pipeline
play

pipeline community information sessions july /august 2018 - PowerPoint PPT Presentation

crib point pakenham pipeline community information sessions july /august 2018 July/August 2018 Agenda and protocols July/August 2018 Agenda APA presentation (30-40 mins) Who is APA Key concerns The Project Pipeline


  1. crib point pakenham pipeline community information sessions july /august 2018 July/August 2018

  2. Agenda and protocols July/August 2018

  3. Agenda • APA presentation (30-40 mins)  Who is APA  Key concerns  The Project  Pipeline construction overview  Approvals process and overview of environmental investigations • Questions and Answers (50-60 mins) • Follow up one-on-one questions and discussions with public and APA and AGL project team members 10/08/2016 3 July/August 2018

  4. Protocols All pipeline topics available for comment and • questions AGL project elements can be directed to AGL during • the Q&A session, though today is principally about the pipeline Highly technical questions may be answered briefly • and followed up with written advice to questioner One person speaking at a time. Please state your • name when asking a question Q&A will be facilitated by APA Communications • advisor to ensure everyone gets a turn – please wait for microphone (if necessary) so everyone can hear questions and comments Don’t intend to get into detailed questions about • individual property matters at a public session This presentation will be placed on the APA website • following the information session Please register your details with AGL representatives • if you wish to be placed on AGL Crib Point Project mailing list 10/08/2016 4 July/August 2018

  5. about APA July/August 2018

  6. Gas transmission 15,134 kms of transmission pipelines, including 7,500 kms in the East Coast Grid. Gas distribution We manage 28,424 kms of gas mains & pipelines, serving 1.3 million gas consumers 6 July/August 2018

  7. key items to be addressed environmental referrals pipeline route selection pipeline impacts on Ramsar wetlands July/August 2018

  8. project overview July/August 2018

  9. crib point pakenham pipeline Overview Pipeline overview: Pipeline Project is between existing Length Approx. 55km • jetty facilities at Crib Point (south of Hastings) and Pakenham Material Epoxy coated high strength steel line pipe Diameter 600mm Project supports AGL’s proposal to • import natural gas (Crib Point Nominal Project) Approx. 750 TJ/day (bi-directional) capacity Generally 1,200mm (deeper at crossing of Burial Depth AGL responsible for gas importation • third party infrastructure and waterways) activities while APA provides Permanent Nominally 15 metres (reduced at areas of necessary connection to the Easement ecological sensitivity or other constraint) Victorian Transmission System End of line above-ground facilities (Crib Point and east of Pakenham) as well as Facilities two(2) mainline valves (contained within Targeting construction during • easement) summer / autumn of 2019 /2020 Strictly in accordance with the latest version Design Principles of AS2885 – Pipelines Gas and Liquid Petroleum 9 July/August 2018

  10. APA relationship with AGL APA has entered into a development • agreement with AGL to undertake development of the pipeline APA is the proponent for the pipeline • and will own and operate the asset The AGL Crib Point Project and the APA • Pipeline Project are subject to further project approvals and Final Investment Decisions Pipeline asset can also facilitate (in • addition to AGL gas importation proposal)  Supply of gas to new and existing developments along pipeline route  Allowance for future offtakes – townships, developments and subdivisions etc. 10/08/2016 10 July/August 2018

  11. regulatory approvals July/August 2018

  12. environmental referrals • APA and AGL currently preparing environmental referrals (State and Commonwealth)  Likely submission of these to regulators in mid to late- August 2018 We are • The Projects generally have separate temporal here and spatial impacts  Pipeline impacts during construction and FSRU during operation Mid-late  Pipeline impacts land based and FSRU primarily August marine impacts 2018 • Recent public interest in joint assessment of Projects to allow a full and transparent assessment • APA and AGL confirm that cumulative and Sept/Oct indirect impacts of the developments will be 2018 assessed as part of each environmental referral  A specific report will be submitted with the referrals identifying the cumulative and indirect impacts of Yes No (EES is (EES is not the other Project Required) Required)  Ensure the full impacts of the development are assessed together No Assessments completed to date indicate that the (EES is not Required • but conditions must combined effects would likely not require APA or be met) AGL to require formal assessment under EE Act or EPBC Act 10/08/2016 12 July/August 2018

  13. approvals and consultation process Consultation Approvals late initial feasibility investigations project announcement 2017 Initial route option study Project announced and collateral on APA • • Approval of pipeline consultation website • plan Initial stakeholder and landowner contact • program Early route refinement and environmental landowner and stakeholder consultation 2018 – investigations now Voluntary and ministerial consent Detailed meetings with landowners and • • to enter land for survey occupiers – survey access and land use Detailed field survey program Landowner and stakeholder briefings • • Preparation of technical reports Community drop-in sessions and meetings • • Target: environmental referrals and approval application public exhibition and submission August applications period 2018 State and Commonwealth (EPBC Public exhibition of EPBC and pipeline • • and EES referrals) licence application – EES if required Pipeline licence application Opportunity for stakeholders to lodge a • • submission Target: completion of regulatory approvals ongoing stakeholder consultation mid- Decision by DELWP – pipeline Easement negotiations • • 2019 licence and environment and Detailed community briefings – lead-up to • safety documentation construction 13 July/August 2018

  14. pipeline construction overview July/August 2018

  15. crib point pakenham pipeline - proposed route 15 July/August 2018

  16. construction - overview • Pipeline construction methods dependent on location and constraints  Open agricultural land  Sensitive environmental and vegetated areas  Urban and industrial land  Crossing of major infrastructure (e.g. road, rail) • APA construction planning taking into account both seasonal and project delivery timeframes  Reputable and experienced construction contractor  Receiving advice from contractors in relation to design, scheduling, cost and constructability assessments • Construction corridor of 30m (15m permanent and 15m temporary) width required for safe and efficient pipeline construction  Additional requirements for truck turn-arounds, stockpiling and lateral access  Width can be reduced in areas of constraint  Alternative construction methods (e.g. horizontal directional drill, boring) 10/08/2016 16 July/August 2018

  17. construction - typical layout Open-cut 20m 10m HDD 10/08/2016 17 July/August 2018

  18. construction - street works • APA proposed an alignment that utilises the verge and service road of Frankston Flinders Road through Hastings Between Reid Parade and Graydens Road  • Complex route selection and congested existing linear corridors • Consultation undertaken with council and VicRoads to determine initial feasibility • Proposing detailed service proving program to verify final pipeline alignment • Pipeline construction typical of civil roadworks program 18 - 36 metres of pipe laying per day  Restrict to small section of pipeline and associated  traffic impact at any one time • Detailed engagement with the public and notifications as APA proceeds closer to construction 10/08/2016 18 July/August 2018

  19. construction - timelapse video https://youtu.be/-a8GyaZKyaU 10/08/2016 19 July/August 2018

  20. construction - reinstatement of land Construction Pipeline corridor during construction (January 2017) Rehabilitation Pipeline corridor after rehabilitation (July 2017) 10/08/2016 20 July/August 2018

  21. technical investigations July/August 2018

  22. pipeline route selection Terrain  Accessibility  Public and worker  safety High density land  use Length  No. of landowners /  parcels Environment –  Reserves, Conservation Areas High-value  agricultural land Heritage  Linear co-location  Operational  challenges 10/08/2016 22 July/August 2018

  23. supplementary route analysis 10/08/2016 23 July/August 2018

  24. technical investigations - overview • Various technical investigations have been completed to support APA’s design and regulatory approvals processes • These investigations include:  Ecology – terrestrial and aquatic  Heritage – Aboriginal and European  Acid Sulfate Soil assessment  Hydrogeological assessment  Noise emissions  Greenhouse gas emissions  Landscape and visual amenity  Safety hazards • The purpose of these investigations are to avoid or minimise potential environmental and community impacts • Assessments are near finalisation and will inform APA’s environmental referrals. • Final drafts of relevant reports will be placed on APA’s website 10/08/2016 24 July/August 2018

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend