Plans for installa,on Jim Stewart BNL July 18 2018 DUNE Far - - PowerPoint PPT Presentation

plans for installa on
SMART_READER_LITE
LIVE PREVIEW

Plans for installa,on Jim Stewart BNL July 18 2018 DUNE Far - - PowerPoint PPT Presentation

Plans for installa,on Jim Stewart BNL July 18 2018 DUNE Far Detector layout Bridge There is no rock pillar. Assembly work outside the cryostat occurs under the bridge. Detector Equipment is inserted Cryostat through a TCO Assembly


slide-1
SLIDE 1

Plans for installa,on

Jim Stewart BNL July 18 2018

slide-2
SLIDE 2

DUNE Far Detector layout

Detector Cryostat Bridge Assembly area. There is no rock pillar. Assembly work outside the cryostat occurs under the bridge. Equipment is inserted through a TCO

7/18/18 J Stewart BNL 2

slide-3
SLIDE 3

Ini,al Installa,on Phases

  • The DUNE surface and CUC areas are available years

before we gain access to the cryostat.

  • The DAQ is installed well before the detector installaMon
  • starts. (Should be true for slow control also.)
  • Cryostat #2 foam and membrane are installed in

parallel to detector #1

  • The first 4 months aSer we gain access to the cryostat

are spent seTng up the installaMon infrastructure.

  • The racks, cable trays, AC power, Rack cooling on the cryostat

roof will be in place.

  • The detector support structure will be in place with the

internal switchyard.

  • The installaMon cleanroom with all needed equipment are

installed.

3 7/18/18 J Stewart BNL

slide-4
SLIDE 4

4

Status at Start of Detector Assembly

Footbridge Cryostat Access Door (~5 m Wide) Cavern Bridge (5m Wide) TCO Plug (2) Cave Crane Elevator CPA Fixture Movable Lift (4) APA Work Platforms Clean Room Boundary APA Crate Cart SAS Boundry Exit Stairs Dressing Room 7/18/18 J Stewart BNL

slide-5
SLIDE 5

5

View Under the Bridge

Changing Room HV Assembly Area APA-CE Assembly Area Material Airlock

7/18/18 J Stewart BNL

slide-6
SLIDE 6

6

DUNE Far Detector

Outline of Clean Room

Divider Curtain Clean West Toaster & under Bridge North Utility Corridor South Utility Corridor ‘Dirty’ East Toaster Divider Curtain around stairs Exit Stairway (dirty) Changing Room 7/18/18 J Stewart BNL

slide-7
SLIDE 7

7

Plan View of Detector #1 Setup Under the bridge

  • Access

Underground is either using the stairs or using the manliS.

  • If the stairs are

used then one needs to walk through the Air Lock Area.

  • Changing room for

~30 people per shiS

7/18/18 J Stewart BNL

slide-8
SLIDE 8

8

APA Delivery

1) Crated APA is positioned on Bridge, Cave Crane moved into position 2) Crate lifted & moved over SAS in East Toaster

Equipment enters from the North driS Not much space between the bridge and the APA boxes The guard rails need removed and people need to be Med off

  • 2 APA with PD and CE

boxes are in a crate.

  • The CE cables are not

acached

7/18/18 J Stewart BNL

slide-9
SLIDE 9

9

APA are Rotated to Vertical in the Airlock

3) APA Crate on SAS Floor 4) Crated APA rotated to vertical position 7/18/18 J Stewart BNL

slide-10
SLIDE 10

10

DUNE Far Detector

Panel Components Staged in SAS & Clean Room

A cart on rails could be used to slide the APA into the cleanroom

7/18/18 J Stewart BNL

slide-11
SLIDE 11

11

DUNE Far Detector

APA Handling

Vertical APA Crate placed in cart APA Panels moved to Fixture

  • The 2 APA Panels are fixed

together

  • A bridge crane will be mounted under the

bridge to move equipment in the cleanroom

7/18/18 J Stewart BNL

slide-12
SLIDE 12

APA-CE cabling

  • CE cables are routed through the

APA side tubes in the cleanroom aSer the two APA are connected together.

  • A stairway work plaeorm “APA

Assembly Tower” is used to work

  • ff of for the cabling and tesMng.

12 7/18/18 J Stewart BNL

slide-13
SLIDE 13

Rail system for Inser,on into the cryostat

  • The yoke and a transfer

beam are mounted while the APA are on the assembly fixture.

  • When cabling is done the

APA are liSed onto the transport rails.

  • A crawler will push the

APA along the rails

13 7/18/18 J Stewart BNL

slide-14
SLIDE 14

14

DUNE Far Detector

APA Handling

10) APA panel ready to install in Cryostat, moved to APA-side of TCO track 7/18/18 J Stewart BNL

slide-15
SLIDE 15

Debugging sta,on

  • Space is available next to the

assembly staMon for debugging if needed.

15 7/18/18 J Stewart BNL

slide-16
SLIDE 16

DSS and switchyard

  • A shucle system of beam

inside the cryostat are used to transport the APA to to the correct row of I- Beams for deployment.

  • It is planned to stop the

APA at an intermediate posiMon to allow tesMng for several shiSs.

  • Access will be with a

scissor liS

16 7/18/18 J Stewart BNL

slide-17
SLIDE 17

CE cabling and tes,ng

  • Cabling through the cryostat

roof will take two shiSs. Two people will be on a scissor liS and two on the roof.

7/18/18 J Stewart BNL 17

slide-18
SLIDE 18

Assembly Labor Assumptions

Standard work week is considered to be four 10 hour days. Starting and ending at the headframe. The cage can carry 35 workers max, with 150 people underground per shift. This includes LBNF, SURF, Cryogenic construction, contractors as well so shift start times will have to be staggered. A standard work shift assumes ~70% efficiency

  • Ride underground, morning safety and assembly tasks meeting,

morning coffee break (20 min)- 1 hour

  • Lunch break including time to get to lunch area- 1 hour
  • Afternoon coffee break (20 min), end of the day cleanup and

ride to the surface- 1 hour This leaves us with a typical work day of ~3.5 hours in the morning and ~3.5 hours in the afternoon for each shift Scientific effort on off days needs negotiated.

slide-19
SLIDE 19

APA Assembly Area

APA Assembly Area: There are three work locations for the APAs in the

  • cleanroom. The crew size is 6 FTE, 2 are

crane operators

  • The APAs box is already in position in

the cart and they are lifted into position using the under-bridge crane with 2 FTE in the scissor lift, 2 on the ground and 2 FTE in the stair/work platform

  • The APA CE and PD cabling, joining the

two APAs together, cable tray installation, lifting the APA to DSS height, initial testing and cable management all take place over 3 shifts in this area

slide-20
SLIDE 20

APA Test Area
 Shuttle beam

APA Test Area-Shuttle Beam: Still working on the testing scope in the shuttle area Expect several shifts based on APA estimates.

Shuttle Beam with APA Curved rail for bringing APA into cryostat

S h u t t l e

  • B

e a m

slide-21
SLIDE 21

APA Top/Inside Cryostat Cable Area

APA Top/Inside Cryostat Cable Area: There are two work locations for this task which is expected to take two shifts per APA

  • pair. Most of the time:
  • A crew of 2 FTE are in a scissor lift inside the cryostat
  • 2 FTE are on the top if the cryostat pulling the cables up
slide-22
SLIDE 22

Summary

  • An initial draft plan for the installation is available.
  • This plan is being iterated with the consortia to be sure there is

consensus on the time an labor estimates.

  • It is understood that the start of the installation will go slow.
  • We need to discuss in a broader group the plan for testing.
  • Should we stop every so often to make the detector dark and

shielded to measure noise?

  • The organization of effort between TC and the consortia is still

being discussed.

slide-23
SLIDE 23

Backup

slide-24
SLIDE 24

24

DUNE Far Detector

CPA Unpacking & Assembly

Boxed CPA in position. 1/3 panel being raised from crate CPA panels placed into fixture Boxed CPA lowered into SAS and moved to Assy Fixture in CR 7/18/18 J Stewart BNL

slide-25
SLIDE 25

25

DUNE Far Detector

CPA Unpacking & Assembly

Assembled CPA panel placed onto North TCO Beam 7/18/18 J Stewart BNL

slide-26
SLIDE 26

26

DUNE Far Detector

Field Cage Unpacking & Assembly

FC Panels to be installed as the CP array hangs under the TCO beam

  • Crated FC Panels lowered into SAS

and moved into Clean Room 7/18/18 J Stewart BNL

slide-27
SLIDE 27

27

DUNE Far Detector

Upper Assembly Area

7/18/18 J Stewart BNL

slide-28
SLIDE 28

28

DUNE Far Detector

Outline of Clean Room

‘Dirty’ East Toaster Clean West Toaster & under Bridge South Utility Corridor North Utility Corridor SAS 7/18/18 J Stewart BNL

slide-29
SLIDE 29

29

DUNE Far Detector

Assembly Area – Elevation View

7/18/18 J Stewart BNL