PROVISIONS AGAINST THERMAL AND DRYING SHRINKAGE CRACKING IN - - PowerPoint PPT Presentation

provisions against thermal and drying shrinkage cracking
SMART_READER_LITE
LIVE PREVIEW

PROVISIONS AGAINST THERMAL AND DRYING SHRINKAGE CRACKING IN - - PowerPoint PPT Presentation

PROVISIONS AGAINST THERMAL AND DRYING SHRINKAGE CRACKING IN CONSTRUCTION OF PRESTRESSED CONCRETE BRIDGE K. Koroyasu Shimizu Corporation, JAPAN N. Kiyotaka Shimizu Corporation, JAPAN S. Nojima Central Nippon Expressway, JAPAN JCI-RILEM


slide-1
SLIDE 1

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

1

PROVISIONS AGAINST THERMAL AND DRYING SHRINKAGE CRACKING IN CONSTRUCTION OF PRESTRESSED CONCRETE BRIDGE

  • K. Koroyasu
  • N. Kiyotaka
  • S. Nojima

Shimizu Corporation, JAPAN Shimizu Corporation, JAPAN Central Nippon Expressway, JAPAN

slide-2
SLIDE 2

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

2

AGENDA 1.Introduction & Summary of Construction 2.Provisions for Thermal Cracking

3.( Provisions for Drying Shrinkage Cracking )

4.Conclusions

slide-3
SLIDE 3

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

3

Prestressed concrete bridge

In winter, the lowest temperature < 0° C During the in-service period, the de-icing agent is planed to be used. If the concrete structure has some cracks, the accelerated concrete deterioration becomes an issue. Technical challenges was to control the early age cracking.

Introduction & Summary of Construction

slide-4
SLIDE 4

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

4

Construction Outline

[Unit: m]

Type: 5 and 9 span of continuous PC box-girder bridges Erection method: Cantilever, Fixed falsework

Introduction & Summary of Construction

slide-5
SLIDE 5

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

5 Side Closure 6.473 Cantilever 35.000 Column Carital 12.000 Cantilever 35.000 Closure 2.962 3.500

Cantilever Erection

Typical longitudinal section Typical cross sections

2.025 2.325 3.050 2.850 5.500 10.250 10.250 2.225 2.325 2.850 2.850

In the Spans

Introduction & Summary of Construction

Column Capital

slide-6
SLIDE 6

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

6

Introduction & Summary of Construction This report explains the controlling methods

  • f the early age cracking that had been

adopted for the bridge construction of the cantilever erection.

Contents of this report The early age cracking: Thermal cracking ( and Drying shrinkage cracking )

slide-7
SLIDE 7

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

7

Requirements and Constraints Targets of Thermal Crack Control (Minimum Limit Values of Thermal Cracking Index) 3D-FE Analysis for Initial Construction Verification (Satisfy the Limit Values?) Yes Consideration of Additional Provisions No Standard Construction Methods and Material

Construction

First

Provisions for Thermal Cracking

Objective

Flow diagram of verification (Ordinary) Additional verification

slide-8
SLIDE 8

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

8

Verification (Satisfy the Limit Values?) Yes Consideration of Additional Provisions Confirmation of Each Matter Value for Property No First Construction Thermal Fitting Analysis 3D-FE Analysis for the Following Constructions Verification (Satisfy the Limit Values?) Yes Consideration of Additional Provisions No Remaining Constructions to Follow Measurement of Concrete Temperature

Provisions for Thermal Cracking

Objective

Flow diagram of verification (This Construction) Additional verification

slide-9
SLIDE 9

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

9

Objective

Provisions for Thermal Cracking

Part Minimum limit values of cracking index Rough indication of cracking index in [1] Upper slab, Bridge end 1.75 When thermal cracking is required to be prevented (Thermal cracking probability: 5%) Under slab, Web 1.45 When thermal cracking is required to be limited as much as possible (Thermal cracking probability: 25%)

Target values of thermal cracking index

[1]: Standard Specification for Concrete Structures -2007

slide-10
SLIDE 10

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

10

Part Change of cement type Expansive additive Insulated curing Concrete cooling Column capital 1st lift ○ ○ ○ 2nd lift ○ ○ Cantilever ○ ○ Closure ○ ○ ○ Side closure 1st lift ○ ○ 2nd lift ○ ○ ○

List of provisions against thermal cracking

Provisions for Thermal Cracking

Objective

slide-11
SLIDE 11

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

11

Provisions for Thermal Cracking

Part Original cement type Modification Column capital HPC*1 MPC*2 Cantilever HPC*1 OPC*3 Closure HPC*1 OPC*3+EX*4 Side closure 1st lift HPC*1 OPC*3 2nd lift HPC*1 OPC*3+EX*4 *1: High-early-strength Portland Cement (HPC) *2: Moderate-heat Portland Cement (MPC) *3: Ordinary Portland Cement (OPC) *4: Expansive Additive (EX)

Different types of binders for each part Cement type and Expansive additive

slide-12
SLIDE 12

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

12

Provisions for Thermal Cracking

Part Method of curing Period Bridge face (In the spans) Wet mat and Insulated mat From casting to the assurance age of strength Bridge face (On the piers) Wet mat and Insulated mat From casting to the assurance age of strength (The time when the insulated mat was installed after the temperature inside the concrete reached the peak)

Types of insulated curing Insulated curing

slide-13
SLIDE 13

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

13

Provisions for Thermal Cracking

Cooling concrete < Cooling concrete with liquid nitrogen >

Agitator–body Truck Tank lorry with liquid nitrogen Jet nozzle Scaffolding for jet

slide-14
SLIDE 14

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

14

Provisions for Thermal Cracking

Part Maximum limit concrete temperature at the casting Management temperature after injection 1st lift 30°C 29°C 2nd lift 26°C 25°C

Management temperature of cooling < Cooling concrete with liquid nitrogen > Cooling concrete Quantity of LN2 necessary to reduce concrete of 1m3 by 1 ° C was 14.9 kg/m3° C

slide-15
SLIDE 15

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

15

Fan Duct Deflection tube Branched duct

Provisions for Thermal Cracking

< Air-cooling with the use of deflection tube > Cooling concrete

slide-16
SLIDE 16

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

16

Case Conditions of analysis model 1 Standard construction only with OPC 2 Case 1 with MPC 3 Case 2 with insulated curing 4 Case 3 with cooling with LN2 and air-cooling

Provisions for Thermal Cracking

Effect of provisions

Cases of 3D-FE analysis in advance for the column capital part

slide-17
SLIDE 17

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

17

Provisions for Thermal Cracking

Effect of provisions

< Case 1 > < Case 2 >

Standard construction

  • nly with OPC

Case 1 with MPC

Target values 2nd lift : 1.75 1st lift : 1.45

slide-18
SLIDE 18

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

18

Provisions for Thermal Cracking

Effect of provisions

< Case 3 > < Case 4 >

Case 2 with insulated curing Case 3 with LN2-cooling and air-cooling

Target values 2nd lift : 1.75 1st lift : 1.45

slide-19
SLIDE 19

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

19

Provisions for Thermal Cracking

Effect of provisions

Result of thermal analysis (Case 4)

Yes First Construction Thermal Fitting Analysis Yes No Remaining Constructions to Follow Confirmation of Each Matter Value for Property Measurement of Concrete Temperature No 3D-FE Analysis for Initial Construction Verification (Satisfy the Limit Values?) Consideration of Additional Provisions Consideration of Additional Provisions Verification (Satisfy the Limit Values?) 3D-FE Analysis for the Remaining Constructions to Follow

: Measurement point

slide-20
SLIDE 20

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

20

10 20 30 40 50 60 70 1 2 3 4 Tempreature inside concrete(℃) (Day) Prior analysis Measured value Fitting analysis 10 20 30 40 50 60 70 1 2 3 4 Tempreature inside concrete(℃) (Day) Prior analysis Measured value Fitting analysis

Provisions for Thermal Cracking

Effect of provisions

< Effect of cooling with LN2 > < Effect of air-cooling >

slide-21
SLIDE 21

JCI-RILEM International Workshop, CONCRACK5, April 24-26, 2017, Japan

21

Conclusions

It was confirmed that the provisions against the thermal cracking were effective. It was confirmed that the provision to the cement type with less total heat generation due to the hydration reactions was effective especially in the 1st lift. And reducing temperature of concrete such as cooling was effective in the 2nd lift for controlling the thermal crack at the column capital. The values of thermal properties calculated after the fitting analysis were almost similar to one of the prior verifications.