QUALITY ASSURANCE FOR RT EQUIPMENT Samuel Tung, M.S. Sr. Medical - - PowerPoint PPT Presentation

quality assurance for rt equipment
SMART_READER_LITE
LIVE PREVIEW

QUALITY ASSURANCE FOR RT EQUIPMENT Samuel Tung, M.S. Sr. Medical - - PowerPoint PPT Presentation

QUALITY ASSURANCE FOR RT EQUIPMENT Samuel Tung, M.S. Sr. Medical Physicist UT MD Anderson Cancer Center Objective: To familiarize the student with the need and the concept of a quality assurance program in radiotherapy as well as with


slide-1
SLIDE 1

QUALITY ASSURANCE FOR RT EQUIPMENT

Samuel Tung, M.S.

  • Sr. Medical Physicist

UT MD Anderson Cancer Center

slide-2
SLIDE 2

Objective:

To familiarize the student with the need and the concept of a quality assurance program in radiotherapy as well as with recommended quality procedures and tests.

slide-3
SLIDE 3
slide-4
SLIDE 4
slide-5
SLIDE 5
slide-6
SLIDE 6

12.3 QUALITY ASSURANCE PROGRAMME FOR RADIATION TREATMENT EQUIPMENT

slide-7
SLIDE 7

The Structure of an Equipment QA Program

(1) Initial specification, acceptance testing and commissioning (2) Quality control tests (3) Additional quality control tests (4) Planned preventive maintenance program

slide-8
SLIDE 8

The Structure of an Equipment QA Program

(1) Initial specification, acceptance

testing and commissioning ü Specification to meet clinical needs ü Site visit ü Acceptance Testing to meet specs ü Commissioning for clinical use

slide-9
SLIDE 9

Equipment Specification

— In preparation for procurement of

equipment, a detailed specification document must be prepared.

— A multidisciplinary team from the

department should be involved.

— This should set out the essential aspects

  • f the equipment operation, facilities,

performance, service, etc., as required by the department.

slide-10
SLIDE 10

Questions Related to Clinical Needs

— Which patients will be affected by this technology? — What is the likely number of patients per year? — Number of procedures or fractions per year? — Will the new procedure provide cost savings over

  • ld techniques?

— Would it be better to refer patients to a specialist

institution?

— Is the infrastructure available to handle the

technology?

— Will the technology enhance the academic

program?

— What is the organizational risk in implementation

  • f this technology?

— What is the cost impact? — What maintenance is required?

slide-11
SLIDE 11

Equipment Specification and Clinical Needs Assessment

Ø Once this information is compiled, the

purchaser is in a good position to clearly develop his own specifications.

Ø Specification can also be based on:

  • Manufacturer’s specification (brochures)
  • Published information
  • Discussions with other users

Ø Specification data must be expressed in

measurable units.

Ø Decisions on procurement should again be

made by a multidisciplinary team.

slide-12
SLIDE 12

Acceptance Testing

— Acceptance of equipment is the process in

which the supplier demonstrates the baseline performance of the equipment to the satisfaction of the customer.

— After the new equipment is installed, the

equipment must be tested in order to ensure, that it meets the specifications and that the environment is free of radiation and electrical hazards to staff and patients.

— Essential performance required and expected

from the machine should be agreed upon before acceptance of the equipment begins.

slide-13
SLIDE 13

Acceptance Testing

— It is a matter of the professional judgment of

the responsible medical physicist to decide whether any aspect of the agreed acceptance criteria is to be waived.

— This waiver should be recorded along with an

agreement from the supplier, for example, to correct the equipment should performance deteriorate further.

— Equipment can only be formally accepted to be

transferred from the supplier to the customer when the responsible medical physicist either is satisfied that the performance of the machine fulfills all specifications as listed in the contract document or formally accepts any waivers.

slide-14
SLIDE 14

Commissioning

— Commissioning is the process of preparing

the equipment for clinical service.

— Expressed in a more quantitative way: A full

characterization of its performance over the whole range of possible operation must be undertaken.

— In this way the baseline standards of

performance are established to which all future performance and quality control tests will be referred.

— Commissioning includes preparation of

procedures, protocols, instructions, data book, etc., on the clinical use of the equipment.

slide-15
SLIDE 15
slide-16
SLIDE 16
slide-17
SLIDE 17
slide-18
SLIDE 18
slide-19
SLIDE 19

The Structure of an Equipment QA Program

(2) Quality control tests ü Establish QC program ü Establish QC tests ü Set up baselines ü Determine acceptable/action level

slide-20
SLIDE 20

Quality Control Program

— Equipment quality control program should

specify the following:

Ø Parameters to be tested and the tests to be performed Ø Specific equipment to be used Ø Geometry of the tests Ø Frequency of the tests Ø Staff group or individual performing the tests Ø The individual supervising and responsible for the standards of the tests and for actions that may be necessary if problems are identified.

slide-21
SLIDE 21

Quality Control Program

— Daily/Weekly Checks:

  • Usually done by RTTs, including the machine

warm up procedures, simple output and mechanical checks, plus safety checks.

  • Results verified by physics

— Monthly Checks:

  • Usually done by physics staff, standardized

dosimetry and mechanical tests

— Annual Calibration:

  • Usually done by QMP, including the absolute

dose calibration for every beams.

slide-22
SLIDE 22

Quality Control Program

— Consistency Check: It is essential that the

performance of treatment equipment remain consistent within accepted tolerances throughout its clinical life

— Prior to Clinical Use: Ongoing quality

control program of regular performance checks must begin immediately after acceptance/commissioning

— Monitor the Change: If these quality

control measurements identify departures from expected performance, corrective actions are required.

slide-23
SLIDE 23

Consistency Output Check Versa2 Prior to Clinical Use

slide-24
SLIDE 24

Quality Control Program

— Equipment quality control program should

specify the following:

Ø Expected results Ø Tolerance and action levels Ø Actions required when the tolerance levels are exceeded

— Actions required must be based on a

systematic analysis of the uncertainties involved and on well defined tolerance and action levels.

slide-25
SLIDE 25

Corrective Actions

Role of Uncertainty: Ø When reporting the result, it is obligatory that some quantitative indication of the quality of the result be given. Ø Otherwise whoever receives this QC report cannot really asses its reliability. Ø Concept of measurement uncertainty has been introduced. Ø In 1993, ISO has published a “Guide to the expression of uncertainty in measurement”

slide-26
SLIDE 26

Corrective Actions

Role of Tolerance Level: Ø Within the tolerance level, the performance of an equipment gives acceptable accuracy in any situation. Ø Tolerance values should be set with the aim of achieving the overall uncertainties desired. Ø However, if the measurement uncertainty is greater than the tolerance level set, then random variations in the measurement will lead to unnecessary intervention Ø Therefore, it is practical to set a tolerance level at the measurement uncertainty at the 95% confidence level

slide-27
SLIDE 27

Corrective Actions

Role of Action Level: Ø Performance outside the action level is considered unacceptable and demands action to remedy the situation. Ø It is useful to set action levels higher than tolerance levels thus providing flexibility in monitoring and adjustment. Ø Action levels are often set at approximately twice the tolerance level. Ø However, some critical parameters may require tolerance and action levels to be set much closer to each other or even at the same value.

slide-28
SLIDE 28
slide-29
SLIDE 29

System of Actions

— If a measurement result is within the

tolerance level, no action is required.

— If the measurement result exceeds the

action level, immediate action is necessary and the equipment must not be clinically used until the problem is corrected

— If the measurement falls between tolerance

and action levels, this may be considered as currently acceptable. But, the physicist review and repeated measurements are required.

slide-30
SLIDE 30

MDACC RT-250 Unit Control Console

slide-31
SLIDE 31

MDACC RT-250 Unit

slide-32
SLIDE 32

New Jig for RT-250 Monthly

slide-33
SLIDE 33
slide-34
SLIDE 34
slide-35
SLIDE 35

Possible Output Drift?

slide-36
SLIDE 36

MDACC Co-A Control

slide-37
SLIDE 37
slide-38
SLIDE 38

CoA Monthly Check Summary

slide-39
SLIDE 39

CoA Monthly Output Check

slide-40
SLIDE 40

Co Unit Annual Tests

slide-41
SLIDE 41

Co Unit Annual Tests

slide-42
SLIDE 42

Co Unit Annual Tests

slide-43
SLIDE 43

LINAC Daily Tests (RTT)

AAPM Task Group 142

slide-44
SLIDE 44

LINAC Monthly Tests (Physics)

AAPM Task Group 142

slide-45
SLIDE 45

LINAC Monthly Tests (Physics)

AAPM Task Group 142

slide-46
SLIDE 46

LINAC Monthly Tests (Physics)

AAPM Task Group 142

slide-47
SLIDE 47

MDACC LINAC QC Form

slide-48
SLIDE 48

Action Level

slide-49
SLIDE 49

OBI Monthly Tests (Partial List)

slide-50
SLIDE 50

The Structure of an Equipment QA Program

(3) Additional quality control tests ü After significant repair ü After major parts replacement ü After significant adjustment ü After adding new procedures ü Indication of a change of performance

slide-51
SLIDE 51
slide-52
SLIDE 52

The Structure of an Equipment QA Program

(4) Planned preventive maintenance program ü To prevent from major problem ü Quarterly PM is reasonable ü In accordance with the manufacture’s recommendations ü Regulatory Requirements

slide-53
SLIDE 53
slide-54
SLIDE 54

Summary: The Structure of an Equipment QA Program

(1) Initial specification, acceptance testing and commissioning (2) Quality control tests (3) Additional quality control tests (4) Planned preventive maintenance program

slide-55
SLIDE 55

Summary: Task Group 142

— It is recommended that a departmental

QA team be formed to support all the QA activities and draft necessary policies and

  • procedures. The policy should establish

the roles and responsibilities of involved QA personnel.

slide-56
SLIDE 56

Summary: Task Group 142

— The first step is to establish institution-

specific baseline and absolute reference values for all QA measurements. The results should be reviewed regularly to

  • Ensure the consistency of machine performance
  • Determine any significant trend of dose

deviations from the base line.

slide-57
SLIDE 57

Summary: Task Group 142

— A QMP should lead the QA team. — In general, the daily QA tasks may be carried

  • ut by a radiation therapist using a cross-

calibrated dosimetry system.

— Monthly QA tasks should be performed by a

QMP or by individuals directly supervised by a QMP.

— The annual QA items in the report represent

the most extensive tests on the machine

  • performance. it is recommended that the

annual measurements be performed by a QMP with involvement of other QA team members.

slide-58
SLIDE 58

Summary: Task Group 142

— An end-to-end system check is

recommended to ensure the fidelity of

  • verall system delivery whenever a new
  • r revised procedure is introduced

— During the annual QA review, absolute

machine output should be calibrated as per the TG51 calibration protocol using ionization chamber with a NIST traceable calibration