University of Michigan Founded: 1817 Ann Arbor Campus Number of Buildings: ~750 Campus Size: ~3200 acres Gross Sq Ft: ~40M Ray Garrett Senior Manager Utilities Records Integration (URI) Department With UM since 2006 6 FTEs in URI, 2 shared


slide-1
SLIDE 1

UNIVERSITY OF MICHIGAN Ray Garrett Senior Manager Utilities Records Integration (URI) Department With UM since 2006 6 FTEs in URI, 2 shared support

University of Michigan Founded: 1817 Ann Arbor Campus Number of Buildings: ~750 Campus Size: ~3200 acres Gross Sq Ft: ~40M

slide-2
SLIDE 2

UNIVERSITY OF MICHIGAN 300+ miles of underground services

Utilities Department Power Plant Medium Voltage Low Voltage Water Sanitary Storm Chilled Water Tunnels Steam Condensate Compressed Air DWS & DWR

Other Departments Fiber Fire Service

slide-3
SLIDE 3

Utilities Records Integration (URI)

Mapping Electrical Documentation FMS Web Miss Dig Administration Distribution Management System

slide-4
SLIDE 4

UNIVERSITY OF MICHIGAN

How do you start a Utility GIS System?

Determine the benefits Management’s Commitment Authoritative Data Source Implementation Plan

Involve the trades! Maintenance Plan Involve the trades!

slide-5
SLIDE 5

UNIVERSITY OF MICHIGAN

Benefits

Single source of truth – Authoritative data source

Reduction in documentation costs by elimination of duplicate systems

Data Federation Consolidation of institutional knowledge Better Panning Lower Miss Dig costs

Fewer Miss Dig hits

Consistent & wider distribution of knowledge

slide-6
SLIDE 6

GIS Organizational Structure

AEC URI- Utilities ITcomm - Fiber OSEH-EP3 AEC-REO

De partme nt GI S Staff GI S De partme nt/GI S Co o rdinato r

Grounds Building Services Fire Safety PTS

slide-7
SLIDE 7

UNIVERSITY OF MICHIGAN GIS Standards Committee Talk with the Shops and Trades Jumpstart with Total Station locations of Water/Sanitary/Storm Transfer Electrical from CAD Involve the Trades for data correction 80/20 rule

Implementation Plan

slide-8
SLIDE 8

UNIVERSITY OF MICHIGAN

Resolved duplication of efforts Security Coordination Data Federation

Data interchange guidelines Established Spatial Reference

Meta data guidelines Resolution of differences Exchange of ideas

Implementation Plan

GIS Standards Committee

slide-9
SLIDE 9

UNIVERSITY OF MICHIGAN

Find out what would truly save the trades time and money Solicit their help in correcting the data Assure them that we are not going to take any paper away Borrow and return redlines stashed in trucks and shop Meet with them regularly

Implementation Plan

Talk with the Shops and Trades

Only promise what you can do and do what you say

Deliver results that benefit the trades

slide-10
SLIDE 10

UNIVERSITY OF MICHIGAN

Implementation Plan

slide-11
SLIDE 11

UNIVERSITY OF MICHIGAN

Routinely solicit feedback on correcting the data Help them in a timely manner If you are unable to implement a suggestion or update in a timely manner let them know a realistic time frame

Maintenance Plan

Talk with the Shops and Trades

Updates should be timely and routine Plan for measured growth

slide-12
SLIDE 12

UNIVERSITY OF MICHIGAN

How do you get the information to the end user?

Paper – 2% ArcMap -2% Web – 98%

slide-13
SLIDE 13

URI GIS Website

Responsive Design Multi-Platform Desktop/Laptop

Windows, Mac

Mobile

iOS 8+, Android 4.4+ MS Surface

UNIVERSITY OF MICHIGAN

slide-14
SLIDE 14

UNIVERSITY OF MICHIGAN

Web Technologies

HTML, CSS, JavaScript

ESRI ArcGIS API for JavaScript, Dojo Toolkit Backbone.js, Marionette.js, Underscore.js Bootstrap, JQuery

ESRI ArcGIS for Server ASP.NET WebAPI

slide-15
SLIDE 15

UNIVERSITY OF MICHIGAN

Website Demonstration

slide-16
SLIDE 16

UNIVERSITY OF MICHIGAN

Other areas we are working on

slide-17
SLIDE 17

UNIVERSITY OF MICHIGAN

ArcFM ArcMap GIS to DMS

slide-18
SLIDE 18

DSM

UNIVERSITY OF MICHIGAN

slide-19
SLIDE 19

IR

UNIVERSITY OF MICHIGAN

slide-20
SLIDE 20

IR

UNIVERSITY OF MICHIGAN

slide-21
SLIDE 21

UNIVERSITY OF MICHIGAN

High Quality Aerials

slide-22
SLIDE 22

CityEngine Campus

Why 3D? To accurately represent:

Buried Utilities Tunnels Building Light Locations

Help with Miss Dig Help with project planning Reduce Engineering Costs BIM Integration

Join us Friday August 14, 2015 9:45am at the CFTA annual conference hosted at Michigan State University, East Lansing, MI

slide-23
SLIDE 23

Tunnels

Join us Thursday August 13, 2015 9:30 am at the CFTA annual conference hosted at Michigan State University, East Lansing, MI

Point cloud to BIM to GIS BIM to AiM (CMMS)

slide-24
SLIDE 24

UNIVERSITY OF MICHIGAN

CFTA 2015 Silver Anniversary Conference @ Michigan State University in East Lansing, Michigan August 11-14

Registration @ http://www.cfta.org/

slide-25
SLIDE 25

UNIVERSITY OF MICHIGAN

Questions?