Responding to COVID Capital Program Impacts Sound Transit Board - - PowerPoint PPT Presentation

responding to covid capital program impacts
SMART_READER_LITE
LIVE PREVIEW

Responding to COVID Capital Program Impacts Sound Transit Board - - PowerPoint PPT Presentation

Responding to COVID Capital Program Impacts Sound Transit Board April 23, 2020 Why we are here Informational and discussion only, no Board action required Discuss possible COVID effects on our capital program. Revisit Board


slide-1
SLIDE 1

Responding to COVID Capital Program Impacts

Sound Transit Board April 23, 2020

slide-2
SLIDE 2

2

Why we are here

Informational and discussion only, no Board action required

  • Discuss possible COVID effects on our capital program.
  • Revisit Board precedent from last recession.
  • Frame possible agency responses.
slide-3
SLIDE 3

3

We’ve been here before

Sound Transit’s response to the Great Recession after ST2

  • 25% initial revenue loss.
  • Board held workshops to guide response.
  • Board modified system plan to reduce, reschedule, suspend, or

cancel select projects.

slide-4
SLIDE 4

4

  • Sept. 2010 Board workshop

Project realignment priorities High priorities

  • Achieve goals of voter-approved system plan.
  • Preserve projects underway or near completion.
  • Maintain assets.
slide-5
SLIDE 5

5

  • Sept. 2010 Board workshop

Project realignment priorities Lower priorities

  • Projects meeting fewer System Plan goals.
  • Discretionary programs.
  • Maintaining project reserves.
  • Projects with undefined scope or uncertain partner

commitments.

  • Projects or services with low ridership.
slide-6
SLIDE 6

6

ST2 project realignment categories

Design & construct as planned. Continue with schedule and affordability risk. Retain limited funding to develop future options. Suspend indefinitely and remove from finance plan. Delete project from program entirely.

slide-7
SLIDE 7

7

Uncertain future finances

Data available

  • March national retail sales: 8.7% in March
  • Unemployment claims: 26 million in last 5 weeks
  • ST Ridership loss: 86%
  • Federal assistance available:$166 million

Data not yet available

  • March and April actual tax receipts.
  • Duration of WA State social distancing.
  • Length and depth of recession.
slide-8
SLIDE 8

8

Program Funding sources (2017-2041: $97.9B)

8 Sales Tax 53% MVET 9%

Property

5% Grants 8% Fares 7% Debt 18%

  • Tax revenues fund 67% of

the program.

  • Debt funds 18%.
  • Fares fund 7%.

All above funding sources will be negatively impacted by a recession.

slide-9
SLIDE 9

9

Revenue shortfall as a result of the recession

9

Sales Tax MVET

Property

Grants Fares Debt Revenu e shortfall

  • As revenue sources

shrink as a proportion

  • f the total program,

more debt will be issued to make up for some or all of the shortfall.

*Conceptual illustration

slide-10
SLIDE 10

10

Insufficient funding would require adjustment to the program

1

Sales Tax MVET

Property

Grants Fares Higher debt up to capacity limits

Funding gap

  • When funding need exceeds

available debt capacity, the program becomes unaffordable.

  • One of the debt capacity

constraints is based on regional property values, which is also likely to decline in a recession.

*Conceptual illustration

slide-11
SLIDE 11

11

  • Mild scenario: similar to dot com recession (2002)
  • Severe scenario: similar to great recession (2008)

Recession threatens program affordability

Debt Capacity

$- $5 $10 $15 $20 $25 $30 $35 $40 $45

2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041

Billions of YOE$

Debt Capacity - Fall 2019 vs Recession Scenarios

Principal Balance as Forecasted in Fall 2019 Principal Balance as Forecasted with Dot Com Recession Principal Balance as Forecasted with Great Recession Debt Capacity as Forecasted in Fall 2019

slide-12
SLIDE 12

12

Revenue and Capacity Impact

2020-2041 (YOE$ in millions)

` Dot Com Recession Great Recession

Loss of revenue

  • $5.6 Billion
  • $11.9 Billion

As % of remaining capital

  • 11.8%
  • 25.2%

Loss of debt capacity

  • $4.9 Billion
  • $14.5 Billion

As % of remaining capital

  • 10.5%
  • 30.8%

Remaining capital (includes 2020): $47.2 Billion

slide-13
SLIDE 13

13

Board tools to manage affordability

  • Extend the time to complete the system.
  • Modify project scope.
  • Secure new grant funding or funding partners.
  • Suspend or delete projects.
  • Request a further tax increase from the legislature

and voters.

slide-14
SLIDE 14

14

ST Board’s Core Priorities for ST3

Elements of good design

slide-15
SLIDE 15

15

CEO’s near-term approach

Maintain Board’s flexibility and readiness for uncertain future Keep construction going safely

  • Northgate, East Link, Lynnwood, Federal Way, Downtown

Redmond, Hilltop Tacoma Link, OMF East.

slide-16
SLIDE 16

16

CEO’s near-term approach

Maintain Board’s flexibility and readiness for uncertain future Continue work in planning and final design

  • Maintain readiness for variable revenue/grant scenarios.
  • Slower, more incremental approach in some instances as

longer-term realignment takes shape.

slide-17
SLIDE 17

17

CEO’s near-term approach

Maintain Board’s flexibility and readiness for uncertain future Hold on moving further projects into final design or construction

  • Avoid over-commitment until Board priorities become clearer.
slide-18
SLIDE 18

18

Board discussion schedule

Board, Executive Committee, Finance & Audit Committee April Establish context & process May Board workshop (History, context) June Board workshop (Criteria, options, evaluation) July Establish initial project priorities Fall Review project priorities via 2021 budget process

slide-19
SLIDE 19

Thank you.

soundtransit.org