PROJECT MAP – PLATFORM AND TRACK WORK
0.
Warriors Arena Platform and Track work
3
PROPOSED WARRIORS ARENA AND OFFICE SPACE
- 18,000 seat multi-purpose arena and
event space
- 580,000 square-feet of office / lab space
- 10,000 square-feet of retail space
- 35,000 square-feet of public plaza space
- 3.2 acres (plaza, landscaping, and other
public space)
- 950 parking spots for office users and site
visitors
4
PROPOSED WARRIORS ARENA AND OFFICE SPACE
5
EXISTING UCSF PLATFORM
Existing Platform dimension - 160’ x 10’
6
CENTER PLATFORM PROPOSAL
Proposed 320’ x 16’
7
PROJECT SCHEDULE
Milestone Duration
Environmental: Part of Warrior EIR. BOS Approved Nov 2015 Conceptual Engineering: Spring 2016 Detailed Design: Summer 2016 to Spring 2017 Advertise & Award: Fall 2017 Construction: Winter 2017 to Spring 2019 Testing Spring 2019 Warrior Stadium Opening Spring-Summer 2019
8
Contact: Project Manager: Cathal Hennessy, Cathal.Hennessy@sfmta.com Project Engineer: Chris Nocon, Chris.Nocon@sfmta.com Public Works PM: Will Quan, Will.Kwan@sfdpw.org