Pryor Mountain Wind Project September 4, 2019 PacifiCorp Overview - - PowerPoint PPT Presentation

pryor mountain wind project
SMART_READER_LITE
LIVE PREVIEW

Pryor Mountain Wind Project September 4, 2019 PacifiCorp Overview - - PowerPoint PPT Presentation

Pryor Mountain Wind Project September 4, 2019 PacifiCorp Overview Two divisions Rocky Mountain Power and Pacific Power 5,600 Employees 1.9 million electricity customers 141,000 square miles of service territory in six


slide-1
SLIDE 1

Pryor Mountain Wind Project

September 4, 2019

slide-2
SLIDE 2

PacifiCorp Overview

  • Two divisions – Rocky Mountain

Power and Pacific Power

  • 5,600 Employees
  • 1.9 million electricity customers
  • 141,000 square miles of service

territory in six states

  • 17,457 miles of transmission
  • 10,887 MW owned generation

capacity

slide-3
SLIDE 3

PacifiCorp Wind Resources

  • 1,040 MW of wind owned by

PacifiCorp

  • 1,190 MW to be added in 2020
  • Total of 2,220 MW owned
  • 1,000 MW of wind under PPA

contracts

  • 320 MW to be added in 2020
  • Total of 1,320 MW of power

purchase contracts

slide-4
SLIDE 4

Rocky Mountain Power Utah Statistics:

  • 892,849 customers
  • 1,928 employees
  • State property taxes:

$73.1 million

slide-5
SLIDE 5

This information is based on Federal Energy Regulatory Commission Form 1 data. The Rocky Mountain Power “basic fuel mix” is based on energy production and not resource capability, capacity or delivered energy. All or some of the renewable energy attributes associated with wind, solar,biomass, geothermal and qualifying hydro facilities in Rocky Mountain Power’s fuel mix may be: (a) used to comply with renewable portfolio standards or other regulatory requirements, (b) sold to third parties in the form of renewable energy credits and/or other environmental commodities or (c)not acquired. Rocky Mountain Power’s basic fuel mix includes owned resources and purchases from third par ties.

56.39% 15.44% 5.15% 8.80% 3.79% 9.75%

Rocky Mountain Power 2018 Fuel Mix*

Coal Natural Gas Hydroelectric Wind Biomass Geothermal Solar Other/misc

slide-6
SLIDE 6

U.S. Average

0.00 5.00 10.00 15.00 20.00 25.00 30.00

Louisiana Texas Oklahoma Wyoming Tennessee ROCKY MOUNTAIN POWER Arkansas Idaho North Carolina Utah Iowa Mississippi Virginia Kentucky West Virginia North Dakota Georgia South Carolina Nevada New Mexico Missouri Indiana PACIFIC POWER Oregon Colorado Montana Minnesota Ohio Washington Alabama Florida South Dakota Pennsylvania Kansas U.S.A. Wisconsin Illinois Michigan Delaware Arizona District of Columbia Maryland Vermont New Jersey Maine California Rhode Island New York New Hampshire Connecticut Massachusetts Hawaii

Average Rate (¢/kWh)

Average Electricity Price by State

Source: Edison Electric Institute Sales and Revenue Data for the 12 months ending December 2017

RMP

slide-7
SLIDE 7

Production Tax Credits

  • Wind projects that are

completed in 2020 and meet certain qualifications can receive federal tax credits (currently $24/MWh) for their electric production

  • ver the first 10 years of
  • peration.
slide-8
SLIDE 8

Photo Credit Motah on unsplash

slide-9
SLIDE 9

Pryor Mountain

  • Multiple developers between

2009 and 2019

  • Some permits issued in 2014
  • PacifiCorp purchased the

project in May 2019

  • 240 MW project size
  • Interconnect with an existing

230 kV transmission line owned by PacifiCorp

slide-10
SLIDE 10

Wind Turbine Generators (WTG)

  • 114 WTGs
  • 57 Vestas V110-2.0 B
  • 21 Vestas V110-2.2 C
  • 32 Vestas V110-2.2 D
  • 4 GE 2.3-116
  • 80 meter hub height
  • 54 to 58 meter blade length
slide-11
SLIDE 11
slide-12
SLIDE 12

Annual Electric Production

  • 2.2 MW WTG with a 40% net

capacity factor (NCF) will produce 7,709 MWh/year

  • 240 MW wind project with a

40% NCF will produce 841,000 MWh/year

  • Average household in the US

uses 11 MWh/year (US DOE)

  • 240 MW wind project with a

40% NCF can power over 76,000 US households on an annual basis

slide-13
SLIDE 13

Construction Schedule

  • Fall 2019 - Roads and

Foundations

  • Spring 2020 - Foundations

and Collector Substation

  • Summer 2020 - Turbine

Erection and POI Substation

  • Fall 2020 - Commissioning
  • Dec 15, 2020 - Commercial

Operation Date

slide-14
SLIDE 14

Construction Impacts

  • 10 truckloads of

equipment for each WTG

  • 1,140 truckloads of

WTG equipment for the project

  • Delivery schedule is

10 WTGs per week

  • 100 trucks per week

for WTG equipment

slide-15
SLIDE 15

Construction Employment

  • Maximum of

300 workers on site at any one time

  • Peak number of

workers on site anticipated to

  • ccur in July

and August of 2020

slide-16
SLIDE 16

Operations

  • Project is expected to

have a 30 year life

  • Full time employment
  • 1 Site manager
  • 10 to 12 wind

technicians

  • Normal working hours

are Monday to Friday 7:00 am to 4:00 pm

  • Site monitored remotely

24/7

slide-17
SLIDE 17

Questions?