Responding to COVID Capital Program Impacts
Sound Transit Board April 23, 2020
Responding to COVID Capital Program Impacts Sound Transit Board - - PowerPoint PPT Presentation
Responding to COVID Capital Program Impacts Sound Transit Board April 23, 2020 Why we are here Informational and discussion only, no Board action required Discuss possible COVID effects on our capital program. Revisit Board
Sound Transit Board April 23, 2020
2
Informational and discussion only, no Board action required
3
Sound Transit’s response to the Great Recession after ST2
cancel select projects.
4
Project realignment priorities High priorities
5
Project realignment priorities Lower priorities
commitments.
6
Design & construct as planned. Continue with schedule and affordability risk. Retain limited funding to develop future options. Suspend indefinitely and remove from finance plan. Delete project from program entirely.
7
Data available
Data not yet available
8
8 Sales Tax 53% MVET 9%
Property
5% Grants 8% Fares 7% Debt 18%
the program.
All above funding sources will be negatively impacted by a recession.
9
9
Sales Tax MVET
Property
Grants Fares Debt Revenu e shortfall
shrink as a proportion
more debt will be issued to make up for some or all of the shortfall.
*Conceptual illustration
10
1
Sales Tax MVET
Property
Grants Fares Higher debt up to capacity limits
Funding gap
available debt capacity, the program becomes unaffordable.
constraints is based on regional property values, which is also likely to decline in a recession.
*Conceptual illustration
11
Debt Capacity
$- $5 $10 $15 $20 $25 $30 $35 $40 $45
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041
Billions of YOE$
Debt Capacity - Fall 2019 vs Recession Scenarios
Principal Balance as Forecasted in Fall 2019 Principal Balance as Forecasted with Dot Com Recession Principal Balance as Forecasted with Great Recession Debt Capacity as Forecasted in Fall 2019
12
2020-2041 (YOE$ in millions)
` Dot Com Recession Great Recession
Loss of revenue
As % of remaining capital
Loss of debt capacity
As % of remaining capital
Remaining capital (includes 2020): $47.2 Billion
13
14
Elements of good design
15
Maintain Board’s flexibility and readiness for uncertain future Keep construction going safely
Redmond, Hilltop Tacoma Link, OMF East.
16
Maintain Board’s flexibility and readiness for uncertain future Continue work in planning and final design
longer-term realignment takes shape.
17
Maintain Board’s flexibility and readiness for uncertain future Hold on moving further projects into final design or construction
18
Board, Executive Committee, Finance & Audit Committee April Establish context & process May Board workshop (History, context) June Board workshop (Criteria, options, evaluation) July Establish initial project priorities Fall Review project priorities via 2021 budget process