Project Update
Library Board of Trustees Update, Main Library – June 25, 2020
Prepared and Presented by Toni Lombardozzi, CCPL Project Manager
Project Update Prepared and Presented by Toni Lombardozzi, CCPL - - PowerPoint PPT Presentation
Project Update Prepared and Presented by Toni Lombardozzi, CCPL Project Manager Library Board of Trustees Update, Main Library June 25, 2020 June 25, 2020 Page 2 Location Updates Regional Library Renovations Completed review of 95%
Library Board of Trustees Update, Main Library – June 25, 2020
Prepared and Presented by Toni Lombardozzi, CCPL Project Manager
Completed review of 95% drawing set mid-June Cost estimates underway If schedule holds, expect to begin construction October 1 (tentative) Plan to complete three regionals in first round, then once those are complete, move on to the
June 25, 2020 Page 2
Master Plan design work for Shipwatch Corridor still in progress Anticipate beginning design work on the library this fall CCPL and County are looking into options for temporary library space since a portion of the existing
June 25, 2020 Page 3
Furniture installation delayed due to COVID-19, many pieces expected for delivery in June/July AMH installation week of July 6th, Self-check installation July 14/15th ODC mid-August (tentative) Anticipated Milestones
Substantial Completion: July 2020 Opening: Fall 2020 (tentative)
June 25, 2020 Page 4
Virtual ribbon cutting held June 7th Opened for curbside service along with other CCPL branches June 8th
June 25, 2020 Page 5
Working through correcting/finalizing some items + attention to warranty items County working through closeout process
June 25, 2020 Page 6
County working through closeout process
Temporary Certificate of Occupancy issued March 16
Certificate of Occupancy pending one final item: installation of an air grille and surrounding ceiling;
installation of grille complete, ceiling installation wrapping up this week
Furniture installation 98% complete; remaining items expected mid-July Anticipated Milestones
Final Completion/Certificate of Occupancy: early July 2020 Move-in/Opening: July 2020 (last week June, first week July)
June 25, 2020 Page 7
June 25, 2020 Page 8
June 2020
Substantial Completion Fall 2020
Completion
July 2020
construction start
June 25, 2020 Page 9
Project Title Status Total Bees Ferry West Ashley Baseline* 14,441,665 Actual/Projected CWE 14,567,174 Baxter – Patrick James Island Baseline* 13,131,000 Actual/Projected CWE 11,953,344 Wando Mount Pleasant Baseline* 26,135,000 Actual/Projected CWE 20,221,226
Baseline* 10,673,609 Actual/Projected CWE 11,921,528
Baseline* 10,946,000 Actual/Projected CWE 11,554,500 Support Services Baseline* 7,669,549 Actual/Projected CWE 8,603,517 Existing Library Upgrades Baseline* 25,503,177 Actual/Projected CWE 29,652,428 LIBRARY TOTAL Baseline* 108,500,000 CWE 108,473,717 Project Title Status Total Bees Ferry West Ashley Baseline* 14,441,665 Actual/Projected CWE 14,567,174 Baxter – Patrick James Island Baseline* 13,131,000 Actual/Projected CWE 11,953,344 Wando Mount Pleasant Baseline* 26,135,000 Actual/Projected CWE 20,221,226
Baseline* 10,673,609 Actual/Projected CWE 11,921,528
Baseline* 10,946,000 Actual/Projected CWE 11,554,500 Support Services Baseline* 7,669,549 Actual/Projected CWE 8,603,517 Existing Library Upgrades Baseline* 25,503,177 Actual/Projected CWE 29,652,428 LIBRARY TOTAL Baseline* 108,500,000 CWE 108,473,717