PRIORITIZING STORMWATER CAPITAL IMPROVEMENT PROGRAM (CIP) PROJECTS - - PowerPoint PPT Presentation

prioritizing stormwater capital improvement program cip
SMART_READER_LITE
LIVE PREVIEW

PRIORITIZING STORMWATER CAPITAL IMPROVEMENT PROGRAM (CIP) PROJECTS - - PowerPoint PPT Presentation

PRIORITIZING STORMWATER CAPITAL IMPROVEMENT PROGRAM (CIP) PROJECTS Presented by APWA Fall Joint Conference| Kearney, NE | November 6 th , 2013 Lalit Jha, PE, D.WRE, CFM Miles Simmons, EIT, M.S. 1 Agenda Urban Drainage Issues CIP


slide-1
SLIDE 1

1

PRIORITIZING STORMWATER CAPITAL IMPROVEMENT PROGRAM (CIP) PROJECTS

APWA Fall Joint Conference| Kearney, NE | November 6th , 2013

Presented by Lalit Jha, PE, D.WRE, CFM Miles Simmons, EIT, M.S.

slide-2
SLIDE 2

2

Agenda

  • Urban Drainage Issues
  • CIP Prioritization
  • Study Methodology
  • Project Benefits
  • Conclusion
slide-3
SLIDE 3

3

Urban Drainage Issues

  • Flooding Problems
  • Structural Condition of the System
  • System Upgrades and Master Planning
  • Operation and Maintenance
  • Stormwater Program Financing
slide-4
SLIDE 4

4

63rd and Fletcher Ave. 50th and R St.

Localized Flooding

slide-5
SLIDE 5

5

27th and Highway 2 33rd and Highway 2

Stormwater System Deficiencies

slide-6
SLIDE 6

6

14th and Holdrege St. 11th and Oak St.

Structural Condition

slide-7
SLIDE 7

7

Urban Drainage Issues

“How can drainage problems be identified?” “Which problems should be addressed first?” “What are the financing needs?”

“Most bang for the buck”

slide-8
SLIDE 8

8

Background – Lincoln, Nebraska

  • State Capital, second largest City in NE
  • Population 260,000
  • 82 square miles within City limits
  • 500 miles of public storm drain system
  • 230 miles of open channel system
  • 31,000 ancillary items
slide-9
SLIDE 9

9

Background – CIP Prioritization

  • Previous methodology developed in 1966
  • Based on out‐dated standards
  • Reactive approach

“Squeaky wheel gets the grease”

slide-10
SLIDE 10

10

Project Objective

  • Develop an updated prioritization

methodology and a proactive CIP

  • Identify stormwater CIP projects
  • Enhance the City’s stormwater database

“Reduce Flooding and Drainage Issues”

slide-11
SLIDE 11

11

Prioritization Approach

  • Written Scoring
  • Written Policy
  • Engineering

Judgment / Committee Review

slide-12
SLIDE 12

12

Prioritization Methodology

  • Prioritization Categories
  • Structural Flooding
  • Non‐Structural Flooding
  • Existing Infrastructure Condition
  • Miscellaneous Factors
  • health and safety
  • critical locations
  • downstream impacts
  • community development
  • links to other utility projects
slide-13
SLIDE 13

13

Prioritization Methodology Example Prioritization Worksheet

slide-14
SLIDE 14

14

Previous Study Process

  • Data Preparation / Data Collection
  • Identify Deficiencies

– MicroStation GeoPak Drainage – 1‐D, Rational Method, steady flow

  • Propose Drainage Improvements
  • Prioritize Projects
  • GIS Coverage and Database

– Imported from MicroStation

slide-15
SLIDE 15

15

Application

  • Studied 10,000 acres of watershed
  • 135 miles of pipe, 20,000 LF of open channel,

5,000 ancillary items

  • Identified 150 CIP stormwater projects

– Dozens of projects proceeded to design/construction through funding from 2005‐2012 Stormwater bonds

slide-16
SLIDE 16

16

Current Urban Drainage Study

slide-17
SLIDE 17

17

Current Study Process

  • Phase 1‐ Screening Level Analysis

– 1‐D, Rational Method, steady flow – Identify Storm System Deficiencies

  • Pipe Capacity, Inlet Ponding Depths, Ponding Limits, Structural

Flooding

– Update GIS Database

  • Phase 2‐ Detailed Analysis and CIP Development

– Optional 2‐D, unsteady flow – Develop CIP stormwater projects

  • Evaluate conceptual alternatives
slide-18
SLIDE 18

18

Hydrology and Hydraulics

Screenshot of DGN map

ArcGIS XP SWMM

slide-19
SLIDE 19

19

Drainage system deficiencies based on design storm as defined in City design criteria manual. Pipes

(Discharge Relative to Capacity)

Inlets

(Ponded Depth at Inlet)

Ponding Areas

(Structural Flood Frequency)

Street Flooding

Stormwater System Deficiencies

slide-20
SLIDE 20

20

1-D/2-D Analysis

1-D Pipes/Open Channels 2-D Overland Flow/Flooding

slide-21
SLIDE 21

21

Flooding Animations

slide-22
SLIDE 22

22

CIP Project Development

  • Structural Flooding
  • Location
  • City Design Standards
  • Cost-Effectiveness
slide-23
SLIDE 23

23

CIP Project Development

slide-24
SLIDE 24

24

CIP Project Prioritization

slide-25
SLIDE 25

25

GIS Database Management

slide-26
SLIDE 26

26

GIS Database Management

slide-27
SLIDE 27

27

Model Validation

slide-28
SLIDE 28

28

Conclusion

  • Cost‐effective approach to prepare a proactive

stormwater CIP

  • Ensures taxpayers’ dollars spent on most

needed projects

  • Helpful in justifying stormwater program

financing needs to elected officials and public

slide-29
SLIDE 29

29

Thank You! Questions?