right of way industry forum
play

Right-of-Way Industry Forum SR 400 Express Lanes PI 0001757 - PowerPoint PPT Presentation

Right-of-Way Industry Forum SR 400 Express Lanes PI 0001757 Fulton/Forsyth Joe Carpenter, PE P3 Director Tim Matthews, PE MMIP Program Manager January 8, 2019 1 Disclaimer Statement At this meeting the Department will provide


  1. Right-of-Way Industry Forum SR 400 Express Lanes PI 0001757 Fulton/Forsyth Joe Carpenter, PE – P3 Director Tim Matthews, PE – MMIP Program Manager January 8, 2019 1

  2. Disclaimer Statement At this meeting the Department will provide information about the project’s delivery goals, anticipated scope, anticipated Design-Build procurement process, and potential risks. Participants will be encouraged to ask questions during this meeting; however, any information provided by the Department shall be considered as informational only and is subject to change . 2

  3. We Will Cover • Major Mobility Investment Program • SR 400 Express Lanes • Disadvantaged Business Enterprise (DBE) Program • Right-of-Way (ROW) Services for the Office of Innovative Delivery (OID) • Open Discussion 3

  4. Major Mobility Investment Program 4

  5. 11 MMIP Projects 3 Major 4 Major Express 3 Major Interstate 1 Commercial Interchange Lanes Projects Widening Projects Vehicle Lanes Projects Project 5

  6. MMIP Project Locations 6

  7. MMIP Schedule 7

  8. Consultant Opportunities 8

  9. Disadvantaged Business Enterprises 9

  10. Program Delivery Model- PMC & GECs 10

  11. DBE Goal and Mentoring Program • 15% DBE Goal for GECs • GEC Mentoring Program o RFQ may require Mentoring Program implementation plan 11

  12. SR 400 Express Lanes 12

  13. SR 400 Express Lanes Overview • Anticipate Design-Build-Finance-Operate-Maintain (DBFOM) delivery method – Availability Payment Approach • Two express lanes in each direction along SR 400 between I-285 and McGinnis Ferry Road • One express lane in each direction from McGinnis Ferry Road to McFarland Parkway • Will directly connect to I-285 Top End Express Lanes • Intermediate access points to be determined • Estimated Cost: $1.8 Billion • Est. Construction Letting: Q4 2020 13

  14. SR 400 Express Lanes • I-285 to McGinnis Ferry Road • Two express lanes in each direction (illustrative example) Express lanes Bi-directional (Buffer Separated) Express Lanes 15

  15. SR 400 Express Lanes • McGinnis Ferry Road to McFarland Parkway • One express lane in each direction (illustrative example) Express lanes Bi-directional (Buffer Separated) 16 Express Lanes

  16. SR 400 Express Lanes Project Status Scoping Phase • Traffic analysis • Access testing • Coordination with Stakeholders, SRTA, and MARTA • Environmental field work GEC Pre-Let Status Concept Approval Q1 2019 • PIOH Q1 2019 • Advance ROW Acquisitions • DBFOM Development and Technical Provisions • Issue NOIA/PNA Q2 2019 • Issue RFQ Q3 2019 • Issue Preliminary RFP Q1 2020 • Costing Plans Set Complete & Draft RFP Q2 2020 • Final NEPA Approval Q3 2020 • Issue Final RFP Q3 2020 • Letting/Proposer Selection Q4 2020 • 17

  17. SR 400 Express Lanes Schedule Pr Project ect Ph Phases es 2017 2017 2018 2018 2019 2019 202 202 202 202 202 202 202 202 202 202 0 1 2 3 4 Environmental Design-Build Procurement Right-of-Way Final Design Construction Schedule subject to change Early ROW acquisition 18

  18. SR 400 Express Lanes Next Steps Environmental phase • Concept approval • Future conditions operational analysis • Opportunity for early ROW acquisition • 19

  19. Right-of-Way Services for Office of Innovative Delivery Phil Copeland PMC Right-of-Way Lead 20

  20. Anticipated Right-of-Way Service Classes for the Prime 21

  21. Anticipated Right-of-Way Service Classes for Sub-consultants Number Right-of-Way Acquisition Services 10.3.1 Appraisal Report 10.3.3 Cost to Cure Report 10.3.4 Trade Fixture Report 10.3.5 Sign Report 10.3.9 Detailed Cost Estimator 10.4.1 ROW Project Manager 10.4.2 Pre-Acquisition 10.4.3 Acquisition 10.4.4 Negotiation through Closing 10.4.5 Relocation (Negotiations) 10.1.2 Relocation (Benefits Package Preparation) 22

  22. MMIP Right-of-Way Service Provider Roles & Responsibilities Pre-Let • Cost Estimates • Conceptual Plan Review and Coordination with GEC • Pre-Acquisition Activities • Status Meetings • Right-of-Way Plan Revisions • Offer Packages and Negotiations • Closing Preparation • Property Management • Relocation Activities • Detailed Record Keeping • e-Builder Utilization 23

  23. MMIP ROW Keys to Success • Experienced Project Manager • Qualified Key Team Agents • Appropriate Team Structure • Proven Responsiveness • Proactive Coordination • Committed to DBE Success • Schedule Expeditor • Innovative Delivery Approaches 24

  24. RFP Overview • Approximately 50 Parcels • Anticipated 18-24 Months Duration • GDOT will evaluate price and technical approach • DBE Goal • Conflict of Interest-Refer to GDOT Design-Build Manual for More Info 25

  25. Team Requirements # of Agents Number Valuation/Acquisition Services 4 10.3.1 Appraisal Report 2 10.3.3 Cost to Cure Report 1 10.3.4 Trade Fixture Report 1 10.3.5 Sign Report 1 10.3.9 Detailed Cost Estimator 1 10.4.1 ROW Project Manager 1 10.4.2 Pre-Acquisition 1 10.4.3 Acquisition Manager 2 10.4.4 Negotiation through Closing 2 10.4.5 Relocation (Negotiations) 1 10.1.2 Relocation (Benefits Package Preparation) 26

  26. Work From Conceptual Overlay to… 27

  27. Anticipated Procurement Schedule a. GDOT issues Public Notice Advertisement 12/18/2018 ---------- (PNA) b. Industry Forum/Pre-Bid Meeting – GDOT 01/08/2019 9:00 AM ----------- c. GDOT issues Request for Proposal (RFP) 01/15/2019 d. Proposal Due ----------- 02/15/2019 e. Anticipated Award of ROW Service April 2019 ----------- Provider Tentative dates and subject to change. Refer to RFQ. 28

  28. THANK YOU For Viewing @GADeptofTrans @gadeptoftrans www.dot.ga.gov/MMIP @GeorgiaDOT 29

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend