RIC-30-9.26 PROJECT 200121 , PID 93455 MATCHMAKER EVENT FEBRUARY - - PowerPoint PPT Presentation

ric 30 9 26
SMART_READER_LITE
LIVE PREVIEW

RIC-30-9.26 PROJECT 200121 , PID 93455 MATCHMAKER EVENT FEBRUARY - - PowerPoint PPT Presentation

RIC-30-9.26 PROJECT 200121 , PID 93455 MATCHMAKER EVENT FEBRUARY 26, 2020 GENERAL PROJECT INFORMATION Kent A. Kapustar, P.E. ODOT Project Manager 2 | RIC-30-9.26, PID 93455 ODOT PROJECT TEAM o Kent Kapustar, P.E. Project Manager o


slide-1
SLIDE 1

RIC-30-9.26

PROJECT 200121 , PID 93455 MATCHMAKER EVENT • FEBRUARY 26, 2020

slide-2
SLIDE 2

2 |

GENERAL PROJECT INFORMATION

Kent A. Kapustar, P.E. ODOT Project Manager

RIC-30-9.26, PID 93455

slide-3
SLIDE 3

3 |

ODOT PROJECT TEAM

  • Kent Kapustar, P.E. – Project Manager
  • Mike Fair, P.E. – District Construction Engineer
  • Ed Yetzer, P.E. – Construction Area Engineer
  • Jeff Labaki, P.E. – Construction Project

Engineer

  • Lisa Washington – Northwest Regional Outreach

Manager

RIC-30-9.26, PID 93455

slide-4
SLIDE 4

4 |

PROJECT DESIGN TEAM

Fred Seling, P.E. – Prime Consultant Project Manager

RIC-30-9.26, PID 93455

Prime Consultant Subconsultants

slide-5
SLIDE 5

5 |

PROJECT OVERVIEW Project Overview Maps – SR 309 to SR 13

RIC-30-9.26, PID 93455

slide-6
SLIDE 6

6 |

PROJECT OVERVIEW Project Overview Maps – SR 13 to 5th Avenue

RIC-30-9.26, PID 93455

slide-7
SLIDE 7

7 |

KEY PROJECT DATES

  • Sale Date: April 2, 2020
  • Award Date: April 13, 2020
  • Construction Year 1 – Phases 1 & 2
  • All Lanes Open by October 31, 2020
  • Construction Year 2 – Phases 3, 4, 5 & 5A
  • Begin Construction April 1, 2021
  • All Lanes Open by October 31, 2021

RIC-30-9.26, PID 93455

slide-8
SLIDE 8

8 |

KEY PROJECT DATES

  • Construction Year 3 – Phases 6, 7 & 8
  • Begin Construction April 1, 2022
  • All Lanes Open by October 31, 2022
  • Construction Year 4 – Phase 9
  • Construction End Date: May 26, 2023

RIC-30-9.26, PID 93455

slide-9
SLIDE 9

9 |

MAJOR WORK

RIC-30-9.26, PID 93455

slide-10
SLIDE 10

10 |

PROJECT WORK

  • 3.8 Miles of full-depth pavement reconstruction on US 30
  • Subgrade stabilization
  • Widened shoulders
  • Median Barrier
  • Cutting back vertical rock faces along US 30 east of SR 545
  • Interchanges
  • Reconfigure SR 39 interchange
  • Eliminate the closely spaced eastbound SR 13 and SR 545 off/on
  • ramps. Combine into a single off/on ramp
  • Minor improvements to the Trimble Road, SR 13 – westbound, SR

545 – westbound and Fifth Avenue ramps

RIC-30-9.26, PID 93455

slide-11
SLIDE 11

11 |

PROJECT WORK

  • Structure Work
  • Replace 4 mainline bridges
  • Remove 1 existing mainline bridge
  • Minor repair to RIC-30-11.56 (17-span concrete I-beam bridge)
  • Decorative vandal protection fence with “MANSFIELD” lettering on 2

existing bridges

  • Highway Lighting
  • Drainage
  • Two Retaining Walls
  • Noise Barrier Wall

RIC-30-9.26, PID 93455

slide-12
SLIDE 12

12 |

PROJECT WORK

  • Traffic Signal
  • Signing and Pavement Marking
  • ROW Fence Replacement
  • Side Roads
  • Construction of new cul-de-sac with moveable barrier gate on West

Longview Avenue

  • Realignment of West Longview Avenue at SR 39
  • Realignment of SR 545
  • Reconstruction of SR 39
  • Milling and Resurfacing of East Longview Avenue
  • Reconstruction of Wise Avenue

RIC-30-9.26, PID 93455

slide-13
SLIDE 13

13 |

MATERIALS

RIC-30-9.26, PID 93455

slide-14
SLIDE 14

14 |

ROADWAY PAVEMENT

  • Item 301 & 302 – Flexible Pavement: 36,000 CY
  • Item 441 & 442 Flexible Pavement: 25,000 CY
  • Item 452 Concrete Pavement: 19,000 SY
  • Item 254 Pavement Planing: 82,000 SY

Roadway and Pavement Estimated Cost: $24.7 Million

RIC-30-9.26, PID 93455

slide-15
SLIDE 15

15 |

STRUCTURE WORK

  • Replace 4 mainline bridges with 3-span continuous steel

beam bridges on semi-integral abutments

  • Remove 3-span continuous steel beam bridge and replace

with embankment

  • Partial deck overlay, bearing resets, replace strip seals on

RIC-30-1156 L/R major bridge

  • Decorative fencing with lettering on two bridges
  • Two retaining walls and one noise wall

Structure Work Estimated Cost: $21.5 Million

RIC-30-9.26, PID 93455

slide-16
SLIDE 16

16 |

DRAINAGE AND EROSION CONTROL WORK

  • Item 611 Drainage – 6” to 78” Conduit
  • Item 659 and 832 Erosion Control and Storm Water Pollution

Prevention Drainage and Erosion Control Work Estimated Cost: $5.9 Million

RIC-30-9.26, PID 93455

slide-17
SLIDE 17

17 |

TRAFFIC CONTROL, TRAFFIC SIGNAL & LIGHTING WORK

  • Item 642 Pavement Markings
  • Item 630 Signs and Supports
  • Item 625 Highway Lighting
  • Item 625, 632, 633 and 809 Traffic Signal

Traffic Control, Signal and Lighting Work Estimated Cost: $3.3 Million

RIC-30-9.26, PID 93455

slide-18
SLIDE 18

18 |

MAINTAINING TRAFFIC

  • Item 614 Maintaining Traffic
  • Includes $750,000 for maintaining existing bridge decks and

pavement patching on the existing roadway throughout the project

  • Item 615 Pavement for Maintaining Traffic, Class A: 77,000SY
  • Item 622 Portable Barrier: 306,000 FT

Maintenance of Traffic Work Estimated Cost: $11.7 Million *************************************************************************** Opinion of Probable Construction Cost Total $72.9 Million

RIC-30-9.26, PID 93455

slide-19
SLIDE 19

19 |

MAINTENANCE OF TRAFFIC

RIC-30-9.26, PID 93455

slide-20
SLIDE 20

20 |

MAINTENANCE OF TRAFFIC

  • CY 2020
  • Phases 1 & 2
  • Construct outside portion of EB Bowman St Bridge
  • Mainline pavement for maintaining traffic
  • Longview Ave. relocation
  • Median and shoulder reconstruction east of SR 545
  • Ramp I
  • Drainage and pavement on SR 39 and SR 545.
  • Construct Median Crossovers

RIC-30-9.26, PID 93455

slide-21
SLIDE 21

21 |

MAINTENANCE OF TRAFFIC

  • CY 2021
  • Phase 3

RIC-30-9.26, PID 93455

slide-22
SLIDE 22

22 |

MAINTENANCE OF TRAFFIC

  • CY 2021
  • Phase 4

RIC-30-9.26, PID 93455

slide-23
SLIDE 23

23 |

MAINTENANCE OF TRAFFIC

  • CY 2021
  • Phase 5 / 5A – Median / Bridge Construction

RIC-30-9.26, PID 93455

slide-24
SLIDE 24

24 |

MAINTENANCE OF TRAFFIC

  • CY 2022
  • Phase 6

RIC-30-9.26, PID 93455

slide-25
SLIDE 25

25 |

MAINTENANCE OF TRAFFIC

  • CY 2022
  • Phase 7

RIC-30-9.26, PID 93455

slide-26
SLIDE 26

26 |

MAINTENANCE OF TRAFFIC

  • CY 2022
  • Phase 8
  • Asphalt Surface Course
  • Pavement markings, RPMs, shoulder rumble strips
  • CY 2023
  • Phase 9
  • Pavement markings, RPMs, shoulder rumble strips not

completed due to temperature restrictions

  • Punch list items

RIC-30-9.26, PID 93455

slide-27
SLIDE 27

27 |

DISADVANTAGED BUSINESS ENTERPRISE (DBE)

DBE Goal –10%

  • Contains the Proposal Note 013-Disadvantaged

Business Enterprise (DBE) Utilization Plan and Good Faith Efforts updated 04/20/2018

  • All bidders shall submit a DBE Utilization Plan at the time of

bid.

RIC-30-9.26, PID 93455

slide-28
SLIDE 28

28 |

DISADVANTAGED BUSINESS ENTERPRISE (DBE)

  • The DBE Utilization Plan should set forth specific information

demonstrating how bidder will achieve DBE Goal

  • DBE Certified Firms:
  • http://www.dot.state.oh.us/Divisions/ODI/SDBE/Pages/DBE-

Directory.aspx

RIC-30-9.26, PID 93455

slide-29
SLIDE 29

29 |

?

QUESTIONS

Last updated 2/27/2020

RIC-30-9.26, PID 93455

Please state your Name and Company prior to asking your question

slide-30
SLIDE 30

30 |

THANK YOU FOR ATTENDING

RIC-30-9.26, PID 93455