Project 21 update FA Scrutiny & Audit Panel
21/05/20 - Webex
Project 21 update FA Scrutiny & Audit Panel 21/05/20 - Webex - - PowerPoint PPT Presentation
Project 21 update FA Scrutiny & Audit Panel 21/05/20 - Webex Reminder of P21 background & purpose Background: East Sussex FRS currently operates its control and mobilising function from East Sussex Fire Control (ESFC) at Haywards
21/05/20 - Webex
2
Background: East Sussex FRS currently operates its control and mobilising function from East Sussex Fire Control (ESFC) at Haywards Heath, formerly know as the Sussex Control Centre (SCC) prior to 4/12/19.
Therefore, East Sussex FRS had to consider its options for it’s future control and mobilising service. Purpose: Project 21 exists to determine and deliver the future operating model for Fire Control services for ESFRS from September 2021 onwards. On 9/1/20 the Fire Authority approved the recommendation of the DCFO to partner with Surrey Fire & Rescue Service for Fire Control from September 2021 onwards
3
As currently scoped Project 21 will deliver the following - to be finalised during the Definition & Design phase:
Progress since January ’20 has been as follows:
5
Project 21 and its associated workstreams.
associated joint decisions on operational, technical or financial matters material to the future joint operating model to be delivered by Project 21.
Workstream
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
BAU role Project role
Key:
Project role (p/t)
IT Lead & PM
Ken Pearce + John Price (telent)
HR Lead
Lucy Birch
Chris Sharp
Finance Lead
Parmjeet Jassal
Ops Lead
Simon Neill
SME
Paula Wheatley
Colette Porter
SRO
(chair) Matt Lloyd
IT
Ken Pearce
Finance
Duncan Savage
Senior User
Mark Andrews
People
Hannah Scott-Y
Legal
Alice Rowland
Workstreams
(as required)
Sponsor
(chair) Mark O’Brien Executive
ESFRS Delivery Board Programme team
Internal Strategic Board Internal Delivery Board Programme Workstreams
+ suppliers
+
Workstream
+ suppliers
Workstream
+ suppliers
Workstreams
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
Workstreams
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
Workstreams
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
Workstreams
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
Workstreams
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
Workstream
+ suppliers
Workstreams
+ suppliers
Key:
Workstream specific workshops / meetings
+ suppliers
East PM
Chris Sharp
Joint Strategic Board Joint Delivery Board Joint Workstreams
ESFRS
DCFO Mark O’Brien
SFRS
DCFO Dan Quin
WSFRS
ACFO Jon Lacey
ESFRS
SRO Matt Lloyd
SFRS
SRO Sally Wilson
WSFRS
SRO Jon Lacey
Workstream specific workshops / meetings
+ suppliers
Workstream specific workshops / meetings
+ suppliers
Workstream specific workshops / meetings
+ suppliers
Workstream specific workshops / meetings
+ suppliers
Joint Strategic Board Finance
+
Joint Delivery Board Legal
+
Surrey PM
TBC
WSCC IT
+
HR
+
Programme
8
PROJECT 21
Purpose Scale
TIME:
live Sept. ‘21
to delivery
Workload
To determine and deliver the future operating model for Fire Control services for ESFRS from Sept. 2021 onwards COST:
QUALITY:
workstreams
packages
Team FTE & no. of suppliers
WSFRS: Core: 1 Virtual: 3 Suppliers: 4 SFRS: Core: 3 Virtual: 18 Suppliers: 4 ESFRS: Core: 6 Virtual: 21 Suppliers: 16 Governance Internal: 2 Joint: 3 Total: 5 Workshops Complete: 20 Attendees: 50+ Options papers Complete: 0 Drafted: 3 Planned: 14
9
Discovery
Q3 Q4 Q1 Q2 Q3 Q4 Q2 Q1 Q3 Q4 18/19 19/20 20/21
Realise Deliver Definition & Design Due diligence Pre-Qual.
21/22 Q1 Q2 Q3 We are here FA decision January 2020 Target go-live September 2021
10
Define Recommend Decide Consult Agree Deliver
External Stakeholder engagement
appropriate (staff, Trade Unions etc)
WoW’s agreed following consultation
We are here
11
Item Channel To whom Frequency Content 1 Report Senior Officers Weekly Weekly summary, progress v plan, key risks and issues 2 Governance meetings IDB, ISB, JDB, JSB Monthly Monthly progress update, workstream specifics, decisions and escalations 3 BAU meeting SLT Monthly headlines & quarterly presentation Progress update and any key highlights 4 BAU meeting Ops Committee, GM meetings, Safer Comm. etc Quarterly Progress update and workstream / option specific consultation 5 Service Brief All Monthly P21 article P21 headlines, progress update, highlights, workstream specific features 6 Intranet All Ongoing P21 overview, contacts, FAQ, progress updates, key materials, workstream specific features 6 Design Workshops Workstream stakeholders As required Workstream specific information gather, option development and analysis (tri-service) 7 Meeting & formal consultation Trade Unions Monthly Progress update and any workstream specific consultation 8 1:1’s ESFC staff As required Welfare, progress update, individual Q&As 9 1:1’s Key stakeholders As required Topic specific sessions to ensure all stakeholders are engaged and consulted as appropriate
12
Programme Support HR Lead Programme Manager Finance Lead Ops Lead IT Lead
Delivery of all programme outcomes to time, cost and quality on behalf of the SRO. Programme financial control and reporting. Supports SRO in stakeholder management. Represents HR interests throughout the programme
People matters. Owns the People workstream content. Represents Finance interests throughout the programme
Financial matters. Owns the Finance workstream content. Technical project management and delivery of all IT elements of the programme, including supplier management and coordination with Design Authority. Programme administration, document and financial
benefits register. Supports Programme Manager. Supports the ESFC lead in terms of requirements and
and train new WoWs. Testing resource. Change advocate. Represents ES control and Ops P&P interests. Manages SME input to the programme. ESFC SPOC and owns Control
SRO
Overall responsibility for programme Vision, Blueprint, Benefits and Governance on behalf of the Executive Sponsor and whole Service. ESFRS Tri-Service Lead.
Legal
Legal workstream responsible for all legal advice, negotiation and sanction of legal framework documentation (confidentiality, data protection & S16)
BAU role Project role
Key:
Project role (p/t)
14
15 As @ Mar. ‘20
Financial Year 2019/20 2020/21 2021/22 2022/23 Total TOTAL (BASELINE) 305,000 4,305,851 319,550 118,670 5,049,071 TOTAL (FORECAST) 325,000 3,005,043 1,600,358 118,670 5,049,071