PROSPEX UKCS Exploration & Appraisal Status Gunther Newcombe December 2016 Director Operations OGA OGA became a GOVCO on 1 st October 2016 with additional powers and sanctions Progressive Regulation Role of the OGA OGA Approach MER UK
OGA became a GOVCO on 1st October 2016 with additional powers and sanctions
OGA
Progressive Regulation
Balanced application of new regulatory framework
Role of the OGA
Investment and action Encouraging collaboration Effective stewardship
OGA Approach
Sanctions Rewards
Sanctions Information & Samples Dispute resolution Meetings MER UK Strategy – binding obligations & safeguards
Striking the right balance
UKCS Summary
Production (boepd)
2014 1.4 million 2015 1.6 million 2016 1.65 million
Production efficiency
2012 60% 2015 71% 2016 80% target
Infrastructure
12,000+ wells 250+ subsea systems 3,000+ pipelines 250 fixed installations
Exploration & appraisal
2014 wells 32 2015 wells 26 2016 wells 20
Costs
Unit costs down by nearly 30%
Source – OGA Source – OGA and Oil & Gas UK
Development
6.3bn boe
in production
- r under
development
Source – OGA Source
– OGASource – OGA and Oil & Gas UK
Resources
Source – OGA
Remaining potential
Produced
43bn
10bn 20bn
Improving & adapting to new conditions
Supply chain
c.£30bn turnover
Source –Oil & Gas UK and EY
80% of UK oil and gas jobs 40% through exports Jobs
330,000 jobs in the UK
Source – Oil & Gas UK
Delivered through or supported by upstream oil and gas activity
Average unit operating costs have fallen from £18 per barrel in 2014 to an estimate of £13 per barrel in 2016
OGA Corporate Plan
OGA on track to delivering exploration priorities
Share dry-hole review with industry Licensing strategy for frontier & mature acreage Work with HMT & Industry to enhance exploration Provide high quality geophysical data Rockall & MNSH Undertake rigorous pre & post-drill evaluation High-grade operator prospect inventory to stimulate drilling Manage release of geophysical & well data Produce high quality geological maps 2015 2015 2015 1Q 2016 2016 2016 2016 2018 Provide industry with regional prospectivity & YTF 2018
UKCS highly competitive fiscal regime with government working closely with OGA & Industry
Fiscal Regime
Strong commitment & listening from government Recent budgets provided £2.3bn relief to industry OGA provide expertise and evidence to HMT
Mature Yet-to-Find
UKCS has 6bnboe YTF best estimate in mature areas
c
NNS WOS SNS
CNS NNS WOS
SNS
NNS CNS WOS SNS
Source: OGA
Number of Wells
Exploration and Appraisal
Commercial discovery rate better than 1 in 2 with 350mmboe at $3.50 finding cost
Source: OGA mmboe
100 200 300 400 500 600 700 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
Reserve Adds Sanctioned Reserves
Oil Gas Loanan Lincoln Lancaster Storr W/E Belinda Eagle Laverda/Slough Finlaggan Bagpuss Winchelsea Skipper
E&A Well Activity
OGA working with operators to ensure well activity is undertaken
Exploration Well Appraisal Well Firm Well Contingent Well Other well
Exploration Activity
Templewood accelerated to 2016 and well spudded in October
- Late Jurassic turbidite sands
- Hanging wall structural trap, HPHT
- 3D seismic reprocessed 2011
- Drill or drop commitment
Templewood – Central North Sea (ConocoPhillips)
Appraisal Activity
Fast track appraisal moving towards development
Fractured basement
Rona Ridge fractured basement potential Hurricane exploration & appraisal
Halifax
Discoveries
5bnboe discovered to date with 2.4bnboe in small pools & 150 small pools in open acreage
Reserves/resources mmboe
Producing fields Ongoing developments Currently locked discoveries 10 100
Source: OGA
1000
CNS WoS MF NNS SNS
3.4bnboe
Total Recoverable Resources (mmboe)
Frontier Exploration
Significant focus & investment in frontier exploration in last 2 years
2015 & 2016 Programs
£40m government funded 80,000 km new/reprocessed data 2016 seismic data acquisition complete, processing underway
Palaeozoic study issued. SW Britain & East Shetland Platform in progress
Competition to define potential
£500k prize money for 2015/2016 projects
New 3D visualization facility
£700k funding for Lyell Centre in Edinburgh
Supporting skills for the future
£750,000 for 3 post-doctoral appointments in geoscience & reservoir engineering
29th Round Areas
29th Offshore Licensing Round
29th Round received 29 applications from 24 companies covering 113 blocks
Supplementary Round with 14 blocks nominated
Offshore Licensing Rounds
30th Offshore Round will open in 2Q 2017 coupled with discovered small pools initiative
Strategies & Expectations
All strategies and stewardship expectations published
10 Asset Stewardship Expectations
JV Hub Strategy E&A Work Programme Optimum use of Subsurface Data Licence Activity, Decision Points & Milestones Robust Project Delivery Production Optimisation Information Management Technology Plan Collaboration Planning for Decommissioning
E&A Stewardship Expectations
Asset Stewardship Expectations co-authored with industry & to be viewed as “good practice”
Annual E&A work program Resource evaluations Pre, syn & post drill evaluations & weekly drilling reports OGA involvement prior to investment decisions Common JV data sets Technical & cost benefit assessment Evaluation best available data, technologies, processes and skills Focus on quality geophysical data sets Executed JOA 6 months from licence award Notify OGA one month before drill or drop OGA notified of farm-out or divestment prior to activity commencing
E&A Work Programme Subsurface Data Licence Activity
Key Messages
OGA, industry & government need to continue to work together
OGA has been a GovCo since 1 October 2016 with new powers & sanction abilities Significant remaining mature & frontier exploration potential and discovered volumes E&A activity had a successful year in 2016 with increasing activity seen Asset stewardship expectations need to be followed