Northwest Water Treatment Facility (NWWTF)
Public Works & Utilities November 6, 2018
Project Update Public Works & Utilities November 6, 2018 EPA - - PowerPoint PPT Presentation
Northwest Water Treatment Facility (NWWTF) Project Update Public Works & Utilities November 6, 2018 EPA LOI H IGHLIGHTS 2 Regional/National Significance: Asset Management and Utility Optimization: The City of Wichita is the
Public Works & Utilities November 6, 2018
2
regional drinking water in the state of Kansas, providing drinking water to more than 500,000 people.
condition of the MWTP constitute an unacceptable level of risk to the City of Wichita and the region.
minimum of 7 years in the absence of WIFIA financing.
program will extend the expected life of project assets.
maintaining the viability of all sources during extended drought periods.
July 10th
treatment plant using a DBo model
needs replaced to avoid catastrophic outages
to providing water service to approx. 500,000 people
3
4
7/1/18 8/30/18 10/29/18 12/28/18 2/26/19 4/27/19 6/26/19 8/25/19 10/24/19 12/23/19 2/21/20
Council Approval of Letter of Interest(LOI) and NWWTF RFP RFP Proposals Due September 7, 2018 EPA Letter of Interest Process RFP Interviews to Council Approval Application Development* EPA WIFIA Loan Negotiation & Closing to Start of Construction
5 D (Design) B (Build) O (Operate – short term) Jacobs Treatment: Non-Local Pipelines: Non-Local * Appx 70% Local Identified O&M Team Wichita Water Partners Treatment: Non-Local Pipelines: Local Significant Local Construction Planned No Identified O&M Team
* In contract discussions, Jacobs has indicated its preference to utilize local design firms for aspects of the pipelines
6
Jacobs
Management all by one firm out of Denver and Corvallis offices
Wood Engineering Wichita office. Jacobs working with other local firms on supporting designs
design QA/QC
decisions
Wichita Water Partners
Management by HDR and B&M out of Kansas City
firms PEC, MKEC, GMLV, SJCF all of Wichita
design QA/QC
discussions during design
confirm constructability
Both teams would review previously identified design concepts
7
Jacobs
70-80% of project locally. Sub contractor McCarthy planning to hire locally as demonstrated on current project in Kansas
early
surrounding properties and mitigation measures to be utilized
design to flatten the need rather than short term spikes in labor force Wichita Water Partners
sub contractors of three local firms with competitive bid packages to decide about 80%
management and commissioning of facility
8
Jacobs
demonstrated
tools that transition to City for training of new staff and refresher training
United States water and wastewater facilities
process Wichita Water Partners
construction narrowed to one prior to
plants
9
Jacobs
and 180MGD
NWWTF size or larger
Applications from 2017 Wichita Water Partners
NWWTF size or larger – one as designer, one as builder, and one as DB
WIFIA Application
10
Jacobs
partner)
Wichita Water Partners
McDonnell)
Alberici Builder
Committee Membership
community
experience with the City
management
11 Jacobs Wichita Water Partners Average Selection Score 89 80
Ranking as Preferred Proposer 11
12
Sequence #1 7/20 – 1/21 Sequence #2 12/20 – 1/23 Sequence #3 12/20 – 8/23 Sequence #4 12/20 – 7/23 Sequence #5 1/21 – 11/22 Sequence #6 7/21 – 11/22 Sequence #7 5/21 – 7/22
Site Clearing & Preparation Clearwells Filters BW Tank / CCB / CCB PS Finished Water PS Raw Water Sed. Sedimentation Basins Solids Contact Clarifiers Gravity Thickeners Solids Pump Station Operations Building Maintenance Facility Switchgear Generators Fuel Tank
13
be used to conduct probability analysis of costs and schedule changes
14
training
15
Key Takeaways 1) City received two strong proposals 2) Delays to the schedule endangers WIFIA 3) Selection Committee unanimously recommends Jacobs
4) Represents the best team and schedule to minimize rate increases through a lower GMP and successful WIFIA application Recommended Future Actions