Right-of-Way Industry Forum SR 400 Express Lanes PI 0001757 - - PowerPoint PPT Presentation

right of way industry forum
SMART_READER_LITE
LIVE PREVIEW

Right-of-Way Industry Forum SR 400 Express Lanes PI 0001757 - - PowerPoint PPT Presentation

Right-of-Way Industry Forum SR 400 Express Lanes PI 0001757 Fulton/Forsyth Joe Carpenter, PE P3 Director Tim Matthews, PE MMIP Program Manager January 8, 2019 1 Disclaimer Statement At this meeting the Department will provide


slide-1
SLIDE 1 1

Right-of-Way Industry Forum

SR 400 Express Lanes PI 0001757 Fulton/Forsyth

Joe Carpenter, PE – P3 Director Tim Matthews, PE – MMIP Program Manager January 8, 2019

slide-2
SLIDE 2 2

Disclaimer Statement

At this meeting the Department will provide information about the project’s delivery goals, anticipated scope, anticipated Design-Build procurement process, and potential risks. Participants will be encouraged to ask questions during this meeting; however, any information provided by the Department shall be considered as informational only and is subject to change.

slide-3
SLIDE 3 3

We Will Cover

  • Major Mobility Investment Program
  • SR 400 Express Lanes
  • Disadvantaged Business Enterprise (DBE) Program
  • Right-of-Way (ROW) Services for the Office of Innovative Delivery

(OID)

  • Open Discussion
slide-4
SLIDE 4 4

Major Mobility Investment Program

slide-5
SLIDE 5 5

11 MMIP Projects

3 Major Interchange Projects 4 Major Express Lanes Projects 3 Major Interstate Widening Projects 1 Commercial Vehicle Lanes Project

slide-6
SLIDE 6 6

MMIP Project Locations

slide-7
SLIDE 7 7

MMIP Schedule

slide-8
SLIDE 8 8

Consultant Opportunities

slide-9
SLIDE 9 9

Disadvantaged Business Enterprises

slide-10
SLIDE 10 10

Program Delivery Model- PMC & GECs

slide-11
SLIDE 11 11

DBE Goal and Mentoring Program

  • 15% DBE Goal for GECs
  • GEC Mentoring Program
  • RFQ may require Mentoring Program implementation plan
slide-12
SLIDE 12 12

SR 400 Express Lanes

slide-13
SLIDE 13 13

SR 400 Express Lanes Overview

  • Anticipate Design-Build-Finance-Operate-Maintain (DBFOM) delivery method –

Availability Payment Approach

  • Two express lanes in each direction along SR 400 between I-285 and McGinnis

Ferry Road

  • One express lane in each direction from McGinnis Ferry Road to McFarland

Parkway

  • Will directly connect to I-285 Top End Express Lanes
  • Intermediate access points to be determined
  • Estimated Cost: $1.8 Billion
  • Est. Construction Letting: Q4 2020
slide-14
SLIDE 14 15

SR 400 Express Lanes

  • I-285 to McGinnis Ferry Road
  • Two express lanes in each direction (illustrative example)

Express lanes Bi-directional (Buffer Separated) Express Lanes

slide-15
SLIDE 15 16

SR 400 Express Lanes

  • McGinnis Ferry Road to McFarland Parkway
  • One express lane in each direction (illustrative example)

Express lanes Bi-directional (Buffer Separated) Express Lanes

slide-16
SLIDE 16 17

SR 400 Express Lanes Project Status

Scoping Phase

  • Traffic analysis
  • Access testing
  • Coordination with Stakeholders, SRTA, and MARTA
  • Environmental field work

GEC Pre-Let Status

  • Concept Approval Q1 2019
  • PIOH Q1 2019
  • Advance ROW Acquisitions
  • DBFOM Development and Technical Provisions
  • Issue NOIA/PNA Q2 2019
  • Issue RFQ Q3 2019
  • Issue Preliminary RFP Q1 2020
  • Costing Plans Set Complete & Draft RFP Q2 2020
  • Final NEPA Approval Q3 2020
  • Issue Final RFP Q3 2020
  • Letting/Proposer Selection Q4 2020
slide-17
SLIDE 17 18

SR 400 Express Lanes Schedule

Pr Project ect Ph Phases es 2017 2017 2018 2018 2019 2019 202 202 202 202 1 202 202 2 202 202 3 202 202 4 Environmental Design-Build Procurement Right-of-Way Final Design Construction

Schedule subject to change Early ROW acquisition
slide-18
SLIDE 18 19

SR 400 Express Lanes Next Steps

  • Environmental phase
  • Concept approval
  • Future conditions operational analysis
  • Opportunity for early ROW acquisition
slide-19
SLIDE 19 20

Right-of-Way Services for Office of Innovative Delivery

Phil Copeland PMC Right-of-Way Lead

slide-20
SLIDE 20 21

Anticipated Right-of-Way Service Classes for the Prime

slide-21
SLIDE 21 22

Anticipated Right-of-Way Service Classes for Sub-consultants

Number Right-of-Way Acquisition Services 10.3.1 Appraisal Report 10.3.3 Cost to Cure Report 10.3.4 Trade Fixture Report 10.3.5 Sign Report 10.3.9 Detailed Cost Estimator 10.4.1 ROW Project Manager 10.4.2 Pre-Acquisition 10.4.3 Acquisition 10.4.4 Negotiation through Closing 10.4.5 Relocation (Negotiations) 10.1.2 Relocation (Benefits Package Preparation)

slide-22
SLIDE 22 23

MMIP Right-of-Way Service Provider Roles & Responsibilities

Pre-Let

  • Cost Estimates
  • Conceptual Plan Review and Coordination with GEC
  • Pre-Acquisition Activities
  • Status Meetings
  • Right-of-Way Plan Revisions
  • Offer Packages and Negotiations
  • Closing Preparation
  • Property Management
  • Relocation Activities
  • Detailed Record Keeping
  • e-Builder Utilization
slide-23
SLIDE 23 24

MMIP ROW Keys to Success

  • Experienced Project Manager
  • Qualified Key Team Agents
  • Appropriate Team Structure
  • Proven Responsiveness
  • Proactive Coordination
  • Committed to DBE Success
  • Schedule Expeditor
  • Innovative Delivery Approaches
slide-24
SLIDE 24 25

RFP Overview

  • Approximately 50 Parcels
  • Anticipated 18-24 Months Duration
  • GDOT will evaluate price and technical approach
  • DBE Goal
  • Conflict of Interest-Refer to GDOT Design-Build Manual for More Info
slide-25
SLIDE 25 26

Team Requirements

# of Agents Number Valuation/Acquisition Services 4 10.3.1 Appraisal Report 2 10.3.3 Cost to Cure Report 1 10.3.4 Trade Fixture Report 1 10.3.5 Sign Report 1 10.3.9 Detailed Cost Estimator 1 10.4.1 ROW Project Manager 1 10.4.2 Pre-Acquisition 1 10.4.3 Acquisition Manager 2 10.4.4 Negotiation through Closing 2 10.4.5 Relocation (Negotiations) 1 10.1.2 Relocation (Benefits Package Preparation)

slide-26
SLIDE 26 27

Work From Conceptual Overlay to…

slide-27
SLIDE 27 28

Anticipated Procurement Schedule

  • a. GDOT issues Public Notice Advertisement
(PNA) 12/18/2018
  • b. Industry Forum/Pre-Bid Meeting – GDOT
01/08/2019 9:00 AM
  • c. GDOT issues Request for Proposal (RFP)
01/15/2019
  • d. Proposal Due
  • e. Anticipated Award of ROW Service
Provider 02/15/2019 April 2019
  • Tentative dates and subject to change. Refer to RFQ.
slide-28
SLIDE 28 29

www.dot.ga.gov/MMIP @GeorgiaDOT @GADeptofTrans @gadeptoftrans

THANK

YOU

For Viewing