ric 30 9 26
play

RIC-30-9.26 PROJECT 200121 , PID 93455 MATCHMAKER EVENT FEBRUARY - PowerPoint PPT Presentation

RIC-30-9.26 PROJECT 200121 , PID 93455 MATCHMAKER EVENT FEBRUARY 26, 2020 GENERAL PROJECT INFORMATION Kent A. Kapustar, P.E. ODOT Project Manager 2 | RIC-30-9.26, PID 93455 ODOT PROJECT TEAM o Kent Kapustar, P.E. Project Manager o


  1. RIC-30-9.26 PROJECT 200121 , PID 93455 MATCHMAKER EVENT • FEBRUARY 26, 2020

  2. GENERAL PROJECT INFORMATION Kent A. Kapustar, P.E. ODOT Project Manager 2 | RIC-30-9.26, PID 93455

  3. ODOT PROJECT TEAM o Kent Kapustar, P.E. – Project Manager o Mike Fair, P.E. – District Construction Engineer o Ed Yetzer, P.E. – Construction Area Engineer o Jeff Labaki, P.E. – Construction Project Engineer o Lisa Washington – Northwest Regional Outreach Manager 3 | RIC-30-9.26, PID 93455

  4. PROJECT DESIGN TEAM Prime Consultant Fred Seling, P.E. – Prime Consultant Project Manager Subconsultants 4 | RIC-30-9.26, PID 93455

  5. PROJECT OVERVIEW Project Overview Maps – SR 309 to SR 13 5 | RIC-30-9.26, PID 93455

  6. PROJECT OVERVIEW Project Overview Maps – SR 13 to 5 th Avenue 6 | RIC-30-9.26, PID 93455

  7. KEY PROJECT DATES o Sale Date: April 2, 2020 o Award Date: April 13, 2020 o Construction Year 1 – Phases 1 & 2 o All Lanes Open by October 31, 2020 o Construction Year 2 – Phases 3, 4, 5 & 5A o Begin Construction April 1, 2021 o All Lanes Open by October 31, 2021 7 | RIC-30-9.26, PID 93455

  8. KEY PROJECT DATES o Construction Year 3 – Phases 6, 7 & 8 o Begin Construction April 1, 2022 o All Lanes Open by October 31, 2022 o Construction Year 4 – Phase 9 o Construction End Date: May 26, 2023 8 | RIC-30-9.26, PID 93455

  9. MAJOR WORK 9 | RIC-30-9.26, PID 93455

  10. PROJECT WORK o 3.8 Miles of full-depth pavement reconstruction on US 30 Subgrade stabilization o Widened shoulders o Median Barrier o Cutting back vertical rock faces along US 30 east of SR 545 o o Interchanges Reconfigure SR 39 interchange o Eliminate the closely spaced eastbound SR 13 and SR 545 off/on o ramps. Combine into a single off/on ramp Minor improvements to the Trimble Road, SR 13 – westbound, SR o 545 – westbound and Fifth Avenue ramps 10 | RIC-30-9.26, PID 93455

  11. PROJECT WORK o Structure Work Replace 4 mainline bridges o Remove 1 existing mainline bridge o Minor repair to RIC-30-11.56 (17-span concrete I-beam bridge) o Decorative vandal protection fence with “MANSFIELD” lettering on 2 o existing bridges o Highway Lighting o Drainage o Two Retaining Walls o Noise Barrier Wall 11 | RIC-30-9.26, PID 93455

  12. PROJECT WORK o Traffic Signal o Signing and Pavement Marking o ROW Fence Replacement o Side Roads Construction of new cul-de-sac with moveable barrier gate on West o Longview Avenue Realignment of West Longview Avenue at SR 39 o Realignment of SR 545 o Reconstruction of SR 39 o Milling and Resurfacing of East Longview Avenue o Reconstruction of Wise Avenue o 12 | RIC-30-9.26, PID 93455

  13. MATERIALS 13 | RIC-30-9.26, PID 93455

  14. ROADWAY PAVEMENT o Item 301 & 302 – Flexible Pavement: 36,000 CY o Item 441 & 442 Flexible Pavement: 25,000 CY o Item 452 Concrete Pavement: 19,000 SY o Item 254 Pavement Planing: 82,000 SY Roadway and Pavement Estimated Cost: $24.7 Million 14 | RIC-30-9.26, PID 93455

  15. STRUCTURE WORK o Replace 4 mainline bridges with 3-span continuous steel beam bridges on semi-integral abutments o Remove 3-span continuous steel beam bridge and replace with embankment o Partial deck overlay, bearing resets, replace strip seals on RIC-30-1156 L/R major bridge o Decorative fencing with lettering on two bridges o Two retaining walls and one noise wall Structure Work Estimated Cost: $21.5 Million 15 | RIC-30-9.26, PID 93455

  16. DRAINAGE AND EROSION CONTROL WORK o Item 611 Drainage – 6” to 78” Conduit o Item 659 and 832 Erosion Control and Storm Water Pollution Prevention Drainage and Erosion Control Work Estimated Cost: $5.9 Million 16 | RIC-30-9.26, PID 93455

  17. TRAFFIC CONTROL, TRAFFIC SIGNAL & LIGHTING WORK o Item 642 Pavement Markings o Item 630 Signs and Supports o Item 625 Highway Lighting o Item 625, 632, 633 and 809 Traffic Signal Traffic Control, Signal and Lighting Work Estimated Cost: $3.3 Million 17 | RIC-30-9.26, PID 93455

  18. MAINTAINING TRAFFIC o Item 614 Maintaining Traffic Includes $750,000 for maintaining existing bridge decks and o pavement patching on the existing roadway throughout the project o Item 615 Pavement for Maintaining Traffic, Class A: 77,000SY o Item 622 Portable Barrier: 306,000 FT Maintenance of Traffic Work Estimated Cost: $11.7 Million *************************************************************************** Opinion of Probable Construction Cost Total $72.9 Million 18 | RIC-30-9.26, PID 93455

  19. MAINTENANCE OF TRAFFIC 19 | RIC-30-9.26, PID 93455

  20. MAINTENANCE OF TRAFFIC o CY 2020 o Phases 1 & 2 o Construct outside portion of EB Bowman St Bridge o Mainline pavement for maintaining traffic o Longview Ave. relocation o Median and shoulder reconstruction east of SR 545 o Ramp I o Drainage and pavement on SR 39 and SR 545. o Construct Median Crossovers 20 | RIC-30-9.26, PID 93455

  21. MAINTENANCE OF TRAFFIC o CY 2021 o Phase 3 21 | RIC-30-9.26, PID 93455

  22. MAINTENANCE OF TRAFFIC o CY 2021 o Phase 4 22 | RIC-30-9.26, PID 93455

  23. MAINTENANCE OF TRAFFIC o CY 2021 o Phase 5 / 5A – Median / Bridge Construction 23 | RIC-30-9.26, PID 93455

  24. MAINTENANCE OF TRAFFIC o CY 2022 o Phase 6 24 | RIC-30-9.26, PID 93455

  25. MAINTENANCE OF TRAFFIC o CY 2022 o Phase 7 25 | RIC-30-9.26, PID 93455

  26. MAINTENANCE OF TRAFFIC o CY 2022 o Phase 8 o Asphalt Surface Course o Pavement markings, RPMs, shoulder rumble strips o CY 2023 o Phase 9 o Pavement markings, RPMs, shoulder rumble strips not completed due to temperature restrictions o Punch list items 26 | RIC-30-9.26, PID 93455

  27. DISADVANTAGED BUSINESS ENTERPRISE (DBE) DBE Goal –10% o Contains the Proposal Note 013-Disadvantaged Business Enterprise (DBE) Utilization Plan and Good Faith Efforts updated 04/20/2018 o All bidders shall submit a DBE Utilization Plan at the time of bid. 27 | RIC-30-9.26, PID 93455

  28. DISADVANTAGED BUSINESS ENTERPRISE (DBE) o The DBE Utilization Plan should set forth specific information demonstrating how bidder will achieve DBE Goal o DBE Certified Firms: http://www.dot.state.oh.us/Divisions/ODI/SDBE/Pages/DBE- o Directory.aspx 28 | RIC-30-9.26, PID 93455

  29. QUESTIONS ? Please state your Name and Company prior to asking your question Last updated 2/27/2020 29 | RIC-30-9.26, PID 93455

  30. THANK YOU FOR ATTENDING RIC-30-9.26, PID 93455 30 |

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend