Presentation of SMS: Sandbukta-Moss-Sstad By Jarle Rasmussen The - - PowerPoint PPT Presentation

presentation of sms sandbukta moss s stad
SMART_READER_LITE
LIVE PREVIEW

Presentation of SMS: Sandbukta-Moss-Sstad By Jarle Rasmussen The - - PowerPoint PPT Presentation

Presentation of SMS: Sandbukta-Moss-Sstad By Jarle Rasmussen The SMS Team Jarle Midjs Rasmussen Trygve Srb Kvarme Jan Nondal Prosjektsjef Prosjektleder offentlig plan Prosjekteringsleder Project Manager Planning Manager


slide-1
SLIDE 1

Presentation of SMS: Sandbukta-Moss-Såstad

By Jarle Rasmussen

slide-2
SLIDE 2

Trygve Sørbø Kvarme Prosjektleder offentlig plan Planning Manager Ingunn Biørnstad Rådgiver Ytre miljø Environmental Manager Nina Kjønigsen Kommunikasjonsansvarlig Communications Manager Jan Nondal Prosjekteringsleder Engineering Manager Ivar Berge Kommunikasjonsrådgiver Communications Advisor Jarle Midjås Rasmussen Prosjektsjef Project Manager

The SMS Team

2

slide-3
SLIDE 3

The SMS Project

Information is correct as of 10 May 2017, but may be subject to change. 3

  • 10 km of new, double-

track line through Moss and Rygge

  • Two new tunnels:

‒ 2,7 km double tracked tunnel underneath Moss ‒ 2,3 km double tracked tunnel from station to Carlberg

  • New Moss station with a

800m long station area

slide-4
SLIDE 4

Plans and progression

Information is correct as of 10 May 2017, but may be subject to change. 4

  • Archeological excavation:

May-October 2017+2018

  • Preparatory work: 2017 -

2019

  • Construction start: Fall, 2019
  • Train operation: Dec 2024
  • Estimated project finish: 2025
slide-5
SLIDE 5

Information is correct as of 10 May 2017, but may be subject to change. 5

slide-6
SLIDE 6

Information is correct as of 10 May 2017, but may be subject to change.

6

Access to Sandbukta, north of Moss

slide-7
SLIDE 7

Sandbukta, north of Moss city center

Information is correct as of 10 May 2017, but may be subject to change. 7

slide-8
SLIDE 8

Construction pit/culvert, downtown Moss

Information is correct as of 10 May 2017, but may be subject to change. 8

  • Because of the ground

conditions it will be necessary to dig a pit and then cast a concrete tunnel north of the new station

  • Length: Approx. 400-450m
  • Width: Approx. 45m
  • Depth: 18-30m

Map of pit with culvert,

  • approx. 420 meters long
slide-9
SLIDE 9

Information is correct as of 10 May 2017, but may be subject to change. 9

An internal cross section of the area inside the central culvert, Moss

slide-10
SLIDE 10

Houses to be demolished in Moss and Rygge

Information is correct as of 10 May 2017, but may be subject to change. 10

  • Approx. 72 homes
  • 13 business buildings
  • 2 farms
  • = Approx. 87 buildings in total

to be demolished in Moss and Rygge

slide-11
SLIDE 11

Moss Station – a new meeting place

Information is correct as of 10 May 2017, but may be subject to change. 11

  • 4 platforms to the south of tunnel
  • Indoor bike hotel and waiting area
  • Easy access to public transportation
  • Easy access for pedestrians and

bikes, “kiss&ride”

  • Cafés and shops
slide-12
SLIDE 12

Track layout, Moss station

Information is correct as of 10 May 2017, but may be subject to change. 12 100 m 250 m

Rygge Ski

2B 4A 4B 3B 3A 2A 1A 1B

100 m 250 m

Havnspor 1 Havnspor 2

slide-13
SLIDE 13

New Moss station and infrastructure

Information is correct as of 10 May 2017, but may be subject to change. 13

slide-14
SLIDE 14

View from upper area, new Moss station

Information is correct as of 10 May 2017, but may be subject to change. 14

slide-15
SLIDE 15

Bridge for bikes and pedestrians

Information is correct as of 10 May 2017, but may be subject to change. 15

slide-16
SLIDE 16

Station area facing south towards Kleberget

Information is correct as of 10 May 2017, but may be subject to change. 16

slide-17
SLIDE 17

The Carlberg tunnel in Rygge

Information is correct as of 10 May 2017, but may be subject to change. 17

slide-18
SLIDE 18

Larkollveien in Rygge

Information is correct as of 10 May 2017, but may be subject to change.

18

slide-19
SLIDE 19

SMS challenges: EPC substructure contract

Information is correct as of 10 May 2017, but may be subject to change. 19

  • Ground conditions
  • Construction work in a city
  • Construction work in a

protected landscape area

slide-20
SLIDE 20

Challenging ground conditions

  • Areas of solid rock varies greatly, and there are areas of quick

clay and loose soil

  • These are moraine sediments from the ice age
  • Necessary to stabilize ground with cement/lime
  • Important to minimize risk for mudslides and structural damage

Information is correct as of 10 May 2017, but may be subject to change. 20

slide-21
SLIDE 21

Information is correct as of 10 May 2017, but may be subject to change. 21

So far, there has been approximately 450 different site drillings in Moss, allowing us to study soil samples, variations in ground and water pore balance.

Site drillings are necessary and essential

slide-22
SLIDE 22

Ground variations, measuring distance to solid rock in the station area

Information is correct as of 10 May 2017, but may be subject to change. 22

slide-23
SLIDE 23

Geo-technical and geological challenges

Using sheet piling and lime/cement stabilizers

Information is correct as of 10 May 2017, but may be subject to change. 23

Carlberg, Rygge Station area, Moss

slide-24
SLIDE 24

Building/ casting the new culvert

Information is correct as of 10 May 2017, but may be subject to change. 24

slide-25
SLIDE 25

Building in a city

Information is correct as of 10 May 2017, but may be subject to change. 25

slide-26
SLIDE 26

Important environmental challenges for the project, Sandbukta-Moss-Såstad

  • Construction work in a city – noise, dust, transport of masses, lots of

people and traffic in this area

  • Excavation of polluted soil near the sea/water – Risk: emission of

pollutants

Information is correct as of 10 May 2017, but may be subject to change. 26

slide-27
SLIDE 27
  • Construction traffic through an

important open-air recreational area (Mosseskogen) – demands measures and consideration

  • Construction in some of Norway’s

most valuable farmland-areas – need to rebuild and return construction areas and old tracks back to new farm land

  • Construction work through a

landscape protection area (Verne kloster) – demands for special considerations and results

Information is correct as of 10 May 2017, but may be subject to change. 27

Important environmental challenges for the project, Sandbukta-Moss-Såstad

slide-28
SLIDE 28

About Verne Kloster land protection area

  • The County Governor

has specific demands when it comes to construction work and completion of projects in the Verne kloster land protection area.

  • Bane NOR demands

that all government requirements are followed and respected by the contractor.

Information is correct as of 10 May 2017, but may be subject to change. 28

slide-29
SLIDE 29

About Verne kloster land protection area (cont.)

  • Land protection areas are locations which receive protection

through law because of their recognized natural, ecological or cultural values

  • The purpose is to preserve the manor-like landscape

with existing trees, buildings, stone fences, etc.

Information is correct as of 10 May 2017, but may be subject to change. 29

slide-30
SLIDE 30

Communication and information is key

  • Building a railroad through a

city affects everyone who lives and work there.

  • In Moss, the political debate

has taken almost 30 years.

  • This project will demand 87

properties and homes, it will cause noise and dust and demanding traffic situations for many years.

  • Information and

communication is key!

Information is correct as of 10 May 2017, but may be subject to change. 30

slide-31
SLIDE 31

31

Thank you for your attention!