report to future tairawhiti committee for information
play

Report to FUTURE TAIRAWHITI Committee for information SUMMARY The - PDF document

18262 Title: Puhi Kai Iti/Cook Landing Site Concept Plan Presentation Section: Transformation & Relationships Prepared by: De-Arne Sutherland (Senior Programme/Project Manager Tairawhiti Navigations) Meeting Date: 7 June 2018


  1. 18–262 Title: Puhi Kai Iti/Cook Landing Site Concept Plan Presentation Section: Transformation & Relationships Prepared by: De-Arne Sutherland (Senior Programme/Project Manager – Tairawhiti Navigations) Meeting Date: 7 June 2018 ☐ Legal ☐ Financial  Significance = Medium Report to FUTURE TAIRAWHITI Committee for information SUMMARY The purpose of this paper is to refer to a presentation of the Puhi Kai Iti/Cook Landing Site Concept Plans to be presented to the Committee during the meeting. The plans will be presented by the Project Team, including Nick Tupara - Ngati Oneone representative, John Lucas - Operations Manager Department of Conservation, and De-Arne Sutherland - Tair ā whiti Navigations Programme Manager. The Cook Landing Site project is a partnership project between the Department of Conservation (DOC) and Ngati Oneone and Council, with Council providing project management support and co-ordination as part of the Tair ā whiti Navigations programme. The concept plans have been informed through stakeholder workshops undertaken earlier in the year. The decisions or matters in this report are considered to be of Medium significance in accordance with Council’s Significance and Engagement Policy. RECOMMENDATION That the Future Tairawhiti Committee: 1. Notes the contents of this report - and in particular: a) The Cook Landing site Project presentation for information. Authorised by: Keita Kohere Director Transformation & Relationships Keywords : Puhi Kai Iti, Cook Landing Site, Concept Plans, 1000 year walkway A948887 Page 1 of 3

  2. BACKGROUND 1. In 2017 the Department of Conservation approached Gisborne District Council to assist them, in partnership with Ngati Oneone, to deliver the Cook Landing Site project as part of the Tair ā whiti Navigations Programme, and in time for Sestercentennial Commemorations in 2019. 2. The project is funded by the Department of Conservation, with further external funding being sought to deliver the full scope of the project and meet key stakeholder aspirations. 3. Key stakeholders including; Eastland Port, Te Ha Trust, Heritage New Zealand, Historic Places Tairawhiti, NZTA, Tair ā whiti Roads, Tair ā whiti Navigations Governance Group members have contributed to the design elements and stories to be told from the project site. 4. The Tair ā whiti Economic Action Plan 2017 (TEAP) acknowledges the Cook Landing Site Upgrade project as a key part in delivering economic opportunities for Tair ā whiti through tourism and indicated potential funding of $1 million under Action 5.3. DISCUSSION 5. A funding application has been made to the Ministry of Business Innovation and Employment (MBiE) in March through the Provincial Growth Fund process to fund the components of the project located within the Cook Landing Site reserve, consistent with Action 5.3 of TEAP. 6. Following iwi and stakeholder engagement it became clear there was a strong aspiration for the project to provide for a connection between the Cook Landing Site and Titirangi. The concept plans include a bridge currently referred to as the ‘1000 year walkway’. 7. A funding application has been lodged through the Lottery Significant Project fund for construction of the ‘1000 year walkway’ as well as a commemoration area on Titirangi to acknowledge Te Maro, a significant tipuna of Ngati Oneone. 8. Procurement for construction of the project is yet to be undertaken, and therefore costs of the various components have not been included in this report. 9. Decisions by funders should be made between June and July this year. Should no external funding be made available to this project, then a reduced scope would need to be considered for delivery for sestercentennial commemorations in 2019. However, discussions with funders are proceeding well to date. 10. Further stakeholder workshops will be held in late June to garner further story elements to inform story telling details. 11. A report for decision by the Future Tair ā whiti Committee will be presented in August 2018 to confirm scope and available budget for the project before proceeding through to developed design. ASSESSMENT OF SIGNIFICANCE The Process Criteria This Report Overall The effects on all or a large part of the Gisborne district Low Low The effects on individuals or specific communities Medium High The level or history of public interest in the matter or issue Medium High Inconsistency with Council’s current strategy and policy Low Low Impacts on Council’s delivery of its Financial Strategy and Long Term Plan. Low Low A948887 Page 2 of 3

  3. 12. The decisions or matters in this report are considered to be of medium significance in accordance with Council’s Significance and Engagement Policy. 13. While the matters included in the presentation are of medium significance, the interest from national agencies and those associated with heritage values are high; particularly as we proceed towards development on the Cook Landing Site, as a national historic reserve. NEXT STEPS Date Action/Milestone Comments Purpose is to further develop design June/July 2018 Stakeholder workshop(s) and story details. Councillors will be invited to attend. June-July 2018 Funding application feedback SPF and PGF applications Intention to take full design to Future Detailed design complete and approval sought August 2018 Tairawhiti Committee on 16 August from Council 2018. October/November 2018 Construction starts Following tender process In time for Sestercentennial June 2019 Project completion Commemorations in October 2019 A948887 Page 3 of 3

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend