Plans for installa,on
Jim Stewart BNL July 18 2018
Plans for installa,on Jim Stewart BNL July 18 2018 DUNE Far - - PowerPoint PPT Presentation
Plans for installa,on Jim Stewart BNL July 18 2018 DUNE Far Detector layout Bridge There is no rock pillar. Assembly work outside the cryostat occurs under the bridge. Detector Equipment is inserted Cryostat through a TCO Assembly
Jim Stewart BNL July 18 2018
DUNE Far Detector layout
Detector Cryostat Bridge Assembly area. There is no rock pillar. Assembly work outside the cryostat occurs under the bridge. Equipment is inserted through a TCO
7/18/18 J Stewart BNL 2
before we gain access to the cryostat.
parallel to detector #1
are spent seTng up the installaMon infrastructure.
roof will be in place.
internal switchyard.
installed.
3 7/18/18 J Stewart BNL
4
Status at Start of Detector Assembly
Footbridge Cryostat Access Door (~5 m Wide) Cavern Bridge (5m Wide) TCO Plug (2) Cave Crane Elevator CPA Fixture Movable Lift (4) APA Work Platforms Clean Room Boundary APA Crate Cart SAS Boundry Exit Stairs Dressing Room 7/18/18 J Stewart BNL
5
View Under the Bridge
Changing Room HV Assembly Area APA-CE Assembly Area Material Airlock
7/18/18 J Stewart BNL
6
DUNE Far Detector
Outline of Clean Room
Divider Curtain Clean West Toaster & under Bridge North Utility Corridor South Utility Corridor ‘Dirty’ East Toaster Divider Curtain around stairs Exit Stairway (dirty) Changing Room 7/18/18 J Stewart BNL
7
Plan View of Detector #1 Setup Under the bridge
Underground is either using the stairs or using the manliS.
used then one needs to walk through the Air Lock Area.
~30 people per shiS
7/18/18 J Stewart BNL
8
APA Delivery
1) Crated APA is positioned on Bridge, Cave Crane moved into position 2) Crate lifted & moved over SAS in East Toaster
Equipment enters from the North driS Not much space between the bridge and the APA boxes The guard rails need removed and people need to be Med off
boxes are in a crate.
acached
7/18/18 J Stewart BNL
9
APA are Rotated to Vertical in the Airlock
3) APA Crate on SAS Floor 4) Crated APA rotated to vertical position 7/18/18 J Stewart BNL
10
DUNE Far Detector
Panel Components Staged in SAS & Clean Room
A cart on rails could be used to slide the APA into the cleanroom
7/18/18 J Stewart BNL
11
DUNE Far Detector
APA Handling
Vertical APA Crate placed in cart APA Panels moved to Fixture
together
bridge to move equipment in the cleanroom
7/18/18 J Stewart BNL
APA side tubes in the cleanroom aSer the two APA are connected together.
Assembly Tower” is used to work
12 7/18/18 J Stewart BNL
beam are mounted while the APA are on the assembly fixture.
APA are liSed onto the transport rails.
APA along the rails
13 7/18/18 J Stewart BNL
14
DUNE Far Detector
APA Handling
10) APA panel ready to install in Cryostat, moved to APA-side of TCO track 7/18/18 J Stewart BNL
assembly staMon for debugging if needed.
15 7/18/18 J Stewart BNL
inside the cryostat are used to transport the APA to to the correct row of I- Beams for deployment.
APA at an intermediate posiMon to allow tesMng for several shiSs.
scissor liS
16 7/18/18 J Stewart BNL
roof will take two shiSs. Two people will be on a scissor liS and two on the roof.
7/18/18 J Stewart BNL 17
Standard work week is considered to be four 10 hour days. Starting and ending at the headframe. The cage can carry 35 workers max, with 150 people underground per shift. This includes LBNF, SURF, Cryogenic construction, contractors as well so shift start times will have to be staggered. A standard work shift assumes ~70% efficiency
morning coffee break (20 min)- 1 hour
ride to the surface- 1 hour This leaves us with a typical work day of ~3.5 hours in the morning and ~3.5 hours in the afternoon for each shift Scientific effort on off days needs negotiated.
APA Assembly Area: There are three work locations for the APAs in the
crane operators
the cart and they are lifted into position using the under-bridge crane with 2 FTE in the scissor lift, 2 on the ground and 2 FTE in the stair/work platform
two APAs together, cable tray installation, lifting the APA to DSS height, initial testing and cable management all take place over 3 shifts in this area
APA Test Area-Shuttle Beam: Still working on the testing scope in the shuttle area Expect several shifts based on APA estimates.
Shuttle Beam with APA Curved rail for bringing APA into cryostat
S h u t t l e
e a m
APA Top/Inside Cryostat Cable Area: There are two work locations for this task which is expected to take two shifts per APA
consensus on the time an labor estimates.
shielded to measure noise?
being discussed.
24
DUNE Far Detector
CPA Unpacking & Assembly
Boxed CPA in position. 1/3 panel being raised from crate CPA panels placed into fixture Boxed CPA lowered into SAS and moved to Assy Fixture in CR 7/18/18 J Stewart BNL
25
DUNE Far Detector
CPA Unpacking & Assembly
Assembled CPA panel placed onto North TCO Beam 7/18/18 J Stewart BNL
26
DUNE Far Detector
Field Cage Unpacking & Assembly
FC Panels to be installed as the CP array hangs under the TCO beam
and moved into Clean Room 7/18/18 J Stewart BNL
27
DUNE Far Detector
Upper Assembly Area
7/18/18 J Stewart BNL
28
DUNE Far Detector
Outline of Clean Room
‘Dirty’ East Toaster Clean West Toaster & under Bridge South Utility Corridor North Utility Corridor SAS 7/18/18 J Stewart BNL
29
DUNE Far Detector
Assembly Area – Elevation View
7/18/18 J Stewart BNL