1

UCSF Platform and Track reconfiguration

slide-2
SLIDE 2

2

PROJECT MAP – PLATFORM AND TRACK WORK

0.

Warriors Arena Platform and Track work

slide-3
SLIDE 3

3

PROPOSED WARRIORS ARENA AND OFFICE SPACE

  • 18,000 seat multi-purpose arena and

event space

  • 580,000 square-feet of office / lab space
  • 10,000 square-feet of retail space
  • 35,000 square-feet of public plaza space
  • 3.2 acres (plaza, landscaping, and other

public space)

  • 950 parking spots for office users and site

visitors

slide-4
SLIDE 4

4

PROPOSED WARRIORS ARENA AND OFFICE SPACE

slide-5
SLIDE 5

5

EXISTING UCSF PLATFORM

Existing Platform dimension - 160’ x 10’

slide-6
SLIDE 6

6

CENTER PLATFORM PROPOSAL

Proposed 320’ x 16’

slide-7
SLIDE 7

7

PROJECT SCHEDULE

Milestone Duration

Environmental: Part of Warrior EIR. BOS Approved Nov 2015 Conceptual Engineering: Spring 2016 Detailed Design: Summer 2016 to Spring 2017 Advertise & Award: Fall 2017 Construction: Winter 2017 to Spring 2019 Testing Spring 2019 Warrior Stadium Opening Spring-Summer 2019

slide-8
SLIDE 8

8

Contact: Project Manager: Cathal Hennessy, Cathal.Hennessy@sfmta.com Project Engineer: Chris Nocon, Chris.Nocon@sfmta.com Public Works PM: Will Quan, Will.Kwan@sfdpw.org