Project Update Public Works & Utilities November 6, 2018 EPA - - PowerPoint PPT Presentation

project update
SMART_READER_LITE
LIVE PREVIEW

Project Update Public Works & Utilities November 6, 2018 EPA - - PowerPoint PPT Presentation

Northwest Water Treatment Facility (NWWTF) Project Update Public Works & Utilities November 6, 2018 EPA LOI H IGHLIGHTS 2 Regional/National Significance: Asset Management and Utility Optimization: The City of Wichita is the


slide-1
SLIDE 1

Northwest Water Treatment Facility (NWWTF)

Public Works & Utilities November 6, 2018

Project Update

slide-2
SLIDE 2

EPA LOI HIGHLIGHTS

2

  • Regional/National Significance:
  • The City of Wichita is the largest provider of

regional drinking water in the state of Kansas, providing drinking water to more than 500,000 people.

  • Aging Infrastructure and Utility Risk:
  • The single MWTP and the overall poor

condition of the MWTP constitute an unacceptable level of risk to the City of Wichita and the region.

  • Project Timing and Risk Mitigation:
  • The NWWTF project would be delayed a

minimum of 7 years in the absence of WIFIA financing.

  • Asset Management and Utility Optimization:
  • The City’s proactive asset management

program will extend the expected life of project assets.

  • Adaptive Resource Management:
  • The adaptive management practices focus on

maintaining the viability of all sources during extended drought periods.

slide-3
SLIDE 3

BACKGROUND

  • Council approved release of NWWTF RFP on

July 10th

  • Two-phase process to construct a new water

treatment plant using a DBo model

  • Nearly 80 years old
  • Existing treatment plant is at risk of failure;

needs replaced to avoid catastrophic outages

  • Greater delays in project create greater risk

to providing water service to approx. 500,000 people

3

slide-4
SLIDE 4

PROCESS & SCHEDULE

  • WIFIA timeline identified by EPA and drives project schedule
  • Need to have 30% design, GMP, O&M Plan, Environmental Assessment and
  • ther information to fulfill WIFIA application requirements
  • Design process for application requirements expected to take 12 months*
  • Delays jeopardize ability to complete the application process in time for WIFIA

4

7/1/18 8/30/18 10/29/18 12/28/18 2/26/19 4/27/19 6/26/19 8/25/19 10/24/19 12/23/19 2/21/20

Council Approval of Letter of Interest(LOI) and NWWTF RFP RFP Proposals Due September 7, 2018 EPA Letter of Interest Process RFP Interviews to Council Approval Application Development* EPA WIFIA Loan Negotiation & Closing to Start of Construction

slide-5
SLIDE 5

SUMMARY OF PROPOSERS

5 D (Design) B (Build) O (Operate – short term) Jacobs Treatment: Non-Local Pipelines: Non-Local * Appx 70% Local Identified O&M Team Wichita Water Partners Treatment: Non-Local Pipelines: Local Significant Local Construction Planned No Identified O&M Team

* In contract discussions, Jacobs has indicated its preference to utilize local design firms for aspects of the pipelines

slide-6
SLIDE 6

SUMMARY - DESIGN

6

Jacobs

  • Treatment Plant Design, Modeling, and Asset

Management all by one firm out of Denver and Corvallis offices

  • Pipeline and Supporting Assets Design by

Wood Engineering Wichita office. Jacobs working with other local firms on supporting designs

  • Identified separation between design and

design QA/QC

  • Risk management integrated in all design

decisions

  • 3-D Modelling integrated & used in all of project

Wichita Water Partners

  • Treatment Plant Design led by sub firm HDR
  • ut of Omaha. Modeling and Asset

Management by HDR and B&M out of Kansas City

  • Pipeline and Supporting Assets Design by sub

firms PEC, MKEC, GMLV, SJCF all of Wichita

  • Overlap of individuals involved in design and

design QA/QC

  • Discussed need for further risk allocation

discussions during design

  • 3-D Modelling for Designer and Builder to

confirm constructability

Both teams would review previously identified design concepts

slide-7
SLIDE 7

SUMMARY - BUILD

7

Jacobs

  • Will issue competitive bid packages for at least

70-80% of project locally. Sub contractor McCarthy planning to hire locally as demonstrated on current project in Kansas

  • Targeting a projected completion three months

early

  • Identified potential areas of impact on

surrounding properties and mitigation measures to be utilized

  • Identified labor needs and ability to work with

design to flatten the need rather than short term spikes in labor force Wichita Water Partners

  • Alberici Construction part of joint venture with

sub contractors of three local firms with competitive bid packages to decide about 80%

  • f construction responsibilities.
  • Lack of discussion on construction

management and commissioning of facility

  • Can meet overall schedule
slide-8
SLIDE 8

SUMMARY - OPERATE

8

Jacobs

  • Multiple project examples of short term
  • perations and transition to City
  • Extensive training plan developed and

demonstrated

  • Training includes ‘flight’ simulator and other

tools that transition to City for training of new staff and refresher training

  • Jacobs operates more than 200

United States water and wastewater facilities

  • Competitive procurement part of this DBo RFP

process Wichita Water Partners

  • One municipal utility and two private
  • perations firms as subs during design and

construction narrowed to one prior to

  • perations period
  • Provided a general approach and methods to
  • perations, training, and transition but with lack
  • f detail
  • Three sub-contract operators conduct
  • perations for more than 200 water treatment

plants

  • Competitive procurement would occur summer
  • f 2019
slide-9
SLIDE 9

SUMMARY - EXPERIENCE

9

Jacobs

  • Proven DB and DBO and DBo experience
  • Identified DBO projects of 30MGD, 100 MGD,

and 180MGD

  • Identified at least nine water treatment plants

NWWTF size or larger

  • Developed and/or reviewed 8 of the 12 WIFIA

Applications from 2017 Wichita Water Partners

  • Proven DB experience
  • No DBO projects identified
  • Identified three water treatment plant projects

NWWTF size or larger – one as designer, one as builder, and one as DB

  • Sub-engineering firm developed one 2017

WIFIA Application

slide-10
SLIDE 10

SUMMARY - EXPERIENCE

10

Jacobs

  • As DBO
  • 180 MGD; Renton, WA
  • 100 MGD; San Diego, CA
  • 30 MGD; Woodlands, CA
  • As DB
  • 80 MGD; Phoenix, AZ
  • 15 MGD; Santa Fe, NM
  • 24 MGD; Brighton, CO
  • 320 MGD; Houston, TX (joint venture

partner)

  • 50 MGD; Colorado Springs, CO

Wichita Water Partners

  • No DBO projects identified
  • As DB
  • Wichita ASR Surface Water Treatment
  • Wichita Chemical Feed Replacement
  • 20 MGD; Thornton, CO (Burns &

McDonnell)

  • Involved in some aspect of project
  • 100 MGD; Omaha, NE; HDR Designer and

Alberici Builder

  • 160 MGD; Omaha, NE; HDR Designer
  • Membrane WTP; Fargo, ND; Alberici Builder
slide-11
SLIDE 11

SELECTION PROCESS

Committee Membership

  • 11 committee members
  • 1 member from wholesale

community

  • 175 years of combined

experience with the City

  • Senior and mid-level

management

  • Multiple departments

11 Jacobs Wichita Water Partners Average Selection Score 89 80

  • No. Members

Ranking as Preferred Proposer 11

slide-12
SLIDE 12

CONSTRUCTION SEQUENCING

12

  • Simultaneous construction in separate work areas
  • Speeds up construction and levels out skilled labor needs
  • Creates competitive bid packages for local subcontractors

Sequence #1 7/20 – 1/21 Sequence #2 12/20 – 1/23 Sequence #3 12/20 – 8/23 Sequence #4 12/20 – 7/23 Sequence #5 1/21 – 11/22 Sequence #6 7/21 – 11/22 Sequence #7 5/21 – 7/22

Site Clearing & Preparation Clearwells Filters BW Tank / CCB / CCB PS Finished Water PS Raw Water Sed. Sedimentation Basins Solids Contact Clarifiers Gravity Thickeners Solids Pump Station Operations Building Maintenance Facility Switchgear Generators Fuel Tank

  • Chem. Facility
slide-13
SLIDE 13

RISK-BASED GMP

13

  • Design and construction cost a primary driver of rate increases
  • Lowest possible GMP would minimize water rate adjustments
  • “Risk and Opportunity Management Tool” tied to project scheduling would

be used to conduct probability analysis of costs and schedule changes

  • Identifies risks with potential to add the highest costs
  • Develops strategies to eliminate, minimize, and offset cost impacts
slide-14
SLIDE 14

O&M PLAN

14

  • WIFIA Application requirement for defined O&M Plan
  • Experience with having O&M integrated into their organization
  • Experience with O&M integrated into Design and Construction
  • Defined O&M Transition Plan that includes staffing options
  • O&M Plan that includes simulators and other tools for ongoing

training

slide-15
SLIDE 15

CONCLUSION

15

Key Takeaways 1) City received two strong proposals 2) Delays to the schedule endangers WIFIA 3) Selection Committee unanimously recommends Jacobs

  • Experience with O&M in organization
  • More experience with similar projects
  • Risk-based GMP should lower costs
  • Advantages with construction sequencing

4) Represents the best team and schedule to minimize rate increases through a lower GMP and successful WIFIA application Recommended Future Actions

  • November 20th Council Meeting
  • NWWTF Design
  • Phase 1 DBo contract with Jacobs
  • Financing
  • Development of SRF Loan Application
  • Development of WIFIA Loan Application
  • 2019 Rate Adjustments
  • Increase of 7.7%
  • Owner’s Representative Contract
  • Staff return for Council approval