Registration for Regulatory Energy Management Non- Generator Resource Fall 2012 Market Simulation Web Conference July 23, 2012 9:00 a.m. 12:00 p.m. (Pacific Time) Web Conference
Page 2
Agenda
July 23, 2012 9:00 a.m. – 12:00 p.m. (Pacific Time)
Time Topic Facilitator 9:00 – 10:05 Agenda & ISO Roll call Julia Payton 10:05 – 11:00 NGR registration plan James Li Zhou Sirajul Chowdhury Chris Mcintosh Meghna Khatri James Lynn Wendell Tamblyn, Saurabh Monga Sirajul Chowdhury June Xie George Angelidis Andrew Ulmer Jeremy Malekos 11:00 – 12:00 Q&A
Registration deadline Friday July 27, 2012 5 pm (Pacific Time)
Fall NGR Non-REM Market Simulation Plan – 2012
- Tentative Market Simulation dates
– Week 1: 9/4/12 – 9/7/12
- 1 week Non-Rem structured scenarios
- 3 trade dates: 9/5, 9/6, 9/7
– Week 2: 9/10/12 – 9/14/12
- Allow market participants to analyze data
- No scheduled scenarios
– Week 3: 9/17/12 – 9/21/12
- 1 week Non-Rem unstructured scenarios
- 3 trade dates: 9/19, 9/20, 9/21
Page 4
NGR Registration Requirements
- Type
– Storage Resource or – Demand Response
- Brief description of technology being modeled.
– Other resources that operate as either generation or load and can be dispatched seamlessly within their entire capacity range
- Model (See diagram: Show matrix)
– Regulation Energy Management. (DR is only able to participate under the REM Model.) – Non-REM (Storage resource that can participate in Spin/Non-Spin, Energy, Regulation Up/Down)
- Resource characteristics required on July 27, 2012
– Location:
- address
- substation name, voltage level
– size (Pmin, Pmax) – Energy Limits: MWH (Upper and Lower limits if existing) – Technology (brief description of the technology)
Note: A Complete Generator V6.5 Resources Data Template will be due prior to the September 4, 2012 Market
- Simulation. The ISO will work through your Scheduling Coordinator to complete this document.
Page 5
NGR Model Matrix
Project Technology Model Option to REM (Special Treatment) Regulation Spin/Non- Spin Energy Qualified MW Non-Generator Resource (NGR) New functions in EMS, and market from Bid to Bill
Limited Energy Storage Resource (LESR) (Flywheel, battery, energy storage) Operation range between negative (Charge) and positive (Discharge), constrained by State of Charge (SOC) REM SC Bid No No 15 minute continuous delivery Non REM SC Bid SC Bid SC Bid Depending on registration and certification Dispatch-able Demand Response (DDR) Implementation of the Participating Load (PLR) model Operation range is non-positive, REM SC Bid No No 15 minute continuous delivery Non REM SC Bid SC Bid SC Bid Depending on registration and certification
Page 6
NGR – Regulation Energy Management Option
http://www.caiso.com/Documents/Plans%20and%20schedule/2012ReleasePlan.pdf
NGR REM only resource option description
- This is typically a 15min. resource. i.e. 0.25MWh
- Demand response can utilize this model to participate in wholesale regulation
- Brief description of how AGC signal is derived.
- Brief description of 50% rule.
NGR – Non Regulation Energy Management Option
NGR Non-Rem resource option description
- This option allows a storage resource to participate in Energy, Spin/Non Spin and regulation Up/Down.
- This option will be for the resources that have a long period of maintaining generation or load sides.
- This option assumes a resource is continuous for more than 1 hour.
In August the ISO will host a workshop with market participants to review the Market Simulation structured scenarios and discuss
Next Steps
- In August the ISO will host a workshop with market participants to review the Market Simulation