Planning and NEPA for Freight and Passenger Rail Projects - - PowerPoint PPT Presentation

planning and nepa for freight and passenger rail projects
SMART_READER_LITE
LIVE PREVIEW

Planning and NEPA for Freight and Passenger Rail Projects - - PowerPoint PPT Presentation

Planning and NEPA for Freight and Passenger Rail Projects Presenters from FRAs Office of Railroad Policy and Development: Peter Schwartz, Senior Planner Andra Martin, Senior Environmental Protection Specialist A New Approach to Project


slide-1
SLIDE 1

Planning and NEPA for Freight and Passenger Rail Projects

Presenters from FRA’s Office of Railroad Policy and Development: Peter Schwartz, Senior Planner Andréa Martin, Senior Environmental Protection Specialist

slide-2
SLIDE 2

2

A New Approach to Project Development and NEPA

  • Getting projects ready for implementation
  • Substance stays the same – but refined sequencing/process

FASTER MORE EFFICIENTLY MORE SUCCESSFULLY LESS CONFUSION

slide-3
SLIDE 3

3

Project Lifecycle – Systems Planning to Project Implementation

Regional Rail Plans State Rail Plans Service Planning Preliminary Engineering Environmental Analysis Alternatives Analysis Final Design Construction

Begin NEPA Process NEPA Decision Application Project Identification

PROJECT DEVELOPMENT/NEPA SYSTEMS PLANNING PROJECT IMPLEMENTATION

slide-4
SLIDE 4

4

Existing Process – PRIIA to Present

  • Tied to $8B in ARRA funding appropriated

for project development and delivery

  • Focus on application requirements
  • Focus on eligibility
  • Focus on immediate-term pipeline
  • All project development occurring during

NEPA or after

  • All Alternatives Analysis during NEPA
  • Wide use of tiering NEPA documents
  • Focus on Service Development Plan

PRIIA, passed in 2008 ARRA, passed in 2009

slide-5
SLIDE 5

5

Existing Process – PRIIA to Present

Regional Rail Plans State Rail Plans Service Planning Preliminary Engineering Environmental Analysis Alternatives Analysis Final Design Construction

Begin NEPA Process NEPA Decision Application Project Identification

PROJECT DEVELOPMENT/NEPA SYSTEMS PLANNING PROJECT IMPLEMENTATION

slide-6
SLIDE 6

6

Existing Process – PRIIA to Present

Regional Rail Plans State Rail Plans Service Planning Preliminary Engineering Environmental Analysis Alternatives Analysis Final Design Construction

Begin NEPA Process NEPA Decision Application Project Identification

PROJECT DEVELOPMENT/NEPA SYSTEMS PLANNING PROJECT IMPLEMENTATION

Begin Tier 1 NEPA Process Tier 1 NEPA Decision Begin Tier 2 NEPA Process Tier 2 NEPA Decision

slide-7
SLIDE 7

7

Lessons from Existing Process

  • Vaguely defined projects at start of NEPA
  • NEPA timeline extended due to project development work
  • Development/screening of alternatives rushed
  • Grant-funded projects faced challenges
  • Projects implemented with Tier 1 NEPA documents
  • Planning projects for Tier 1 NEPA/SDP
  • Inefficiencies of concurrent NEPA and project development
slide-8
SLIDE 8

8

New Policy Priorities – Environmental Streamlining and One Federal Decision

  • MAP-21 (2012)
  • FEIS/ROD, Preferred Alternative in DEIS, (Sec. 1319)
  • FAST Act (2015)
  • Streamlining Sec. 11503
  • One Federal Decision (OFD) (2017) - E.O. 13807
  • 2-Year timeline for EIS
  • Early agency coordination
  • Mandated for “Major Infrastructure Projects”
  • OFD principles advised for other projects
slide-9
SLIDE 9

9

Improved Process for Project Development/NEPA

  • Enter into NEPA with a better-defined project
  • Strong preliminary Purpose and Need
  • Preliminary range of reasonable alternatives
  • Deemphasizing tiering except for most complex projects
  • Alternatives defined down to design option level prior to starting NEPA
  • Undertake all pre-NEPA work consistent with NEPA principles

and requirements

  • Completion of this “Pre-NEPA” project development represents the new

“tangible early milestone”

slide-10
SLIDE 10

10

Improved Process for Project Development/NEPA

Regional Rail Plans State Rail Plans Service Planning Preliminary Engineering Environmental Analysis Alternatives Analysis Final Design Construction

Begin NEPA Process NEPA Decision Application Project Identification

PROJECT DEVELOPMENT/NEPA SYSTEMS PLANNING PROJECT IMPLEMENTATION

Begin Tier 1 NEPA Process Tier 1 NEPA Decision Begin Tier 2 NEPA Process Tier 2 NEPA Decision

slide-11
SLIDE 11

11

Improved Process for Project Development/NEPA

Regional Rail Plans State Rail Plans Service Planning Preliminary Engineering Environmental Analysis Alternatives Analysis Final Design Construction

Begin NEPA Process NEPA Decision Application Project Identification

PROJECT DEVELOPMENT/NEPA SYSTEMS PLANNING PROJECT IMPLEMENTATION

slide-12
SLIDE 12

12

Benefits of Improved Process

  • Allows NEPA to focus on NEPA – not on basic project development
  • Allows NEPA to be completed more quickly
  • Less basic project development work holding up the process
  • Caveat: Pre-NEPA project development and Alternatives Analysis needs to be

examined during NEPA scoping

  • More clarity about project for public and agencies at start of NEPA
  • Less tiering means less risk
  • More efficient use of resources

Begin NEPA Process NEPA Decision Application Project Identification

slide-13
SLIDE 13

13

Challenges to Improved Process

  • How to fund pre-NEPA Project Development
  • Need for early coordination
  • FRA
  • Other Agencies
  • Less use of tiering means more work needed before “green light”
  • Communicating about improved process
slide-14
SLIDE 14

14

  • FHWA – Planning-Environmental Linkages (PEL)
  • Started from too little Planning/NEPA integration
  • Aims to make project planning/project development

work usable in NEPA

  • Arrived at similar solution to FRA
  • FTA – “Project Development Phase”
  • Still looking for some project development prior to

NEPA, despite elimination of Alternatives Analysis phase

  • FRA still not going so far as allowing pre-NEPA

identification of preferred alternative

Consistency with other USDOT processes

slide-15
SLIDE 15

15

Other Environmental Streamlining Activities

  • MAP-21
  • NEPA Assignment (Sec. 1313)
  • FRA can use FHWA/FTA CEs (Sec. 1314)
  • FAST Act (11503)
  • 23 CFR 771
  • 1999 FRA Procedures
  • New CEs
  • Section 106
  • Program comment
  • “Property-based approach”
  • More information:

www.fra.dot.gov/environment

slide-16
SLIDE 16

CONTACT US

Federal Railroad Administration 1200 New Jersey Avenue, SE Washington, DC 20590 For more information visit us at www.fra.dot.gov