RC Status Report 17 May 2011 LARP CM16 Tom Markiewicz/SLAC SLAC - - PowerPoint PPT Presentation

rc status report
SMART_READER_LITE
LIVE PREVIEW

RC Status Report 17 May 2011 LARP CM16 Tom Markiewicz/SLAC SLAC - - PowerPoint PPT Presentation

US LHC Accelerator Research Program BNL - FNAL- LBNL - SLAC RC Status Report 17 May 2011 LARP CM16 Tom Markiewicz/SLAC SLAC RC Design Details RC-1 Jaw (Glidcop) RF foils carry image current Tank geometry allows a 60mm and shields Rot.


slide-1
SLIDE 1

RC Status Report

17 May 2011 LARP CM16 Tom Markiewicz/SLAC

BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program

slide-2
SLIDE 2

SLAC RC Design Details

Ratchet Gear Drive RC-0 Jaw (copper) RC-1 Jaw (Glidcop) LHC IR7 Style BPM Buttons 4 per end Flex Support Tank geometry allows a 60mm facet-to-facet gap in fully retracted Jaw position Base Plate Drive Mechanism RF foils carry image current and shields Rot. Mech.

slide-3
SLIDE 3

During the 6 prior months of lab tests uncovered

  • Deficiencies in the primary bearing and RF bearing designs
  • Deficiencies in the design of the drive unit and related hardware
  • Problems with testing setup (slippage of parts prior to final welding)

Result is multiple cycles of test, failure, redesign, manufacture, install, retest Rebuilt (& “perfect”) prototype finally moved from test lab (10/28/10) and into vacuum clean room for final welding, assembly, bake out and testing

Summary of CM15 RC Talk on 1-Nov-2010

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz Slide n° 3 / 37

slide-4
SLIDE 4

Weld bellows to base plate and jaw supports to bellows Install final version of all parts Rotation drives with new larger diameter W-S2 impregnated bearings and shafts Rebuilt primary jaw-support bearings and their housings Parts which hold thermistors & prevent “oil-canning” of RF shields Weld cooling tubes into their feed throughs so that all rotation tests from this point on cause tubes to twist Rotation, resistance, & alignment tests Tests under vacuum after vessel cover welded: no more access Vacuum bake out & RGA scan: 2-weeks into 240°C bake

  • Estimated three weeks to achieve 9-scale vacuum
  • Post bake out rotation tests

Punch List of Work Still Required as of 1-Nov-2010

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz Slide n° 4 / 37

slide-5
SLIDE 5

Collimator Assembled, Tank Welded Shut Rotation, Resistance, Alignment Good One New Large Problem

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

Assembly complete on13-Mar-11 All Welding complete Heater Tape & Thermocouples 28-Apr-11

Slide n° 5 / 37

slide-6
SLIDE 6

Baseplate, Bellows & Jaw Support Welds

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

Cooling Tube Feedthrough Welded to A286 SS Jaw Support Bellows Plug Held by Fixture and Welded to Bottom of Bellows Bellows Fixtured, Protected and Welded to Vacuum Side of Baseplate

2010-11-08 2010-12-03 2010-12-03

Slide n° 6 / 37

slide-7
SLIDE 7

Leak Checking Bellows Welds

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

Leak Rate in mbar-l/sec (1.2E-9)

Slide n° 7 / 37

slide-8
SLIDE 8

Rebuilding and Reassembly of Rotation Drives and Main Rotation Bearings

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

Rotation Drives

2011-01-13 2010-12-22

W-S2 Coated Bearings

2011-01-14

Main Bearing in Threaded Housing on Shaft About to be Captured by Jaw Support Bearing on Naked Shaft

2011-01-14

Slide n° 8 / 37

slide-9
SLIDE 9

Remounting All Hardware onto Jaw Shafts for Last Tests Where We Are Free to Rotate Jaw as Much as Needed

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

2011-01-14 2011-01-14

Slide n° 9 / 37

slide-10
SLIDE 10

Final Version “Pawls” to Prevent Backlash

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

Underside w/Spring Visible L/R Symmetric Mo Housing

2011-01-27 2011-01-27 2011-01-27

Slide n° 10 / 37

slide-11
SLIDE 11

Assmann Visit 1 Feb 2011

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

2011-02- 01

Each Jaw Rotated 360 degrees (several times, facet by facet) to check that drive unit does not slip and that each of the 20 facets is perpendicular to beam gap after required number (8 x 48 = 384) of pushes against actuator

Slide n° 11 / 37

slide-12
SLIDE 12

RF Continuity Hardware

“Wiper” and BeCu Foil for RF Continuity between Jaws and Vacuum Tank

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

Rhodium Coated RF “Wiper” Thermistor Holder BeCu Foil Wiper/Foil Held to Rotating RF Bearing by Thermistor Holder

  • Unit Also

Controls Shape and Orientation

  • f Foil

2011-02-08 2011-02-08 2011-03-16 2011-03-16

Slide n° 12 / 37

slide-13
SLIDE 13

RF Continuity: R~1-2 mOhm

Checked for each facet of each side of both jaws

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

Example: 4-wire resistance=0.5mOhm

Slide n° 13 / 37

slide-14
SLIDE 14

Bending the Cooling Tubes

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

2011-03-03 2011-03-03

Slide n° 14 / 37

slide-15
SLIDE 15

Cooling Tubes Threaded through Feedthroughs in Plates Holding Jaw Supports at Bottom of Bellows

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

2011-03-07 2011-03-07

Slide n° 15 / 37

slide-16
SLIDE 16

Actuator Positioning Critical

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

2011-03-07 2011-03-07 2011-03-10

Slide n° 16 / 37

slide-17
SLIDE 17

Rotation Test 1 Successful

Tubes captured, Pre-weld of Internal Parts (13-Mar-2011) First Permanent “Twist” of Long Straight Length of Cooling Tubes

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

Before After

2011-03-10 2011-03-10 2011-03-10 2011-03-10

Slide n° 17 / 37

slide-18
SLIDE 18

Rotation Test 2 Successful

After Internal Parts Welded (16 Mar-2011)

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

Welds

Crack in Mo

Post Alignment Check as Before: Collimating Facets to beam

(required adjustment of switches as actuator moved in weld)

Slide n° 18 / 37

slide-19
SLIDE 19

Tank Installation and Alignment

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

2011-03-15 2011-03-16 2011-03-16

FARO arm Alignment

Slide n° 19 / 37

slide-20
SLIDE 20

Tank Seam Welded then Leak Tested

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

2011-03-22 2011-03-22 2011-03-22

Tubes sealing cooling tube feedthroughs to check vacuum quality of tank weld Leak Rate = 4.7E-10 mbar-l/s

Slide n° 20 / 37

slide-21
SLIDE 21

Copper Cooling Tubes Before and After TIG Braze to Copper Feedthrough

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

2011-03-29 2011-04-04

In principle, tank is now vacuum tight

Slide n° 21 / 37

slide-22
SLIDE 22

Immediate Check of Tank Vacuum on 2011-04-04 Indicates MASSIVE leak of cooling tubes to vacuum vessel

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

2011-04-08

Would be a “water-to-vacuum” leak if the lines had cooling water in them

Slide n° 22 / 37

slide-23
SLIDE 23

Each Jaw Is Damaged Very Near the End of the Jaw

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

2011-04-12 2011-04-12

Pour 60mL Alcohol Into Each Cooling Tube Find that it Drains Out Cracks at the Very End of Each Jaw To make a long story short, we find …

Slide n° 23 / 37

slide-24
SLIDE 24

Possible Leak Locations

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

Recall that Cooling Tube Enters from Opposite Side of Jaw then Begins its Spiral around the Mandrel Upbeam Side of RC0 Jaw Downbeam Side of RC1 Jaw

Slide n° 24 / 37

slide-25
SLIDE 25

Photos of Downbeam RC1 Location

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz Slide n° 25 / 37

slide-26
SLIDE 26

Boroscope Photo of DownBeam End of RC1

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz Slide n° 26 / 37

slide-27
SLIDE 27

Downbeam End of RC1

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

GRAVITY Liquid seems to be on inner surface of tube No “crack” or “hole” visible

Slide n° 27 / 37

slide-28
SLIDE 28

Upbeam end of RC0 Alcohol Accumulating on Tube from

  • ther end as it exits the rotation

bearing housing

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz Slide n° 28 / 37

slide-29
SLIDE 29

No Sign of Alcohol on Tube as it Enters Mandrel of RC0 nor on Long Runs of Tube in Center of the Mo Shaft

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz Slide n° 29 / 37

slide-30
SLIDE 30

When Cooling Tubes Capped and Tank Pumped Vacuum IS Good

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

Pressure: 1.9E-5 Torr (via Cold Cathode Gauge ) Leak rate: 5.9E-10 mbar-l/sec (on the Adixen ) Pressure rate of rise Leak rate of ~1E-4 torr/hour

Slide n° 30 / 37

slide-31
SLIDE 31

Rotation Test 3 Successful

Under Vacuum (18 Apr-2011)

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

RC0 Pawl

Crack in Mo Stable

Alignment Via Telescope and Scribed Lines RC1 Pawl Pawl Alignment Post Rotation Checked Via Boroscope (no slippage) Scribed Lines

2011-03-01

Slide n° 31 / 37

slide-32
SLIDE 32

Pressure and Leak Rate Good Enough to Begin Vacuum Bakeout of Vessel with Capped Cooling Coils 2011-04-29

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

T~240C and P=6.1E-7 at RGA Input on 2011-05-12

Slide n° 32 / 37

slide-33
SLIDE 33

I (we?) never anticipated that the cooling tubes might be subject to damage and I (we) believe that with the knowledge that they might be vulnerable this problem will not happen again. Speculation as to cause:

  • Copper grain boundary growth coupled with stress on material

could result in cracks at boundaries

  • Work hardening from bending
  • Damage from TIG welds/brazes

RC0 Jaw Material: SLAC in-stock magnet conductor

  • OFE 102 copper: 3/8” square with 3/16” hole w/ 6 braze cycles

RC1 Jaw Material: New order from Luvata, 101 OFE COPPER F68 Class 1, w/documentation

  • 10mm square w/ 7mm square hole; 3 braze cycles

Post Mortem has Begun, but No Conclusion

LARP CM16 - 17 May 2011 Slide n° 33 / 37 RC Status - T. Markiewicz

slide-34
SLIDE 34

Metallurgy: Samples to IMR Labs

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

“The samples conform to ASTM F68 Metallographic Class 4 for porosity resulting from oxygen contamination.” * Material purchased as Grade 1 OFE with test data sent by manufacturer “Large non-equiaxed grains consistent with hydrogen

annealed OFE copper. Porosity was rated per ASTM F 68 Plate 1. Porosity was observed within and across grains.

Slide n° 34 / 37

slide-35
SLIDE 35

Furnace Runs to try to Duplicate Problems

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

32# Tungsten Block to Provide Stress Bent & Straight Samples Straight Sample on Braze Oven Stand

Slide n° 35 / 37

slide-36
SLIDE 36

Sectioned Bends & SEM of Material Stressed by Bending

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

No Conclusions

Slide n° 36 / 37

slide-37
SLIDE 37

Prototype RC finished

  • Jaws cannot be cooled
  • Overall volume will soon pass SLAC/CERN vacuum requirements
  • In 2nd of ~3 week bake
  • All mechanical tests look good
  • Will need to do a last test rotation in vacuum after the bake

Plan: TBD

  • Preferred
  • Ship to CERN asap
  • Lab tests at CERN: Impedance, mechanical, vacuum, metrology
  • Install without cooling in SPS for operation & impedance tests
  • Install in HiRadMat test beam for destructive tests
  • But integrity of water circuit under shock untestable
  • Other choice: dissect & destroy at SLAC
  • More HW?: 2nd prototype, 2nd HiRadMat test device, different design,…

Status & Plan Going Forward

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz Slide n° 37 / 37

slide-38
SLIDE 38

Thermistor & Tank Rotation Hardware

LARP CM16 - 17 May 2011 RC Status - T. Markiewicz

2011-02-14 2011-02-14 2011-04-25

Slide n° 38 / 37