crib point pakenham pipeline community information sessions july /august 2018
July/August 2018
pipeline community information sessions july /august 2018 - - PowerPoint PPT Presentation
crib point pakenham pipeline community information sessions july /august 2018 July/August 2018 Agenda and protocols July/August 2018 Agenda APA presentation (30-40 mins) Who is APA Key concerns The Project Pipeline
July/August 2018
July/August 2018
3 10/08/2016
July/August 2018
4 10/08/2016
questions
the Q&A session, though today is principally about the pipeline
and followed up with written advice to questioner
name when asking a question
advisor to ensure everyone gets a turn – please wait for microphone (if necessary) so everyone can hear questions and comments
individual property matters at a public session
following the information session
if you wish to be placed on AGL Crib Point Project mailing list
July/August 2018
July/August 2018
6
Gas distribution We manage 28,424 kms of gas mains & pipelines, serving 1.3 million gas consumers Gas transmission 15,134 kms of transmission pipelines, including 7,500 kms in the East Coast Grid.
July/August 2018
July/August 2018
July/August 2018
9
Overview
Pipeline overview: Length
Material Epoxy coated high strength steel line pipe Diameter 600mm Nominal capacity
Burial Depth Generally 1,200mm (deeper at crossing of third party infrastructure and waterways) Permanent Easement Nominally 15 metres (reduced at areas of ecological sensitivity or other constraint) Facilities End of line above-ground facilities (Crib Point and east of Pakenham) as well as two(2) mainline valves (contained within easement) Design Principles Strictly in accordance with the latest version
Petroleum
July/August 2018
10 10/08/2016
July/August 2018
July/August 2018
12 10/08/2016
referrals (State and Commonwealth)
August 2018
and spatial impacts
during operation
marine impacts
Projects to allow a full and transparent assessment
indirect impacts of the developments will be assessed as part of each environmental referral
identifying the cumulative and indirect impacts of the other Project
assessed together
combined effects would likely not require APA or AGL to require formal assessment under EE Act or EPBC Act
July/August 2018
Yes (EES is Required) No (EES is not Required) No (EES is not Required but conditions must be met)
We are here Mid-late August 2018 Sept/Oct 2018
13
late 2017 initial feasibility investigations
plan project announcement
website
program Early 2018 – now route refinement and environmental investigations
to enter land for survey
landowner and stakeholder consultation
Target: August 2018 environmental referrals and approval applications
and EES referrals)
application public exhibition and submission period
licence application – EES if required
submission Target: mid- 2019 completion of regulatory approvals
licence and environment and safety documentation
construction
July/August 2018
July/August 2018
15
July/August 2018
10/08/2016 16
location and constraints
Open agricultural land Sensitive environmental and vegetated areas Urban and industrial land Crossing of major infrastructure (e.g. road, rail)
seasonal and project delivery timeframes
Reputable and experienced construction contractor Receiving advice from contractors in relation to design, scheduling, cost and constructability assessments
15m temporary) width required for safe and efficient pipeline construction
Additional requirements for truck turn-arounds, stockpiling and lateral access Width can be reduced in areas of constraint Alternative construction methods (e.g. horizontal directional drill, boring)
July/August 2018
17 10/08/2016
10m 20m
July/August 2018
10/08/2016 18
and service road of Frankston Flinders Road through Hastings
linear corridors
VicRoads to determine initial feasibility
verify final pipeline alignment
program
traffic impact at any one time
notifications as APA proceeds closer to construction
July/August 2018
19 10/08/2016
July/August 2018
https://youtu.be/-a8GyaZKyaU
20 10/08/2016
July/August 2018
July/August 2018
10/08/2016 22
July/August 2018
23 10/08/2016
July/August 2018
10/08/2016 24
to support APA’s design and regulatory approvals processes
minimise potential environmental and community impacts
environmental referrals.
website
July/August 2018
10/08/2016 25
smaller trees and patches of native vegetation of different quality
may be retained – i.e. reducing vegetation impact
Creek
Bandicoot, Lewin’s Rail, Cattle Egret and Eastern Great Egret
method (HDD) or minimised by reduction of the ROW
Environment and Energy in August for assessment by the Federal Minister – The expectation is that our construction impact is unlikely to trigger a
‘Controlled Action’.
proposed environmental commitments and mitigation that will accompany our EPBC referral
July/August 2018
10/08/2016 26
locations
construction methodology
boundary
affect the ecological character and ecosystem processes
Source: DELWP, 2017
July/August 2018
10/08/2016 27
Greenhouse Gas Emissions Assessment
facilities at Crib Point and Pakenham
annum – below the Environment Effects Act trigger of 200,000 tonnes of CO2 equivalent per annum
Noise Assessment
model for our Crib Point and Pakenham Facilities as design
in consideration the cumulative impact from the FSRU and United facility at the Jetty
guidelines and in consultation with the affected nearby residents
The GHG Emissions and Noise Assessment reports will form part of the Environment Effects Referral for consideration by the Minister for Planning.
July/August 2018
10/08/2016 28
there is very little visual impact of the pipeline
maintain a visual reminder of the location of the pipeline
Standard (AS2885)
third party interference
the potential cumulative effect of the FSRU
located immediately adjacent to Pakenham East Rail Depot and the Princes Freeway – There is minimal visual impact due to its location and setting
July/August 2018
29
Where can I find more information? A range of detailed information is available on the project website including:
https://www.apa.com.au/about-apa/our-projects/crib-point-to-pakenham-pipeline/
July/August 2018
30
APA – Crib Point Pakenham Pipeline Freecall: 1800 531 811 Email: cribpointpakenham@apa.com.au AGL – Crib Point Project https://www.agl.com.au/cribpoint DELWP – Pipeline Regulation Division https://www.energy.vic.gov.au/pipelines Energy Safe Victoria www.esv.vic.gov.au
July/August 2018