Project Update Prepared and Presented by Toni Lombardozzi, CCPL - - PowerPoint PPT Presentation

project update
SMART_READER_LITE
LIVE PREVIEW

Project Update Prepared and Presented by Toni Lombardozzi, CCPL - - PowerPoint PPT Presentation

Project Update Prepared and Presented by Toni Lombardozzi, CCPL Project Manager Library Board of Trustees Update, Main Library June 25, 2020 June 25, 2020 Page 2 Location Updates Regional Library Renovations Completed review of 95%


slide-1
SLIDE 1

Project Update

Library Board of Trustees Update, Main Library – June 25, 2020

Prepared and Presented by Toni Lombardozzi, CCPL Project Manager

slide-2
SLIDE 2

Regional Library Renovations

 Completed review of 95% drawing set mid-June  Cost estimates underway  If schedule holds, expect to begin construction October 1 (tentative)  Plan to complete three regionals in first round, then once those are complete, move on to the

remaining two

Location Updates

June 25, 2020 Page 2

slide-3
SLIDE 3
  • R. Keith Summey North Charleston (RKSNC)

 Master Plan design work for Shipwatch Corridor still in progress  Anticipate beginning design work on the library this fall  CCPL and County are looking into options for temporary library space since a portion of the existing

Cooper River Memorial Library must be incorporated into the new library due to its historic designation

Location Updates

June 25, 2020 Page 3

slide-4
SLIDE 4

Bees Ferry West Ashley (BFWA)

 Furniture installation delayed due to COVID-19, many pieces expected for delivery in June/July  AMH installation week of July 6th, Self-check installation July 14/15th  ODC mid-August (tentative)  Anticipated Milestones

 Substantial Completion: July 2020  Opening: Fall 2020 (tentative)

Location Updates

June 25, 2020 Page 4

slide-5
SLIDE 5
  • St. Paul’s Hollywood (SPH)

 Virtual ribbon cutting held June 7th  Opened for curbside service along with other CCPL branches June 8th

Location Updates

June 25, 2020 Page 5

slide-6
SLIDE 6

Baxter - Patrick James Island (BPJI)

 Working through correcting/finalizing some items + attention to warranty items  County working through closeout process

Location Updates

June 25, 2020 Page 6

Wando Mount Pleasant (WMP)

 County working through closeout process

slide-7
SLIDE 7

Support Services (SS)

 Temporary Certificate of Occupancy issued March 16

 Certificate of Occupancy pending one final item: installation of an air grille and surrounding ceiling;

installation of grille complete, ceiling installation wrapping up this week

 Furniture installation 98% complete; remaining items expected mid-July  Anticipated Milestones

 Final Completion/Certificate of Occupancy: early July 2020  Move-in/Opening: July 2020 (last week June, first week July)

Location Updates

June 25, 2020 Page 7

slide-8
SLIDE 8

Timeline Summary

June 25, 2020 Page 8

  • SPH Open

June 2020

  • BFWA

Substantial Completion Fall 2020

  • BFWA Open
  • SS Final

Completion

  • SS Move-in

July 2020

  • Regionals

construction start

slide-9
SLIDE 9

Financial Status – Previous Reports

June 25, 2020 Page 9

Figures as of January, 2020 Figures as of November, 2019

Project Title Status Total Bees Ferry West Ashley Baseline* 14,441,665 Actual/Projected CWE 14,567,174 Baxter – Patrick James Island Baseline* 13,131,000 Actual/Projected CWE 11,953,344 Wando Mount Pleasant Baseline* 26,135,000 Actual/Projected CWE 20,221,226

  • R. Keith Summey N. CHS

Baseline* 10,673,609 Actual/Projected CWE 11,921,528

  • St. Paul’s Hollywood

Baseline* 10,946,000 Actual/Projected CWE 11,554,500 Support Services Baseline* 7,669,549 Actual/Projected CWE 8,603,517 Existing Library Upgrades Baseline* 25,503,177 Actual/Projected CWE 29,652,428 LIBRARY TOTAL Baseline* 108,500,000 CWE 108,473,717 Project Title Status Total Bees Ferry West Ashley Baseline* 14,441,665 Actual/Projected CWE 14,567,174 Baxter – Patrick James Island Baseline* 13,131,000 Actual/Projected CWE 11,953,344 Wando Mount Pleasant Baseline* 26,135,000 Actual/Projected CWE 20,221,226

  • R. Keith Summey N. CHS

Baseline* 10,673,609 Actual/Projected CWE 11,921,528

  • St. Paul’s Hollywood

Baseline* 10,946,000 Actual/Projected CWE 11,554,500 Support Services Baseline* 7,669,549 Actual/Projected CWE 8,603,517 Existing Library Upgrades Baseline* 25,503,177 Actual/Projected CWE 29,652,428 LIBRARY TOTAL Baseline* 108,500,000 CWE 108,473,717