator if a facility is in an excess emissions situation
21
A facility could apply in 2016-17 for a baseline using the independent assessment approach if:
the facility;
the change in natural resource grade or depth is the primary reason for this.
22
23
To ensure that information about the effectiveness of the safeguard mechanism is available to the public, the Clean Energy Regulator could publish information relating to:
baseline;
exceptional circumstances.
24
A review could be conducted in 2017-18 and cover the following elements:
and crediting elements of the ERF;
investments already underway;
for new investments;
reference to the Renewable Energy Target; and
25
26
individual baselines for the electricity sector.
electricity grid.
baselines could apply from following financial year.
Thereafter, the sectoral baseline would not be re-established.
broadly consistent with general safeguard approach.
27
Generator emissions tCO2-e
Sectoral baseline Individual baseline Offset emissions Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7
Individual baselines apply from following financial year and continue thereafter
Total sector emissions Individual generator emissions
28