QA, QC, Test plan
- F. Pietropaolo
QA, QC, Test plan F. Pietropaolo CERN / INFN Padova Quality - - PowerPoint PPT Presentation
QA, QC, Test plan F. Pietropaolo CERN / INFN Padova Quality Assurance / Quality control The Quality Assurance (QA) plan is as set of acAviAes for ensuring quality in the process by which products are fabricated and assembled. The quality
2
structure
the TPC
– ResisAve material electrical tests
– Electrode material test
3
– Intrinsic bulk resisAvity in the required range (few MOhm/cm) – Density comparable to LAr
– resisAve ink (~100kOhm/square) printed with specific pa`erns; – laminated resisAve kapton foil Dupont 100XC10E7 (25 µm thickness, graphite loaded, available with resisAvity in the 0.5 to 50 MOhm/square range available in 1.2 m wide rolls)
be`er aging to sparks, high stability in LAr (~50% increase in resiAvity, no planarity deformaAon)
– Graphite loaded (outer layers) FR4 – Thin films of Germanium Coated Polyimide (vacuum deposited)
4
resisAve thick-GEM’s (max 0.6x0.7 mq)
– Stack of FR4 panel + 75 um prepreg + 25 um Kapton foil placed in between metallic sheets and unmoulding foils – Press cycle at 20 Kg/cm2 for about 1 hour at 160-200°C – Press available (Italy, Japan) for dimensions amply larger that 1.2 m x 2.4 m – LaminaAon on both sides of FR4 also possible
x 0.7 mq ( 3mm FR4 thickness)
square in present sample)
thermal cycle from room to LAr temperatures to check stability against delaminaAon performed posiAvely.
5
machines as cathode plane for the 50-liter LAr-TPC available at CERN.
– already operated several Ames in various test runs, with behavior completely equivalent to that of the metallic planes in term of mechanical stability, electric field uniformity and LAr purity.
prototype panel (double sided) following the CERN fabricaAon procedure.
– machined by them into smaller elements to be installed in the 35 ton HV test at FNAL.
field uniformity around the CPA frame will
– Being these elements much smaller with respect to the CPA panels and requiring in addiAon more precise machining and hole drilling, they could be fabricated at CERN. – A first set has been already produced for the 35 ton HV test at FNAL.
6
1.1 m height; ~300 liters total volume)
– Choice of metal (Al, SS) and surface finish
bias voltage required: to reach design E field ~ 60 kV are needed
(based ICARUS scheme)
from arching/discharges and monitor LAr thermal stability (LED illuminated)
up the 100 KV if thermally stable (no bubbles)
finish (roll formed vs extruded) surface quality (up to 100 um scratches)
7
– A new field cage of 50 liter LAr-TPC has been built. – 50 rings made of uncoated extruded 10x10 mm2 aluminum bars with rounded outer corners (4 mm radius) – Spaced by 10 mm – Coupled with resisAve cathode – Minimum distance of rings from detector vessel wall: 5cm – Max local e-field at ring surface ~ 26 kV/cm (for Vcath=-25 kV, 500 V/cm driu field) similar to ProtoDUNE SP case
verify HV stability, electronic noise on wires, possible producAon of UV light
8
Long term operaAon (several weeks) maybe required to measure charging up effects due to cosmic rays
– OpAmizaAon of sAffened aluminum extruded profiles; mechanical properAes verified (with FEA calculaAon) at CERN. – Same outer shape as roll formed profiles, compaAble with standard locking nuts and tooling for mounAng – ProducAon of prototypes started at selected producers (ALEXIA-Italy, MIFA-Netherland) with different aluminum alloy and with conducAve coaAng (at some cost increase). – Prototypes (1.5 m long) verified at CERN. – First 100 m available on 11/15th (sufficient for second phase of the 35 ton HV test): 50m with conducAve coaAng (SURTEC). – Full producAon (~3km) for ProtoDune SP available in few weeks Ame – Cost ~ 1 to 2 Euro/m
and extruded aluminum profiles; final choice can be made at very last moment
9
10
– FR4 Frames completed with FR4 panels
– 2 Panels with latest design (No splice joint and latest modificaAons) – 2 panels older version with stainless hardware just for mockup.
– Top panel with hangers – Panel with beam plug mockup. – 2 Regular End wall panels.
missing ground planes (replaced by plywood) .
11
Phase 1 of the ProtoDUNE Trial Assembly
12
– Follow/contribute to ConstrucAon and tests in collaboraAon with the DP ETH/CERN group.
– Tested ability to hold voltage at full scale; – Tested expected current and stability of current at all monitoring points; – Tested mechanical integrity of all components auer full cool-down, warm-up cycle; – Tested discharge miAgaAon system using induced HV discharge.
13
from a high voltage perspecAve
completely understood
voltage of the experiment
14
not fit in the cryostat
FC and a resisAve cathode at their planned voltages.
– High field areas à corners near cathode – New aspects of the design: FC profiles and FRP beams, resisAve plate cathode, ground planes, – However: dedicated HV feed through (UCLA)
– Do the pieces of the design work together?
From
Cathode Resistor to ground Rela:ve Anode Poten:al (kV)
1.5m 1.5m
15
– Design, fabricaAon, delivery of components to William & Mary
– Clean and preassemble parts – Parts delivery to Fermilab
2016)
– Test installed in cryostat – Purge, cool down, fill the cryostat
Assembled CPA
16
has beam plug a`ached
GOALS:
interfere with the operaAons
performance with and without the beam plug)
extruded Aluminum vs SS
17
18
19
– HV bus cables – Inter-CPA "pigtails" with lug connectors – ConnecAon points on CPAs, with capAve screws – Resistor-to-frame and frame-to-FC connectors
20
21
– Measure voltage drop for each individual stage – Convert to current – calculate equivalent resistance RA
HV power supply: used at 1000 V 100kΩ pick-off resistor
22
à Can stack up to 5 PCBs high à Can have 2 stacks on mechanical mount à 16 MOVs per board à Can test up to 160 MOVs per cool down cycle ParAally populated test stand Use very similar setup to test resistors (based on same PCB) àcan test up to 80 resistors per cool down cycle Components are individually bagged and serialized
23
Top and bo`om panels auer they are assembled with ground plane is 200kg if SS profiles are used and 150kgs if Al profiles are used.
bagged before puyng inside the shipping box.
analysis will be provided to CERN beforehand. FC should be handled in accordance with that document at all Ames.
assembly and was approved. It will be included in each shipping box with individual panels. These documents will also be uploaded on EDMS or docdb as required by the project.
will be coordinated with CERN.
24
will be performed.
inspected for scratches or delaminaAon; resisAvity is sampled on panel surfaces
and in case of any dents and scratches the profiles will be replaced.
checked using a calibrated torque screw
a low torque spec and can become loose due to vibraAons during shipping. ReAghtening of screws may be required.
adjacent field cage profiles (r. divider).
25
adequate to host FC panels and to mount a full CPA column
with surrounding space sufficient to replace the 2.3 m long profile
measurements (and/or reparing) of FC resistor divider and CPA HV bus
for temporary verAcal storage of several bagged FC panels (visual inspecAon)
26
1. When unpacking the crates in the cleanroom each component is scanned in so the part number is recorded and the proper QC form comes is filled out. A carefully visual inspecAon, conAnuity of all electrical connecAons are confirmed and documented the form. This is then recorded in the hardware database. 2. Once the CPA, FC or EW construcAon is completed in the cleanroom a QC form is completed online to record that all visual conAnuity tests are done properly and the values are saved. 3. Once the final cable connecAons to the feed-through is made inside the cryostat they are checked again before the access scaffold is removed.
27
– Is the CPA/FC/HV quality assurance, quality control and test plan adequate and implemented into the QA plan?
execute this plan, and working to complete the documentaAon
at CERN, installaAon and commissioning are being defined to allow for successful operaAon of protoDUNE
ProducAon Readiness Review – Have applicable lessons-learned from previous LAr-TPC devices been documented?
incorporated whenever possible (HV feed-through, ground planes)
be finalized in Ame for a ProducAon Readiness Review – Does the plan appropriately account for CPA/FC/HV produc:on at mul:ple interna:onal sites with different standards (metric/imperial) for available stock materials?
experience, laboratory equipment and manpower of the parAcipaAng insAtuAons
28